HomeMy WebLinkAboutO-1998-2289
.
e
ORDINANCE NO. 98- 2289
ORiGINAL
AN ORDINANCE APPROVING AND AUTHORIZING A CONTRACT
BETWEEN THE CITY OF LA PORTE AND TRIMBLE AND STEPHENS
CONSTRUCTION SERVICES, INC. FOR CONSTRUCTION OF A
PARKING LOT AND RESTROOM/PAVILION FOR SEABREEZE PARK;
APPROPRIATING $259,000.00 PLUS A CONTINGENCY OF
$12,950.00, TO FUND SAID CONTRACT; MAKING VARIOUS
FINDINGS AND PROVISIONS RELATING TO THE SUBJECT; FINDING
COMPLIANCE WITH THE OPEN MEETINGS LAW; PROVIDING AN
EFFECTIVE DATE HEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA
PORTE:
Section 1. The City Council hereby approves and authorizes the
contract, agreement, or other undertaking described in the title of this
ordinance, in substantially the form as shown in the document which is
attached hereto and incorporated herein by this reference. The City
Manager is hereby authorized to execute such document and all related
documents on behalf of the City of La Porte. The City Secretary is hereby
authorized to attest to all such signatures and to affIX the seal of the City
to all such documents. City Council appropriates the sum of
$259,000.00 plus a contingency of $12,950.00 from Capital
Improvement Fund 015 to fund said contract.
Section 2. The City Council officially finds, determines, recites,
and declares that a sufficient written notice of the date, hour, place and
subject of this meeting of the City Council was posted at a place
convenient to the public at the City Hall of the City for the time required
by law preceding this meeting, as required by the Open Meetings Law,
Chapter 551, Texas Government Code; and that this meeting has been
e
e
ORDINANCE NO. 98- 2289
open to the public as required by law at all times during which this
ordinance and the subject matter thereof has been discussed, considered
and formally acted upon. The City Council further ratifies, approves and
confrrms such written notice and the contents and posting thereof.
Section 3. This Ordinance shall be effective from and after its
passage and approval, and it is so ordered.
PASSED AND APPROVED, this 12th day of October 1998.
CIYYF LA PORTE ~
{i1~~if/&
Mayor
By:
ATIEST:
~wJ1~&A1I111
M a Gillett
City Secretary
C!;QJ
Knox W. Askins,
City Attorney
RAN D ALL. 0 R T E R FIE L D ARC. T E C T S, INC.
1006 South Shore Drive
Clear Lake Shores, Texas 77565
SEABREEZE PARK - BID TABULATION
October 1, 1998
(281) 334-5535
Fax: (281) 334-2933
NOTE All
h
d d h
d
b'd
Se
be 8 1998
contractors sown atten e t e man atory pre- 1 meettn~ on :ptem r '.
Architect's Comex Co. Criscon Co. Trimble & D.T. Clear Lake
Estimate Stephens Construction Const.
1. Site Preparation, $ 22,500 $25,000 No Bid $26,400 $31,000 No Bid
Excavation & Grading
2. Site Utilities $ 17,500 $15,000 $16,500 $25,000
3. Concrete Paving, $ 75,000 $90,000 $79,000 $64,000
Curbing & Walks
4. Electrical Service $ 7,000 $14,000 $11,500 $19,000
5. Restroom/Pavilion $ 135,000 $143,000 $139,000 $141,900
Payment & Performance $ 8,000 $7,200 $5,600 $5,500
Bond
TOTAL BASE BID $ 265,000 $294,200 $278,000 $286,400
Days
Alternate #1:
Deduct metal roofing and $(10,000) $(14,000) $(19,000) $(12,900)
flashing, install asphalt
composition roofing
shingles
Architect's Firemen Patak & Moore & Steven Hill
Estimate Const. Poole Moore Const.
