MINUTES OF THE DRAINAGE AND FLOODING COMMITTEE MEETING
JANUARY 13, 2020
The Drainage and Flooding Committee of the City of La Porte met on Monday, January 13, 2020, at the City Hall
Council Chambers, 604 West Fairmont Parkway, La Porte, Texas, at 5:00 p.m. to consider the following items of
business:
Committee Members present: Jay Martin, Chuck Engelken, Danny Earp, (Alternate Gillett available if needed)
Committee Members absent: None
Council-appointed officers present: Corby Alexander, City Manager; Lee Woodward, City Secretary
1. CALL TO ORDER - Chairman Martin called the meeting to order at 5:00 p.m.
2. PUBLIC COMMENTS (Generally limited to five minutes per person, in accordance with state law, the time may be
reduced if there is a high number of speakers or other considerations.
3. STATUTORY AGENDA
(a) Presentation, discussion, and possible action to approve the minutes of the December 9, 2019 meeting.
\[Chairman Martin\]
Committee member Engelken moved to approve the minutes; the motion was adopted, 3-0.
(b) Presentation, discussion, and possible action regarding the status of current drainage projects. \[Lorenzo
Wingate, Assistant Director of Public Works\]
Mr. Wingate said he had reached out to Harris County Precinct 2 concerning the use of additional funding they had
as a match for Bayside Terrace, and that he is also working with Halff Associates as consultants. Chair Martin
ascertained there should be a proposal by the February Committee meeting. Wingate shared that F-216, Phase III
was in the same situation.
Wingate noted that the executed contract between the City and Harris County, for a grant allocation of approximately
$3.4 million (with no match required) in Harvey money, was received today for the Northside Drainage Improvement
Project, adding that the City intends to pay for engineering services and the grant will be used for construction. He
said that the County has selected a consultant for the F-101 project and plans to get approval to execute the
at the next Harris County Commissioners Court meeting. Wingate noted the desilting of F-101
is complete.
(c) Presentation, discussion, and possible action regarding the Texas Division of Emergency Management
(TDEM) Hazard Mitigation Grant Program (HMGP) related to FEMA-DR-4466 (Tropical Storm Imelda).
\[Lorenzo Wingate, Assistant Director of Public Works\]
Mr. Wingate let the Committee know TDEM has opened applications for Tropical Storm Imelda grants and that he
expected the same process of having to wait on any expenditures until the submissions had been awarded, unless
the project was divided into phases. Wingate said there were no updates for Brookglen, and that Harris County
Flood Control was waiting on timing for the release of grant funds and consideration by the Commissioners Court.
January 13, 2020 - Drainage and Flooding Committee Minutes
Wingate said the repetitive loss maps (properties with two or more claims in five years) were reviewed against the
damage from Hurricane Harvey and that he believed the City was moving forward in addressing drainage issues.
Ray Mayo, Director of Public Works, said in-house work was being concentrated on the east side of the airport and
that he believed that about 50% of the work had been completed.
4.Set date for next Drainage and Flooding Committee Meeting - The next meeting date was set for February 10,
2020.
5.Committee Member Comments There were no comments.
ADJOURN The meeting was adjourned without objection at 5:17 p.m.
____________________________________
Lee Woodward, City Secretary
January 13, 2020 - Drainage and Flooding Committee Minutes
REQUEST FOR DRAINAGE & FLOODING COMMITEE AGENDA ITEM
Appropriation
Agenda Date Requested: February 10, 2020
Requested By: Lorenzo Wingate, P.E., C.F.M. Source of Funds:
Department: Public Works
Account Number:
Amount Budgeted:
Report Resolution Ordinance
Amount Requested:
Exhibits: HCFCD Drainage Network Map
Budgeted Item: Yes No
SUMMARY
Receive report regarding Harris County Flood Control District (HCFCD) and Harris County
current and future plans relating to flooding in the City of La Porte.
RECOMMENDED MOTION
Approved for Drainage Committee Agenda
Corby D. Alexander, City Manager Date
REQUEST FOR DRAINAGE & FLOODING COMMITEE AGENDA ITEM
Appropriation
Agenda Date Requested: February 10, 2020
Requested By: Source of Funds:
Lorenzo Wingate, P.E., C.F.M.
Department:
Public Works
Account Number:
Amount Budgeted:
Report Resolution Ordinance
Amount Requested:
Exhibits: Consultant Proposal
Budgeted Item: Yes No
SUMMARY
During the December 9, 2019 City Council Meeting, Council voted to follow the recommendation of the
Drainage Committee of proceeding with the Bayside Terrace Drainage Improvements Project. Staff is
has negotiated the attached scope of work for engineering service with Halff Associates, Inc. The
proposal includes tasks for preliminary engineering, final design, bidding, and construction phase
services. The proposal will be presented to Council for approval at the February 24, 2020 Council
meeting.
