HomeMy WebLinkAboutO-1995-2013
.
.
ORDINANCE NO. 95- 2013
AN ORDINANCE APPROVING AND AUTHORIZING AN ENGINEER AGREEMENT
BETWEEN THE CITY OF LA PORTE AND JIHMY D. DUNHAM, P.E., TO DESIGN
REPAIRS AND IMPROVEMENT TO THE FAIRKONT PARK ELEVATED WATER STORAGE
TANK; APPROPRIATING NOT TO EXCEED $17,835.00 TO FUND SAID CONTRACT;
MAKING VARIOUS FINDINGS AND PROVISIONS RELATING TO THE SUBJECT;
FINDING COMPLIANCE WITH THE OPEN MEETINGS LAW; PROVIDING AN
EFFECTIVE DATE HEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE:
section 1. The City Council hereby approves and authorizes
the contract, agreement, or other undertaking described in the
title of this ordinance, in substantially the form as shown in the
document which is attached hereto and incorporated herein by this
reference. The City Manager is hereby authorized to execute such
document and all related documents on behalf of the City of La
Porte. The City Secretary is hereby authorized to attest to all
such signatures and to affix the seal of the City to all such
documents. The City Council appropriates the sum not to exceed
$17,835.00 from Fund 003 to fund said contract.
section 2. The city Council officially finds, determines,
recites, and declares that a sufficient written notice of the date,
hour, place and subject of this meeting of the City Council was
posted at a place convenient to the public at the City Hall of the
City for the time required by law preceding this meeting, as
required by the Open Meetings Law, Chapter 551, Texas Government
Code; and that this meeting has been open to the public as required
by law at all times during which this ordinance and the subject
matter thereof has been discussed, considered and formally acted
upon. The City Council further ratifies, approves and confirms
such written notice and the contents and posting thereof.
.
.
ORDINANCE NO. 95- 2013
PAGE 2
Section 3. This Ordinance shall be effective from and after
its passage and approval, and it is so ordered.
PASSED AND APPROVED, this 23rd day of January, 1995.
CITY OF LA PORTE
By:
t~?7/~f?l~-
~o man L. Malo e;
Mayor
ATTEST:
s:,,~ ~
Sue Lenes,
City Secretary
.
e
LETTER OF AGREEMENT
This is an Agreement made as of J;MJJ4.ry...2t9~S between the City of
La Porte (Owner) and Jimmy D. Dunham, P. . (Engineer).
owne: inte~ds for Engineer to provide professional engineering
serv~ces ~n connection with the preparation of plans and
specifications, bidding and awarding a contract, and construction
phase services, including on-site inspectional services, for the
repair work to Owner's 500,000 gallon elevated water storage tank
located in Fairmont Park (Project).
Required work is detailed in Reports of Inspection prepared by
Engineer and dated September 22, 1993. A general description of
the Project is the repainting of the inside and outside of the
water storage structure at Fairmont Park as well as certain
structural repairs and modifications.
SCOPE OF BASIC ENGINEERING SERVICES:
Engineer agrees to provide the following professional services:
Desiqn Phase
Meet with Owner to discuss proposed project, and reinspect Project
to insure the conditions remain the same as when last inspected in
1993. Engineer will discuss with Owner the condition of the tower,
applicable AWWA specifications, TNRCC regulations, recommended
paint system(s), as well as any options available for coatings and
other aspects of the Project. At that time, Owner will make any
special requirements known to Engineer.
Provide two (2) draft sets of Plans and specifications to Owner
within thirty (30) days of Notice to Proceed, and meet with Owner
to discuss scope of work and any changes requested by Owner.
Finalize Plans and Specifications, based on meeting and written
comments from Owner, within thirty (30) days and provide two (2)
sets of final plans and specifications with updated cost estimate.
Secure all regulatory approvals necessary.
Biddinq Phase
Provide and distribute copies of plans and specifications to
interested bidders.
Assist the Owner with preparation of legal advertizement, and
advertize the work directly to selected bidders and at least two
(2) contractor clearing houses.
.
e
LETTER OF AGREEMENT
Page 2
Attend and conduct a prebid meeting at Owner's offices, and clarify
any questions or concerns from interested contractors. Prepare and
distribute any addenda necessary to clarify questions raised at
prebid meeting.
Attend bid opening, prepare bid tabulation, and provide written
recommendation for award of bid to contractor.
Construction Phase
Attend and conduct pr~construction conference with Owner and
Contractor prior to beginning construction.
Provide construction phase services, including interpreting
contract documents, process contractor pay requests, prepare change
orders as required, and certify completion of contract.
Receive, evaluate and approve all submittals and shop drawing
required by the contract documents.
Make two (2) inspections to ensure compliance with the
specifications. One will be a preconstruct ion conference. The
second will be a final inspection to ensure completion of work.
Provide and interpret all necessary tests of spent blasting
material to ensure compliance with lead regulations.
COMPENSATION FOR BASIC SERVICES:
The above basic services (design, bidding and construction phase)
shall be compensated at the lump sum price of eleven thousand eight
hundred thirty five dollars ($11,835). This sum shall become due
in accordance with the following schedule:
Design
50% due when draft documents provided
25% due when final documents provided
Design Subtotal
$5,917.50
2.958.75
$ 8,876.25
Bidding
10% due when bid recommendation provided
$ 1,183.50
Construction
10% due during construction
5% due upon final acceptance
Construction Subtotal
$1,183.50
591.75
Total Basic Engineering Fees
$ 1.775.25
$11,835.00
LETTER OF AGREEMENT
.
.
paqe 3
SCOPE OF INSPECTION SERVICES
Upon receipt of written Notice to Proceed from the Owner, Engineer
agrees to provide the following inspection services:
Periodic inspection of the work, in addition to the basic services
outlined above, to ensure compliance with the contract documents
and quality workmanship.
Owner will be notified of all site inspections and may accompany
Engineer. All inspections shall be conducted by the Engineer,
Jimmy D. Dunham, P.E., unless otherwise approved by the Owner.
A total of twelve (12) site visits are estimated, at approximately
eight (8) hours each.
COMPENSATION FOR INSPECTION SERVICES
All inspection work outlined in the Scope of Inspection Services
shall be compensated at a rate of sixty dollars ($60) per hour,
portal to portal. This rate includes all expenses, including
milage, meals and lodging required.
Fees will be invoiced monthly, based on actual hours worked, and
will not exceed six thousand dollars ($6,000) without prior written
approval from owner.
ACCEPTED:
ie~
'~Y\D. Dunham, P.E.
g~neer
G<~ T: l~
Robert T. Herrera
City Manager
ATTEST:
~~
City Secretary