$ 22,500 $70,000 No Bid $26,975 $23,324
1. Site Preparation,
Excavation & Gradin~
2. Site Utilities $ 1 7,500 $12,000 $13,246 $21,000
3. Concrete Paving, $ 75,000 $75,000 $61,400 $100,558
Curbing & Walks
4. Electrical Service $ 7,000 $18,000 $11,000 $20,900
5. Restroom/Pavilion $ 135,000 $165,000 $- $156,268
Payment & Performance $ 8,000 $10,000 $6,010 $7,950
Bond
TOTAL BASE BID $ 265,000 $350,000 $333,754 $330,000
Days
Alternate #1:
Deduct metal roofing and $(10,000) $(13,000) $(6,200)
flashing, install asphalt
composition roofing
shin~les
RANDALL-'ORTERFIELD ARC1tTECTS, INC.
1006 South Shore Drive
Clear Lake Shores, Teus 77565
(281) 334-5535
Fax: (281) 334-2933
October 5, 1998
Mr. Doug Kneupper
City of laPorte
P.O. Box 1115
laPorte, TX 77572
Re: Seabreeze Park - Phase I
Dear Mr. Kneupper.
Please find enclosed a copy of the bid tabulation from six of the nine contractors of record for
the above referenced project.
The apparent low bidder is Trimble & Stephens in the amount of $278,000 for the base bid,
Architect's estimate of $265,000. Please note the deduct alternate #1 amount of $19,000 from
Trimble & Stephens which would bring the project within $4,000 or approximately 1 ~% over
the Architect's estimate.
We recommend the following items for consideration and approval:
1. Apparent low bidder is responsible and willing to enter into a contract for the amount as
bid.
2. Accept the deduct alternate for asphalt roof shingles in lieu of metal roofing. The contractor
claims the metal roof warranty will not be available for structures on the waterfront.
The Phase I project should be substantially complete in five (5) months.
Phase II, Corps permit and drawings, should be complete in four (4) months to allow one (1)
month for bidding and review. This schedule will allow Phase II to commence immediately
upon Phase I completion.
Sincerely,
~
Robert A. (Bob) Randall - Architect
RAR/ cs
Enclosure
e Seabreeze Park - Phase I e
Parking Lot and Restroom/Pavilion
eLP #96-5201
Advertisin2
The Bayshore Sun - September 6 & September 13, 1998
Bid Notice faxed to Chamber of Commerce September 14, 1998
Contractors Notified
Force Corporation
PO Box 1079
La Pone, TX 77571
D.T. Construction
107 W. First, Ste. 207
Humble, TX 77338
Follis Construction
111 N. Broadway
La Pone, TX 77571
Clear Lake Construction
1909 Marvin Circle
Seabrook, TX 77586
Moore & Moore General Contractors
PO Box 1517
La Pone, TX 77572-1517
Firemen Construction
PO Box 96647
Houston, TX 77213
Derk Harmsen Construction
2820 Center
Deer Park, Texas 77536
Patak & Poole
4111 Rice Drier
Houston, TX 77005
Comex Corporation
PO Box 862
Deer Park, TX 77536
Steven Hill Construction
7782 Hammerly
Houston, TX 77055
Trimble & Stephens Construction Services
4701 Gulf Freeway F-1
La Marque, TX 77568
Criscon
PO Box 1426
Clute, TX 77531
Planholders
Trimble & Stephens Construction Services
4701 Gulf Freeway F-l
La Marque, TX 77568
Firemen Construction
PO Box 96647
Houston, TX 77213
Comex Corporation
PO Box 862
Deer Park, TX 77536
Clear Lake Construction
1909 Marvin Circle
Seabrook, TX 77586
Moore & Moore General Contractors
PO Box 1517
LaPorte, TX 77572-1517
DT Construction
107 W. First, Ste. 207
Humble, TX 77338
Steven Hill Construction
7782 Hammerly
Houston, TX 77055
Patak & Poole
4111 Rice Drier
Houston, TX 77005
Criscon
PO Box 1426
Clute, TX 77531