• <br />CITY OF LA PORTE <br />INTER-OFFICE MEMORANDUM <br />T0: Ja Owen, i Manager DATE: March 8, 1981+ <br />FROM: r L. ector of Public Works <br />SUBJECT: C we ergency Rehabilitation <br />The attached report from Turner Collie & Braden is a summary of the work <br />completed on the Catlett sewer rehabilitation project. The report expresses <br />that problems were encountered that were not expected from the initial survey <br />of the project. Excess work and cost was also due to unseasonal rainfall <br />and Hurricane "Alicia". <br />The original estimate of cost from Turner Collie & Braden on the emergency <br />rehabilitation of the Catlett Sewer Main, was $125,000. At closing out of <br />the project account the actual amount spent on the rehabilitation was <br />$186,425.83. Engineering fees and on site inspection fees were $1+6,000 as <br />originally proposed. <br />If you should have any questions, please advise. <br />JLH/me <br />attachment <br />