<br />GOLF COURSE CONSTRUCTION STATUS <br />CARTER CONSTRUCTION <br />Should be complete this week with all the sprigging (will hold of <br />until Thursday and then work till finish sprigging). Clean-up <br />taking place now. <br />ALLGOOD CONSTRUCTION <br />Effluent System - Complete except for final walk-thru <br />Tunnel - Lacking: <br />1. Setting of pumps to drain tunnel <br />2. Lights - (HL & P is setting poles this week) <br />3. Gates - being made <br />4. Hydromulching the sides <br />Wharton-Weems opening - Brush road and stripe. <br />CLUB HOUSE <br />Design completed - Construction drawings in process <br />• MAINTENANCE BUILDING <br />Design build contract in draft stage <br />ENTRANCE ROAD AND PARKING <br />Plans complete - 1 week <br />Revision - 1 week <br />Go for bids - January <br />Pre-Bid - After January 1st <br />Award bid - January 25, 1988 <br />PERSONNEL <br />Introduce Alex Osmond - Golf Course Manager <br />• <br />