S ITEMS FOR GOLF COURSE CONTRACTOR TO COMPLETE <br />1) Finish drainage areas which have been identified by Jay Riviere <br />and City Staff. <br />2) Some fairways and green slopes will need some more 419 grass <br />added. All of these areas ~•rill be done after we can spray the <br />whole course and begin to eliminate the weeds. By doing this we <br />will be able to identify the weak areas and be more specific on <br />where to apply the grass. <br />3) There are a few areas in the rough that need to be seeded. These <br />areas are the drainage areas that are being worked on and some <br />mounds. <br />4) Fix or patch cart paths damaged by construction. <br />• 5) Repair leaking weir on Teo. 2 <br />6) Install main controller for water system. (Can't be done until <br />maintenance building is complete). <br />After contractor is satisfied with his work for completion of the <br />course, a final inspection will be made by Jay Riviere and staff. <br />AO/nb <br />• <br />