REQUEST FOR CITY COUNCIL AGENDA ITEM
Requested By:
3 2004
Appropriation
Agenda Date Requested:
Source of Funds: Various
Department:
Account Number: Various
Report:
Resolution:
Ordinance:
x
Amount Budgeted: $4,470,000
Exhibits: Ordinance
Amount Requested: $2,933,294
Exhibits: Engineer's Recommendation and Bid Tabulation
Budgeted Item: YES
Exhibits Canada Road Cost Allocation and Budl!et
SUMMARY & RECOMMENDATION
Sealed bids from pre-qualified contractors were received on November 15,2004. Nine contractors pre-
qualified under the terms of Section 2-106 of the city's Code of Ordinances. Seven contractors attended
the mandatory pre-bid meeting, with six submitting a bid. Low bid was submitted by Angel Brothers
Enterprises, L TD for a total cost, including Alternates 1 & 2, of $2,793,614. Alternates 1 & 2 represent
costs for sidewalks, which Harris County will not participate in. A five percent (5%) contingency is
recommended, in the amount of$139,680.
Funding for the Project comes from three different sources, as follows:
. CLP 4B (Streets/Drainage) Project No. GEN766
. CLP Utility CIP Fund (Utilities) Project No. UTL899
La Porte Subtotal
. Harris County (1/2 of all costs except utilities and sidewalks)
Total available Budget
$1,900,000
700,000
$2,600,000
1,870,000
$4,470,000
The overall estimated expenditures are on the attached Cost Estimate. Costs for the construction and
engineering are based on existing contracts, as well as the proposed award of the construction and
inspection contracts. Outstanding estimated costs include pipeline adjustments. Adjustments are
complete, however actual costs have not been provided. Based on conversations with the two pipeline
companies, actual costs were well below estimates.
Action Required bv Council: Approve an ordinance authorizing the City Manager to execute a contract
with Angel Brothers Enterprises, L TD in the amount of $2,793,614, and authorize a contingency of
$139,680.
Approved for City Council Aeenda
lJJ bt(j)/J ~du~
I1ebra Feazelle, City anag
IJ -2 ,-ot{
Date
ORDINANCE NO. 2004-~1q1
AN ORDINANCE APPROVING AND AUTHORIZING A CONTRACT BETWEEN THE CITY
OF LA PORTE AND ANGEL BROTHERS ENTERPRISES, LTD., FOR IMPROVEMENTS
TO CANADA ROAD, APPROPRIATING $2,793,614.00 PLUS A CONTINGENCY OF
$139, 680 . 00, TO FUND SAID CONTRACT, MAKING VARIOUS FINDINGS AND
PROVISIONS RELATING TO THE SUBJECT, FINDING COMPLIANCE WITH THE
OPEN MEETINGS LAW, AND PROVIDING AN EFFECTIVE DATE HEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE:
Section 1. The City Council hereby approves and authorizes
the contract, agreement, or other undertaking described in the
title of this ordinance, a copy of which is on file in the office
of the city Secretary. The City Manager is hereby authorized to
execute such document and all related documents on behalf of the
City of La Porte.
The City Secretary is hereby authorized to
attest to all such signatures and to affix the seal of the City to
all such documents.
City Council appropriates the sum of
$2,263,370.50 plus a contingency of $113,168.00 from City of La
Porte Fund 015 - Project No. 766, and the sum of $530,243.50 plus
a contingency of $26,512.00 from Fund 003 - Project No. 899, to
fund said contract.
Section 2. The City Council officially finds, determines,
recites, and declares that a sufficient written notice of the date,
hour, place and subject of this meeting of the City Council was
posted at a place convenient to the pUblic at the city Hall of the
City for the time required by law preceding this meeting, as
required by the Open Meetings Law, Chapter 551, Texas Government
Code; and that this meeting has been open to the pUblic as required
by law at all times during which this ordinance and the subject
matter thereof has been discussed, considered and formally acted
upon.
The City Council further ratifies, approves and confirms
such written notice and the contents and posting thereof.
Section 3. This Ordinance shall be effective from and after
its passage and approval, and it is so ordered.
PASSED AND APPROVED, this 13th day of December, 2004.
By:
CITY OF LA PORTE
kt.K~
Alton E. Porter
Mayor
ATTEST:
\,.~ O. fiLUiJ
Mart a A. Gille t
City Secretary
APokw~
Knox W. AskJ.ns
City Attorney
2
..
I ,I", I ", ~
Freese
Nichols, Inc.
Engineers
Environmental Scientists
Architects
2010 East Broadway
Pearland, TX 77581-5502
281/485-2404
281/485-4322 fax
www.freese.com
November 17, 2004
FNIOI-525
Mr. Steve Gillett
Director of Public Works
City of La Porte
2963 North 23rd Street
La Porte, Texas 77571
Re: Canada Road
Dear Steve:
On November 15,2004, six (6) bids were opened for the referenced project. Bids were checked
and tabulated. The low bidder is Angel Brothers Enterprises, L TD with a base bid of
$2,745,314. Their Alternate Bids 1 and 2 prices prices for sidewalks are $25,460 and $22,840
respectively. Therefore, the total bid including Alternate bids is $2,793,614. Enclosed are ten
(10) copies of bid tabulation sheet.
