RESOLUTION NO. 79-1
.' .
PROJECT SCHEDULE RESOLUTION
Whereas, the City of La Porte
Legal Name ot Appl1cant
has made application to the Texas Department of Water Resources and
the Environmental Protection Agency for a Federal grant pursuant to
the Federal Water Pollution Control Act Amendments of 1972, Public
Law 92-500, and the rules and regulations thereto;
Now Therefore, Be It Resolved by the above named applicant
that the application for which Federal grant ~ssistance has been
requested pursuant to the Federal Water Pollution Control Act
Amendments of 1972, Public Law 92-500, will be constructed to com-
pletion in accordance with the laws, rules, and regulations and
with the following project schedule.
General Information
Date
Date applicant's share
of project costs will
be available.
Step 1
Step 2
Step 3
r.nmplptpd
Nnw AV;:til;:tnlj:ll
Pebruarv 1979
Date site(s) for project
facilities will be available.
Nnw a.vailablp
pro;ect Schedule
Item
Calendar Days
STEP 1
A. Infiltration/Inflow Analysis
(with Evaluation Survey Plan of Study if
required) completed & submitted to State
after Step 1 grant award.
comp 1 eted days
B. Infiltration/Inflow Evaluation Survey (if
required) completed & submitted to State
after grant amendment for Survey.
comp 1 eted day s
e
e
C.
Application for Waste Control
Permit (if required) made no later than
after Public Hearing notice for Facility
Plan is issued.
cornol eted days
..
D. Final Environmental Assessment and
Facility Plan (including time for draft
reports, advertisement & hearing)
completed and submitted to the State
after Step 1 grant award.
camp 1 eted days
STEP 2
A. User Charge System and Industrial
Cost Recovery System (if required)
developed and submitted to the State
after Step 2 grant a~ard.
90
days
.'
B.
Preliminary Plan of Operation (if required)
completed and submitted to the State
after Step 2 grant award.
30
days
C. Final Plans and Specifications,
completed and submitted to State
after Step 2 grant award.
270
days
STEP 3
A. Advertise for Construction Bids within 45 days
after authorization to advertise for
bids has been issued.
B. Submit Bid Opening Documents within 30 days
after authorization to advertise for
bids has been issued.
- C. Award of Construction Contract within 7 days
after authorization to award the contract
has been issued.
D. Initiation of Construction within 30 days
after the award of the contract.
TDWR-0570
Page 2 of 2
-
e
e
E. ) Complete Construction within
after initiation of construction.
540
days
Be it further resolved, that the above named applicant
understands that the above project schedule must be approved by
the Texas Department of Water Resources and the Environmental
Protection Agency, and that once a project schedule has been
approved, no changes will be authorized without first receiving
approval of the change from the Texas Department of Water Resources
and the Environmental Protection Agency.
~ Passed, approved, and adopted this
10
day of
,
January
19 79 .
Sig~ature~f~ial
J. J. Meza. Mayor
Governing Body
~~~~.... ~ ~ ~~
I:~)~:'<:-:.
~ ,~
7 w..... ~
~ . ~
..
""
,;;
~
~'
.,
TDWR-0570
Page 3 of 3
-tS-eal-)-
',A ......<
/'"'-
,ATTES'T:
_ '. t '::'~,
, '~':;-:' .~.;-..~.,="'"
~~4