<br />CITY OF LA PORTE <br />2005 SIDEWALK IMPROVEMENT PROJECT <br />CLP PROJECT 2005-4501 <br />BID OPENING: MARCH 14, 2005 <br />BID TABULATION <br /> <br /> E.L. HARRIS III CONSTRUCTION BROOKS CONCRETE STATEWIDE TREE SERVICE <br /> INC. INC. <br />NO. I ITEM UNIT QUANTITY UNIT AMOUNT I TOTAL PRICE UNIT AMOUNT I TOTAL PRICE UNIT AMOUNT I TOTAL PRICE <br /> voncrete sidewalk placement: four inches thick, <br />1 poured with 3000 psi concrete (min). Complete in SY 755 $ 29.25 $ 22,083.75 $ 38.50 $ 29,067.50 $ 27.81 $ 20,996.55 <br /> place <br /> Removal and disposal of eXisting concrete sidewalk. <br />2 Excavated sidewalk to become property of SY 849 $ 1.10 $ 933.90 $ 18.00 $ 15,282.00 $ 27.81 $ 23,610.69 <br /> Contractor to be disposed of in a legal manner. <br />3 Concrete Type "A" wheel chair ramps. In EA 16 $ 1,250.00 $ 20,000.00 $ 450.00 $ 7,200.00 $ 597.00 $ 9,552.00 <br />accordance with details and completion place. <br />4 Adjustment of existing valve boxes. Complete in EA 3 $ 75.00 $ 225.00 $ 200.00 $ 600.00 $ 500.00 $ 1,500.00 <br />place. <br />5 Adjustment of existing manholes and manhole EA 1 $ 100.00 $ 100.00 $ 400.00 $ 400.00 $ 772.50 $ 772.50 <br />covers. Complete in place. <br /> TOTAL BASE BID $ 43,242.65 $ 52,149.50 $ 55,659.24 <br /> SUPPLEMENTAL BID ITEMS <br />S-1 Extra bank sand (ordered by City). Complete in CY 25 $ 50.00 $ 1,250.00 $ 21.00 $ 525.00 $ 65.00 $ 1,625.00 <br />place. <br />S-2 Strip sodding as directed by City and in accordance SY 50 $ 10.00 $ 500.00 $ 6.00 $ 300.00 $ 4.25 $ 212.50 <br />with Specification 00112. Complete in place. <br />S-3 Extra cement stabilized sand (ordered by City). . CY 50 $ 50.00 $ 2,500.00 $ 35.00 $ 1,750.00 $ 85.00 $ 4,250.00 <br />Complete in place. <br /> TOTAL OF SUPPLEMENTAL $ 4,250.00 $ 2,575.00 $ 6,087.50 <br />TOTAL BID (CALCULATED) $ 47,492.65 $ 54,724.50 $ 61,746.74 <br />TOTAL BID (SUBMITTED) $ 47,592.65 $ 55,124.50 $ 62,519.24 <br />