Angel Brothers Enterprises, L TD is a responsible and responsive company with experience in
this type of work. We have worked with them on previous projects in other cities and they were
previously prequalified. Therefore, we recommend award of this contract to Angel Brothers
Enterprises, LTD. Depending on funds availability and City's desire, award can be made for
base bid or with Alternate bids included..
We are looking forward to the successful implementation of this project. Please call me in can
be of service to you.
Sincerely,
~~---
Mehran (Ron) Bavarian, P .E.
Associate
Houston Area Manager
Attachment:
1: LPTO 1-525GillellS.ltr
CANADA ROAD BID TABULATION
11/15/2004
ENG. ESTIMATE ANGEL BROTHERS BEYER CONST. CONRAD CONST. HUFF&MITCHEl REYTEC CONST. TRIPLE B SERVo TEXAS STERLING
A. PAVING $ 1,639,020.00 $ 1,623,830.00 $ 1,776,775.00 $ 1,635,342.00 $ 1,629,115.00 $ 1,688,860.00 $ 1,991,295.00
B. DRAINAGE $ 664,947.50 $ 541,240.50 $ 763,215.00 $ 658,998.00 $ 669,144.50 $ 621,853.00 $ 847,734.00
C. WATERLINE $ 147,120.00 $ 95,237.00 $ 137,927.00 $ 127,210.00 $ 145,025.00 $ 93,501.00 $ 147,340.00
D. SEWER $ 523,450.00 $ 435,006.50 $ 558,391.00 $ 524,958.00 NO-BID $ 706,003.25 $ 470,953.00 $ 530,066.00
E. EXTRA WORK $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00
TOTAL BASE $ 3,024,537.50 $ 2,745,314.00 $ 3,286,308.00 $ 2,996 508.00 $ 3,199,287.75 $ 2,925,167.00 $ 3,566,435.00
AL TERNA TE 1 $ 35,100.00 $ 25,460.00 $ 22,800.00 $ 22,800.00 $ 22,800.00 $ 26,600.00 $ 42,560.00
AL TERNA TE 2 $ 19,350.00 $ 22,840.00 $ 22,200.00 $ 20,400.00 $ 18,600.00 $ 23,275.00 $ 35,890.00
LOW BID
STREET/DRAINAGE I $ 2,408,417.50 I $ 2,263,370.50 I
ITOTAL UTILITY
I $ 670,570.00 I $
$ 3,078,987.50 $
530,243.50 I
2,793,614.00
TOTAL
COST ESTIMATE FOR CONSTRUCTION OF CANADA ROAD
Exhibit A
Subtotal
5% Contingencies
Total Construction
Cost
$ 1,623,830.00
$ 541,240.50
$ 50,000.00
$ 25,460.00
$ 22,840.00
$ 2,263,370.50
$ 113,168.53
$ 2,376,539.03
Joint Venture 50% Eligible Items
Harris County City of La Porte
$ 811,915.00 $ 811,915.00
$ 270,620.25 $ 270,620.25
$ 25,000.00 $ 25,000.00
$ $ 25,460.00
$ $ 22,840.00
$ 1,107,535.25 $ 1,155,835.25
$ 55,376.76 $ 57,791.76
$ 1,162,912.01 $ 1,213,627.01
RoadwaylDrainage
Pavin
Draina e
Extra Work
Alternate 1 Sidewalk
Alternate 2 Sidewalk
Waterline Installation
Sewerline and Lift Station Installation
Subtotal
5% Contingencies
Total Utilities
Engineering, Survey & Geotech
Freese & Nichols Phase I Desi n $ 192,295.00 $ 96,147.50 $ 96,147.50
Freese & Nichols Phase II Desi n $ 46,375.00 $ 23,187.50 $ 23,187.50
Freese & Nichols Utilit Desi n $ 43,395.00 $ $ 43,395.00
Freese & Nichols Construction Phase I $ 26,305.00 $ 13,152.50 $ 13,152.50
Freese & Nichols Construction Phase II $ 2,275.00 $ 1,137.50 $ 1,137.50
Freese & Nichols Utility Construction Phase $ 11,575.00 $ $ 11,575.00
Pro'ect Representative - Street/Draina e3 $ 77,042.00 $ 38,521.00 $ 38,521.00
Pro'ect Representative - Uti lit Installation $ 13,213.00 $ $ 13,213.00
Materials Testing - Street/Drainage 4 $ 42,680.00 $ 21,340.00 $ 21,340.00
Materials Testing - Utility Installation $ 7,320.00 $ $ 7,320.00
Total Engineering $ 462,475.00 $ 193,486.00 $ 268,989.00
, Represents 65.58% of Estimated Cost
2 Represents 50% of Estimated Cost
3 Represents 85.36% of Estimated Inspection Cost ($100,000)
4 Represents 85.36% of Estimated Testing Costs