a <br />• <br />x ~ _ .. <br />CHANGE ORDER <br />N0. Two <br />DATED: September 16, 1981 <br />Owner's Proj ect No . <br /> <br />Engineer's Project No. 74-1068-03 _ <br />EPA Project No. C-481176-03-0 <br />Project _Contract III -Lift Station Facilities <br />Owner City of La Porte <br />Contractor Big M Constructors, Inc. Contract Date December 22, 1980 <br />Contract For Construction of lift station facilities at Fairmont Park and the intersection <br />of Fairmont Parkway and Southern Pacific Railroad <br />To: Big M Constructors, Inc. <br />Contractor <br />You are directed to make the changes noted below in the subject contract: <br />Owner City of La Porte <br />By <br />James R. Hudgens, City Manager <br />Date September 1981 <br />Nature of the Change - Installation of two electrical poles, temporary connection of new <br />pumps to old discharge line at Fairmont Park Lift Station, repair of Entex Metering <br />Station cathodic protection system, and extension of contract time from 60 working days to <br />~0 working days <br />closures: <br />The changes result in the following adjustment of Contract Price and Contract Time: <br />Contract Price Prior to This Change Order <br />$ 193,121.00 <br />Net (Increase) (IX~~~~ Resulting from this Change Order $ 3.344.80 <br />Current Contract Price Including This Change Order <br />• <br />$ 196,465.80 <br />Page 1 of 2 Pages <br />,~ l <br />