RECOMMENDED MOTION
Approved for Drainage Committee Agenda
Corby D. Alexander, City Manager Date
January 29, 2020
Mr. Lorenzo Wingate
City Engineer
rd
2963 N. 23Street
La Porte, TX 77571
RE: Engineering Services Fee Proposal
Bayside Terrace Subdivision Drainage Improvements
Revision 3
Dear Mr. Wingate:
Halff AssociatesInc. (Halff)is pleased to submit our proposal to provide engineering servicesfor the
Bayside Terrace Subdivision Drainage Improvements projectfor the City of La Porte.The purpose of the
project is to increase capacity and address existing flooding issues within the subdivision by regrading
roadside ditches and upsizing the existing storm sewer system. The project area is generally bounded by
Pine Bluff Drive to the north, S. Broadway Street to the west, Dwire Drive to the south, and the San
Jacinto Bay to the east. This proposal will address development ofa preliminary engineering report
(PER), final design plans, and construction phase services.Additional services include geotechnical
analysis and environmental analysis.
In the PER, Halff will analyze existing conditions and evaluate proposed alternatives to recommend the
most feasible design based on various factors including estimated construction cost, available right-of-
way and easements, constructability, conflicts with existing utilities, and inconvenience to residents.
Alternatives will be presented to the City of La Porte for determination and approval of the final design.
The purpose of the finaldesign phase is to develop signed and sealed construction plansbased upon
findings in the PER.
Existing Conditions:
There are approximately 227 total structures within the “At-Risk” project area, including 206 residential
homes and 21 commercial structures.All 227 structures exist within a FEMA designated Special Flood
Hazard Area. Approximately 17 structures were damaged from Hurricane Harvey in 2017, resulting in
over $1.1 million dollars in damages.
The existing stormwater collection system is comprised of roadside ditches and underground reinforced
box culvert storm sewer to convey flow to two outfall points: an underground collection system along
Bayside Drive at the center of the subdivision, and a secondary collection system running along the
southeasternboundary of the subdivision.Both outfalls terminate at San Jacinto Bay. Access to the
southeastern collection system is limited; the system is located within fenced-in backyards of properties
within the subdivision and does not exist within a utility easement nor public right-of-way.
During intense rainfall events, the capacity of the southern system is exceeded,and the backwater
condition inundates sections of the neighborhood upstream.
Mr. Lorenzo Wingate
City of La Porte
January 29, 2020
Revision 3
Page 3
Attachment “A”
The purpose of this proposal is to develop a PER,final design plans, and construction phase services for
the Bayside Terrace Subdivision Drainage Improvements project.The proposed project area can be seen
inAttachment “C”.
SCOPE OF SERVICES
Preliminary Design Phase Services:
Task 1–Preliminary Engineering Report (PER)
The Preliminary Engineering Report will summarize findings from the drainage analysis and present
alternative options to the City of La Porte for their approval. The PER may consider presenting the
project in multiple phases based upon available funding. Preliminary Engineering Report services
include:
a)Reviewingall available record drawings and drainage reports to determine potential utility
conflicts and constraints.
b)Performingexisting conditions hydrologic analysis and delineate existing drainage basins to
determine drainage boundaries, flowrates, and outfall locations. Existing conditions hydraulic
analysis will quantify water surface elevations of roadside ditches.
c)Evaluatingthree proposed alternatives:
Concrete or asphalt with curb and gutter/storm sewer
Concrete or asphalt with roadside ditch system
Concrete or asphalt with combination storm sewer and roadside ditch system
d)Providingestimated construction costs for each alternative developed.
e)Providingprovide a final recommendation to the City of La Porte for their approvalin the form of
a report.
f)Prepare presentation and attend Drainage Committee meeting to present findings and
recommendations.
