Waterline & Sanitary Sewer Crossing Relocation Along Farrington
<br />Paskey Horseshoe
<br />Paskey UNIT EXTENDED Horseshoe UNIT EXTENDED
<br />Item DescriptionCOSTCOSTCOSTCOST
<br />Item no.UOMQTY
<br />SECTION "A" - Waterline (Base Bid)
<br />1MobilizationLS1$34,850.00$34,850.00$10,000.00$10,000.00
<br />2Traffic ControlLS1$11,797.00$11,797.00$5,000.00$5,000.00
<br />3Remove and Dispose existing 12" PVC waterlineLF40$35.00$1,400.00$35.00$1,400.00
<br />4Remove existing concrete pavementSY3300$0.99$3,267.00$25.00$82,500.00
<br />5Remove and dispose existing 8" A.C. waterlineLF220$35.00$7,700.00$35.00$7,700.00
<br />68" PVC C-900 waterline including excavation and beddingLF1362$92.51$125,998.62$118.00$160,716.00
<br />712" PVC C-900 wterline including excavation and beddingLF231$113.08$26,121.48$125.00$28,875.00
<br />812" 45-degree bend with Mega Lug Lok restraing (MJ)EA10$717.00$7,170.00$800.00$8,000.00
<br />98" 45-degree bend with Mega Lug Lok Restraing (MJ)EA44$477.00$20,988.00$700.00$30,800.00
<br />102" Sample TapsEA15$239.00$3,585.00$1,000.00$15,000.00
<br />11Plug existing 6" waterlineEA12$275.00$3,300.00$500.00$6,000.00
<br />12Plug existing 8" waterlineEA18$375.00$6,750.00$500.00$9,000.00
<br />13Plug existing 12" waterlineEA3$475.00$1,425.00$500.00$1,500.00
<br />146" to 8" PVC reducerEA5$183.00$915.00$500.00$2,500.00
<br />156" to 8" PVC AC adaptorEA5$313.00$1,565.00$500.00$2,500.00
<br />168" PVc-A"C adaptorEA3$413.00$1,239.00$500.00$1,500.00
<br />17tie toexisting 6" WL (wet connect)EA5$3,379.00$16,895.00$2,000.00$10,000.00
<br />18tie-in to existing 8" waterline (wet connection)EA7$3,579.00$25,053.00$2,500.00$17,500.00
<br />19tie to existing 12" WL (wet connect)EA5$5,111.00$25,555.00$3,000.00$15,000.00
<br />2012" x 12" T.S. & V.EA1$5,748.00$5,748.00$5,850.00$5,850.00
<br />218" x 8" T.S. & V.EA1$3,468.00$3,468.00$5,000.00$5,000.00
<br />2212" x 8" T.S. & V.EA11$3,888.00$42,768.00$5,000.00$55,000.00
<br />23Temporary asphalt pavementSY3300$0.99$3,267.00$45.00$148,500.00
<br />2412" plug & clampEA1$475.00$475.00$1,000.00$1,000.00
<br />258" plug and clampEA7$375.00$2,625.00$800.00$5,600.00
<br />266" plug and clampEA5$275.00$1,375.00$500.00$2,500.00
<br />$385,300.10$638,941.00
<br />Section "A" base bid
<br />Paskey Horseshoe
<br />Paskey UNIT EXTENDED Horseshoe UNIT EXTENDED
<br />COSTCOSTCOSTCOST
<br />Section "B" - Sanitary Sewer (Base Bid) UOMQTY
<br />1Remove existing concrete pavementSY140$10.00$1,400.00$25.00$3,500.00
<br />2temporary asphalt pavementSY140$20.80$2,912.00$45.00$6,300.00
<br />3remove and dispose Ex 8" San. Sew.LF60$15.00$900.00$30.00$1,800.00
<br />4plug existing 8" san. Sew.EA8$475.00$3,800.00$500.00$4,000.00
<br />8" SDR 26 ASTM D 2241 San. Swr. Including excavation and bedding
<br />(all depths)
<br />5LF177$252.16$44,632.32$90.00$15,930.00
<br />10" SDR 26 ASTM D 2241 San. Swr. Including excavation and beddin
<br />(all depths)
<br />6LF177$256.00$45,312.00$92.00$16,284.00
<br />7Std manholeEA5$2,725.00$13,625.00$5,000.00$25,000.00
<br />8extra depth manholeVF34$172.00$5,848.00$300.00$10,200.00
<br />9proposed drop structureEA6$1,711.00$10,266.00$1,200.00$7,200.00
<br />$128,695.32$90,214.00
<br />Section "B" base bid
<br />Paskey Horseshoe
<br />Paskey UNIT EXTENDED Horseshoe UNIT EXTENDED
<br />COSTCOSTCOSTCOST
<br />SECTION "C" - Extra Work (base bid)UOMQTY
<br />2412" G.V. with boxEA2$5,252.70$10,505.40$3,000.00$6,000.00
<br />258" G.V. with boxEA2$4,499.70$8,999.40$2,000.00$4,000.00
<br />266" G.V. with boxEA2$3,174.40$6,348.80$1,200.00$2,400.00
<br />$25,853.60$12,400.00
<br />Section "C" base-bid
<br />Total project cost - base bid
<br />$539,849.02$741,555.00