REQUEST FOR CITY COUNCIL AGENDA ITEM
Agenda Date Requested: September 10.2007
Requested By: Wayne s~tf-
Department: Planning
Appropriation
Source of Funds: CDBG
Account Number 032-9090-519-5110
Report: ~ Resolution:
Ordinance: X
Amount Budgeted: $241,950
Exhibits: Ordinance & Bid Tabulation CLP #07-4502
Amount Requested: $94,420
Exhibits:
Budgeted Item: YES
SUMMARY & RECOMMENDATION
Harris County Community & Economic Development Department previously awarded the City a
CDBG grant to extend and pave North 7th Street from Madison to the "E" Street ROW as well as
a linear connectivity amenity along the "E" Street ROW from North 8th to North 2nd Street. The
original grant included utility extensions as well. However, it was decided by staff that Public
Works would extend the waterline and it is complete and in place. The original amount awarded
by the county was $196,950.
As part of the City's leveraging funds, the City surveyed the project area and the Engineering
Division designed and bid the project. On the first bidding period, the City received three (3)
bids with a low bid of$114,030 from D & W Contractors:
. Paving
. Drainage
. Waterline
. Contingencies/Other Work
$83,460.00
$960.00
$19,610.00
$10,000.00
The disparity in the above numbers with the bid tabulation is due to the contractor not including
the addendum price for the manipulation of the lime sub grade in the amount of $7,000 in the
total bid price. Also, as previously noted, the waterline portion of the contract has already been
constructed by Public Works. City staffhas notified the contractor and it is mutually agreed that
the waterline portion of the project will be omitted from the contract, reducing the contract price
to $94,420.
Budgeted funds include a $45,000 award from SETH for additional pedestrian amenities along
the "E" Street ROW in conjunction with the CDBG project. An additional contract will be
awarded at a later date for the linear connectivity amenity.
Staff recommends awarding the bid to D & W Contractors for the paving and drainage ofN. 7th
Street.
Action Required bv Council:
1. Approve an Ordinance to award the bid in the amount of $94,420 to D & W Contractors for the
paving and drainage of North 7th Street with the remaining budgeted funds to be used for linear
connectivity amenities in the "E" Street ROW.
2. Direct Staff to issue a notice to commence construction.
Approved for City Council Al!enda
riot /0 '{
Dat~ .
ORDINANCE NO. 2007- 3 oJ f)
AN ORDINANCE APPROVING AND AUTHORIZING AN AGREEMENT
BETWEEN THE CITY OF LA PORTE AND D & W CONTRACTORS, INC.,
FOR PAVING AND EXTENSION OF NORTH 7th STREET; APPROPRIATING
$94,420.00 TO FUND SAID CONTRACT; MAKING VARIOUS FINDINGS AND
PROVISIONS RELATING TO THE SUBJECT; FINDING COMPLIANCE WITH
THE OPEN METTINGS LA W;PROVlDING AN EFFECTIVE DATE HEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE:
Section 1. The City Council hereby approves and authorizes the contract,
agreement, or other undertaking described in the title of this ordinance, a copy of which
is on file in the office of the City Secretary, as set forth in this section. The City Manager
is hereby authorized to execute such document and all related documents on behalf of the
City of La Porte. The authority given to the City Manager to execute the contract or
agreement approved by this ordinance shall expire sixty (60) days from its passage and
approval. The City Secretary is hereby authorized to attest to all such signatures and to
affix the seal of the City to all such documents. City Council appropriates the sum not to
exceed $94,420.00 from the City of La Porte Grant Fund No. 032, to fund said contract.
Section 2. The City Council officially finds, determines, recites and declares that
a sufficient written notice of the date, hour, place and subject of this meeting of the City
Council is posted at a place convenient to the public at the City Hall of the city for the
time required by law preceding this meeting, as required by the Chapter 551, Texas
Government Code; and that this meeting has been open to the public as required by law at
all times during which this ordinance and the subject matter thereof has been discussed,
considered and formally acted upon. The City Council further ratifies, approves and
confirms such written notice and the contents and posting thereof.
Section 3 This Ordinance shall be effective from and after its passage and
approval, and it is so ordered.
Passed and Approved this lorL day of Sept' n1~007.
CITY OF LA PORTE
~ty~
By:
Alton E. Porter, Mayor
ATTEST:
JJ1~~~UC~
Martha A. Gillett, City Se retary
APPROVED:
M~T~
Clark T. Askins, Assistant City Attorney
BID #07023 NORTH 7TH STREET EXTENSION
TEXCOR
D&W CONSTRUCTION MAR-CON
DESCRIPTION CONTRACTORS SERVICES SERVICES, LLC
Base Bid $107,030.00 $131,337.01 $139,532.50
Total Base Bid $107,030.00 $131,337.01 $139,532.50