Final Design Services:
Task 2-Topographic Survey
Topographic survey will be delivered in AutoCAD Civil 3D format with field notes and ASCII files of all
points obtained. A DTM will be created to generate 1-foot contours.
a)Full topographic survey from ROW to ROW with cross-sections at 100-ft intervals, including: all
existing appurtenances, water meters, valves, valve boxes, fire hydrants, improvements within the
ROW (landscaping, mailboxes, etc.), trees, driveways, storm and sanitary flowlines, ditch and
culvert flowlines, pipe sizes and materials, power poles, fences, etc. Obtain private utility records
and incorporate into base drawing.Delineate public ROW based on land property monuments and
deed records.Provide RPLS signed and sealed survey control maps in PDF format
Mr. Lorenzo Wingate
City of La Porte
January 29, 2020
Revision 3
Page 4
Task 3-Project Management for Final Design
Project management services include:
a)Project progress meetings, design review meetings, and conference calls
b)Project site visits
c)Coordination and communicationwith private utility owners to resolve conflicts
Task 4: Civil Design Services
All design work will be completed using AutoCAD Civil 3D and will adhere to City of La Porte standards
found in Chapter 5 of the PICM Stormwater Design Criteria Manual. Plans, specifications, and estimates
will be submitted in three phases: 60%, 90%, andfinal. Thedrainage design will be based upon decisions
approved by the City of La Porte in the PER phase.Civil design services include:
a)Development of general project drawings: cover sheet, sheet index, legend, general notes, existing
and proposed typical sections, and project layouts
b)Development of paving and drainage, and utilitydrawings:utility plan and profiles and
paving/drainage plan and profiles.Paving and drainageplan and profile sheets will contain all
roadway design and drainage design, including ditches, storm sewer, and cross culverts.Utility
plan and profiles will contain proposed water lineand all related appurtenances.
c)Development of miscellaneous drawings: drainage area maps, hydraulic computations,SWPPP
layouts, traffic control plans, traffic control details; modification of City of La Portewater line
details, SWPPP details, and storm sewer detailsas needed.
d)Preparation of engineer’s estimate of probable construction cost at each submittal. Quantities will
be verified prior to each submittal. Halff will prepare the cost estimate and quantities using City
of La Portepay itemsand specifications.
e)Assist with preparation ofproject manual including applicable technical specifications, general
provisions, special specifications, and bid items with each submittal. The City of La Porte will
provide front end documents.
Task 5:BidPhase Services
a)Attendance at the pre-bid meeting and compilation of notes for distribution.
b)Preparation of pre-bid responses and responding to questions.
c)Attendance at the bid review meeting and providing input on the selection process.
d)Preparation of bid recommendation letter and bid tabulation summary.
Construction PhaseServices
Task 6: Construction Phase Services
a)Respondingto submittalsas requested by the City of La Porte
b)RespondingtoRFI as requested by the City of La Porte
c)Design changes/plan revisionsas requested by the City of La Porte
d)Preparation of record drawings, maintenance of RFI and submittallog
Mr. Lorenzo Wingate
City of La Porte
January 29, 2020
Revision 3
Page 5
Additional Services:
Task 7: Geotechnical Analysis
a)Geotechnical analysis services include: evaluating the soil and groundwater conditions along the
project alignment and providing geotechnical recommendations for proposed utility construction.
Pavement recommendations will also be provided.
Task 8: Environmental
a)Prepare a desktop environmental constraints analysis to provide supporting documentation for and
complete the EHP Checklist. This does not include agency coordination or consultation, permitting,
or NEPA environmental document preparation and clearance.
Services Not Included:
Reviewing change orders or pay estimates
Level of service verification in modeling efforts
Construction staking
Analysis of detention facilities
List of Assumptions:
1.All consultant fees shown on are considered to be lump sum unless otherwise noted.
2.The City of La Porte will provide any procedures, policies, data collection systems, engineering
guidelines, standards, and design criteria that will be required for this project.
3.The City of La Porte will retain ownership of any deliverables and electronic files created for this
project but will not be supplied with software applications or licenses as part of this project.
4.The scope of services does not include any preparation or attendance at any public meetings
pertaining to the project design or construction.
REQUEST FOR DRAINAGE & FLOODING COMMITEE AGENDA ITEM
Appropriation
Agenda Date Requested: February 10, 2020
Requested By: Lorenzo Wingate, P.E., C.F.M. Source of Funds:
Department: Public Works
Account Number:
Amount Budgeted:
Report Resolution Ordinance
Amount Requested:
Exhibits: Project map
Budgeted Item: Yes No
Project update chart
Harris County Drainage Network Map
SUMMARY
Refer to attached exhibit(s) for updates on various drainage projects throughout the
City.
RECOMMENDED MOTION
Approved for Drainage Committee Agenda
Corby D. Alexander, City Manager Date
REQUEST FOR DRAINAGE & FLOODING COMMITEE AGENDA ITEM
Appropriation
Agenda Date Requested: February 10, 2020
Requested By: Lorenzo Wingate, P.E., C.F.M. Source of Funds:
Department: Public Works
Account Number:
Amount Budgeted:
Report Resolution Ordinance
Amount Requested:
Exhibits: None
Budgeted Item: Yes No
SUMMARY
Opportunity to discuss any drainage concerns not covered by previous items.