~ • <br />PUNCH LIST <br />LA PORTS SEWAGE TREATMENT PLANT <br />November 15, 1982 <br />Electrical <br />1. Schedule on all electrical panels must be corrected to reflect actual control. <br />2. Furnish "as builts" of complete plant, both buildings and yard wiring. <br />3. Furnish wiring diagrams of MCC-A and MCC-B. <br />4. Get controls of belt press system to operate properly. Sludge transfer <br />pumps must operate independently of press. Remote speed controls are <br />working backwards. <br />5. Recheck lift station level float switches. They are not at the proper <br />elevations and may not be hanging in the proper sequence. <br />6. ~~l clarifier scum airlift solenoid switching is not working on automatic. <br />7. ~~1 sludge pump motor has damaged cooling fan and must be replaced. <br />• g, Install lightening arrestor. <br />9. Install single phase protection device. <br />• <br />