HomeMy WebLinkAboutO-2008-3116 Teamwork Construction-linear connectivity amenities in the āEā Street ROW
12
--
,~
--------
REQUEST FOR CITY COUNCIL AGENDA ITEM
Requested By: Tim Tietjens
Agenda Date Requested:
er 22 2008
Appropriation
Source of Funds: CDBG
Department: Planning
Account Number 032-9090-519-5110
Report: X Resolution:
Ordinance: X
Amount Budgeted: $168,200.68
Exhibits: Ordinance & Bid Tabulation CLP #08-5202
Amount Requested: $121,230.68
Exhibits:
Budgeted Item: YES
SUMMARY & RECOMMENDATION
Harris County Community & Economic Development Department previously awarded the City a
CDBG grant to extend and pave North 7th Street from Madison to the "E" Street ROW as well as
a linear connectivity amenity along the "E" Street ROW from North 7th to North 2nd Street. The
North 7th Street project was completed in FY 2007. The City now is ready to construct the linear
connectivity amenity and has recently bid the project.
As part of the City's leveraging funds, the Engineering Division designed and bid the project.
As part of the project the City would also purchase the drinking fountains as well as provide all
the water taps. On the first bidding period, the City received five (5) bids with a low bid of
$96,177.00 from Teamwork Construction:
. Paving
. Landscaping
. Irrigation
$87,352.00
$8,825.00
not bid
An addendum was sent out prior to the bid opening specifying that the irrigation portion of the
project would be omitted from the bid package owing to the confusion on the part of the
contractors as to how to bid the irrigation portion. Brooks Concrete submitted the second low
bid at $130,370.25. This price included the irrigation.
Staff recommends the best use of funds is to award low bid on Sections A & B to Teamwork
Construction. We can write up some specifications for the irrigation and send out a quote form
to irrigation firms and the bidder list for E Street. This should provide accurate quotes to award
the irrigation separately. Weare seeking funding in the amount of twenty five percent over the
above referenced low bid in order to purchase the drinking fountains for the project as well as
provide more landscaping. Therefore, Staff recommends $121,230.68 for construction, which is
well within the budget amount. Change orders will be issued to the Contractor for more
landscaping and a separate contract will be awarded to an irrigation specialist. The requested
amount is one hundred percent of the remaining budget the City has with Harris County.
Action Required bv Council:
1. Approve an Ordinance to award the bid in the amount of$121,230.68'to Teamwork Construction
for linear connectivity amenities in the "E" Street ROW.
Direct Staff to issue a notice to commence construction.
ORDINANCE NO. 2008- 3 II ~
AN ORDINANCE APPROVING AND AUTHORIZING AN AGREEMENT
BETWEEN THE CITY OF LA PORTE AND TEAMWORK CONSTRUCTION
LINEAR CONNECTIVITY AMMENITIES IN THE "E" STREET ROW;
APPROPRIA TING $121,230.68 TO FUND SAID CONTRACT; MAKING
VARIOUS FINDINGS AND PROVISIONS RELATING TO THE SUBJECT;
FINDING COMPLIANCE WITH THE OPEN METTINGS LAW; PROVIDING
AN EFFECTIVE DATE HEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE:
Section 1. The City Council hereby approves and authorizes the contract,
agreement, or other undertaking described in the title of this ordinance, a copy of which
is on file in the office of the City Secretary, as set forth in this section. The City Manager
is hereby authorized to execute such document and all related documents on behalf of the
City of La Porte. The authority given to the City Manager to execute the contract or
agreement approved by this ordinance shall expire sixty (60) days from its passage and
approval. The City Secretary is hereby authorized to attest to all such signatures and to
affix the seal of the City to all such documents. City Council appropriates the sum not to
exceed $121,230.68 from the City of La Porte Grant Fund No. 032, to fund said contract.
Section 2. The City Council officially finds, determines, recites and declares that
a sufficient written notice of the date, hour, place and subject of this meeting of the City
Council is posted at a place convenient to the public at the City Hall of the city for the
time required by law preceding this meeting, as required by the Chapter 551, Texas
Government Code; and that this meeting has been open to the public as required by law at
all times during which this ordinance and the subject matter thereof has been discussed,
considered and formally acted upon. The City Council further ratifies, approves and
confirms such written notice and the contents and posting thereof
Section 3 This Ordinance shall be effective from and after its passage and
approval, and it is so ordered.
Passed and Approved this ;);1D day of SetJ/ I , 2008.
CITY OF LA PORTE
~t7~
By:
Alton E. Porter, Mayor
ATTEST:
~~~~
APPROVED:
tI~ T ,f~
Clark T. Askins, Assistant City Attorney
BID TABULATION #08109 E STREET PEDESTRIAN PARK
TEAMWORK BROOKS MAR-CON SOUTHERN IDEAL
DESCRIPTION Unit QTY Construction Concrete Inc. Services Customs Inc. Contracting
Services Services
Section A - Sidewalk Drainage & Park Appurtenances
1. Mobilization for Entire Contract LS 1 $4,000.00 $2,800.00 $17,000.00 $28,000.00 $15,000.00
2. 6' Sidewalk SF 13525 $4.10 $4.95 $4.50 $10.00 $8.00
3 Culverts (all sizes) per linear foot LF 80 $45.00 $70.00 $36.00 $120.00 $300.00
4. Benches EA 5 $1,000.00 $900.00 $1,350.00 $1,800.00 $3,800.00
5. Trash Cans EA 5 $600.00 $750.00 $940.00 $1,800.00 $3,000.00
6. Drinking Fountains SY 2 $350.00 $650.00 $757.00 $250.00 $2,100.00
7. Hydro-mulch Seeding ACRE 0.5 $1,800.00 $1,800.00 $2,800.00 $5,280.00 $12,000.00
8. Clearing & Grubbing 100'STA 16.33 $150.00 $50.00 $155.00 $300.00 $2,000.00
9. Remove Existing Concrete Sidewalk SF 9000 $1.00 $1.00 $1.30 $2.00 $3.00
10. Remove Debris Clearing & Grubbing CY 50 $50.00 $35.00 $30.00 $110.00 $60.00
SUB - TOTAL ITEM A $87,502.00 $98,215.25 $110,837.65 $222,389.00 $254,060.00
Section B- Landscapes
1. Mexican Fan Palm, 30 gallon EA 7 $375.00 $340.00 $550.00 $880.00 $350.00
2. Dallas Red Crepe Myrtle, 10 gallon EA 10 $200.00 $235.00 $360.00 $960.00 $300.00
3. Basham Crepe Myrtle (lavender) 25 gallon EA 6 $450.00 $375.00 $550.00 $830.00 $350.00
4. Pecan, 25 gallon EA 4 $100.00 $360.00 $560.00 $855.00 $400.00
5. Red Oak, 26 gallon EA 9 $100.00 $345.00 $550.00 $855.00 $400.00
6. Bald Cypress, 25 gallon EA 2 $100.00 $315.00 $475.00 $855.00 $500.00
SUB - TOTAL ITEM B $8,825.00 $12,155.00 $18,890.00 $33,565.00 $13,750.00
Alternate Bid #1- Irrigation System
1. Irrigation System no bid $20,000.00 $8,000.00 no bid $30,000.00
GRAND TOTAL $96,327.00 $130,370.25 $137,727.65 $255,980.00 $281,560.00
Information reflects pricing only and other factors may be considered during the evaluation process
Updated 08-28-08