Preliminary Construction Cost Estimate <br /> Proposed Truck Routes <br /> April 3, 2011 <br /> Qty Unit Unit Cost Cost <br /> West M Street <br /> Concrete Pavement : <br /> Remove Existing Pavement 1442 SY $7.00 $10,095.56 <br /> Lime Stabilization 36 Ton $75.00 $2,704.17 <br /> Fly Ash Stabilization 14 Ton $145.00 $2,091.22 <br /> 10 Inch Rienforced Concrete Pavement 1442 SY $36.00 $51,920.00 <br /> Total $66,810.94 <br /> Aspahlt Pavement: <br /> Remove Existing Pavement 1442 SY $7.00 $10,095.56 <br /> Lime Stabilization 36 Ton $75.00 $2,704.17 <br /> Fly Ash Stabilization 14 Ton $145.00 $2,091.22 <br /> Limestone Base 811 Ton $30.00 $24,337.50 <br /> 1.5 inch HMAC 105 Ton $75.00 $7,909.69 <br /> Subtotal $47,138.13 <br /> Maintenance (resurface every 7 years) 7 EA $7,909.69 $55,367.81 <br /> Total $102,505.94 <br /> West G Street <br /> Concrete Pavement : <br /> Remove Existing Pavement 1442 SY $7.00 $10,095.56 <br /> Lime Stabilization 36 Ton $75.00 $2,704.17 <br /> Fly Ash Stabilization 14 Ton $145.00 $2,091.22 <br /> 10 Inch Rienforced Concrete Pavement 1442 SY $36.00 $51,920.00 <br /> Total $66,810.94 <br /> Aspahlt Pavement: <br /> Remove Existing Pavement 1442 SY $7.00 $10,095.56 <br /> Lime Stabilization 36 Ton $75.00 $2,704.17 <br /> Fly Ash Stabilization 14 Ton $145.00 $2,091.22 <br /> Limestone Base 811 Ton $30.00 $24,337.50 <br /> 1.5 Inch HMAC 105 Ton $75,00 $7,909.69 <br /> Subtotal $47,138.13 <br /> Maintenance (resurface every 7 years) 7 EA $7,909.69 $55,367.81 <br /> Total $102,505.94 <br />