Laserfiche WebLink
NEPA PROCESS AND SCHEDULE <br />REVISED DEIS SCHEDULE <br />08/08/01 <br />Process Step <br />Date <br />Application received <br />October 8, 1998 <br />Application determined complete for processing <br />October 19, 1998 <br />Determination that EIS required <br />December 4, 1998 <br />Selection of third party contractor <br />March 30, 1999 <br />Published notice of intent to conduct EIS in Federal Register <br />May 24, 1999 <br />Conducted public scooping meeting <br />September 17, 1999 <br />Conduct environmental analysis <br />Conducting Analysis <br />Publish draft EIS and Release Permit Application for <br />November 7, 2001 <br />public comment <br />Public workshop on DEIS <br />November 21, 2001 <br />Public workshop on DEIS <br />December 5, 2001 <br />Public hearing on draft EIS and Permit Application <br />December 11, 2001 <br />Close of comment period <br />February 5, 2002 <br />Develop final EIS <br />February 6, 2002 <br />Publish final EIS for public comment <br />May 3, 2002 <br />Complete record of decision and permit decision <br />July 1, 2002 <br />• <br />8.1 <br />