HomeMy WebLinkAbout05-11-20 Regular Meeting of the La Porte City Council (2)
Office of the Mayor
WHEREAS, the Office of the Municipal Clerk, a time-honored and vital part of local government, exists throughout
the world, providing the professional link between citizens, local governing bodies, and other agencies of
government, rendering equal service to all; and
WHEREAS, the City Secretary is a City official appointed by the City Council, serving as the secretariat to the
governing body and performing duties including Council administration, Elections Officer, Public Information Officer for both
public information requests and for media and communications, liquor licensing, Records Management Officer, liaison to
boards and commissions, and being part of the City's emergency management team. The City Secretary is accountable for
the City seal and serves as the parliamentarian to the Council. The City Secretary is charged with neutrality, honesty,
integrity, and upholding applicable state law and the City Charter; and
WHEREAS, Municipal Clerks continually strive to improve through continuing education, by providing assistance to their
communities and their peers, and participation in professional organizations; and
WHEREAS, for the vital services they perform and their exemplary dedication to the communities they represent, we extend
our appreciation to City of La Porte City Secretary Lee Woodward, Deputy City Secretary Sharon Harris, Records
Administrator Gladis Sanchez, and temporary Administrative Assistant Kirsty Vigil.
I, Louis R. Rigby, Mayor, do hereby proclaim May 3-10, 2020, as
NOW, THEREFORE,
Municipal Clerks Week
th
In Witness Whereof: I have hereto set my hand and caused the Seal of the City to be affixed hereto, this the 11 day of
May, 2020.
Office of the Mayor
WHEREAS, Public Works professionals focus on infrastructure, facilities, and services that are of vital importance
to sustainable and resilient communities and to the public health, high quality of life, and well-being of the people of
La Porte, Texas; and,
WHEREAS, this work could not be accomplished without the dedicated efforts of public works professionals, who are
engineers, managers, and employees at all levels of government and the private sector, responsible for rebuilding,
improving, ste systems, public
buildings, and other structures and facilities essential for our citizens; and,
WHEREAS, it is in the public interest for the citizens, civic leaders, and children of La Porte to gain knowledge of and to
maintain a progressive interest and understanding of the importance of public works and public works programs in their
respective communities; and,
WHEREAS, the City of La Porte expresses its appreciation for our public works professionals, engineers, managers and
employees and to recognize the substantial contributions they make to improve our infrastructure, protect public health,
provide safety, and improve quality of life.
th
WHEREAS, the year 2020 marks the 60 annual National Public Works Week sponsored by the American Public Works
Association.
NOW, THEREFORE, I, Louis R. Rigby, Mayor, do hereby proclaim the week of May 17-23, 2020, as
National Public Works Week
th
In Witness Whereof: I have hereto set my hand and caused the Seal of the City to be affixed hereto, this the 11 day of
May, 2020.
City of La Porte
______________________________
Louis R. Rigby, Mayor
Office of the Mayor
WHEREAS, emergency medical services provides a vital public service; and
WHEREAS, the members of emergency medical services teams are ready to provide lifesaving care to those in
need 24 hours a day, seven days a week; and
WHEREAS, access to quality emergency care dramatically improves the survival and recovery rate of those who experience
sudden illness or injury; and
WHEREAS, the emergency medical services system consists of emergency physicians, emergency nurses, emergency
medical technicians, paramedics, firefighters, educators, administrators, and others; and
WHEREAS, the members of emergency medical services teams, whether career or volunteer, engage in thousands of
hours of specialized training, and continuing education to enhance their lifesaving skills; and
WHEREAS, it is appropriate to recognize the value and the accomplishments of emergency medical services providers by
designating Emergency Medical Services Weektheme, EMS STRONG: Ready Today. Preparing for
Tomorrowthe community to observe this week with appropriate programs, ceremonies, and activities;
NOW, THEREFORE, I, Louis R. Rigby, Mayor, along with members of the La Porte City Council, do hereby proclaim May
17-23, 2020, as
Emergency Medical Services Week
th
In Witness Whereof: I have hereto set my hand and caused the Seal of the City to be affixed hereto, this, the 11 day of
May, 2020.
City of La Porte
LOUIS RIGBY
BILL BENTLEY
Mayor
Councilperson District 3
BRANDON LUNSFORD
Mayor Pro-Tem
Councilperson At Large A
THOMAS GARZA
STEVE GILLETT
Councilperson District 4
Councilperson At Large B
JAY MARTIN
DANNY EARP
Councilperson District 5
Councilperson District 1
NANCY OJEDA
CHUCK ENGELKEN
Councilperson District 6
Councilperson District 2
MINUTES OF THE REGULAR MEETING OF THE
CITY COUNCIL OF THE CITY OF LA PORTE
APRIL 27, 2020
The City Council of the City of La Porte met in a regular meeting on Monday, April 27, 2020, at the City
Hall Council Chambers, 604 West Fairmont Parkway, La Porte, Texas, at 6:00 p.m., with the following in
attendance:
Councilpersons present: Louis Rigby, Brandon Lunsford, Steve Gillett, Chuck Engelken, Bill Bentley, Thomas
Garza, Jay Martin
Councilpersons attending remotely: Danny Earp, Nancy Ojeda
Councilpersons absent: None
Council-appointed officers present: Corby Alexander, City Manager; Lee Woodward, City Secretary; Clark
Askins, Assistant City Attorney
1. CALL TO ORDER Mayor Rigby called the meeting to order at 6:02 p.m.
2. INVOCATION AND PLEDGES The invocation was given by Pastor Thomas Green of Pleasant Hill Church
of Deliverance, and the pledges were led by Councilperson Jay Martin.
3. PRESENTATIONS, PROCLAMATIONS, AND RECOGNITIONS
a. Proclamation in recognition of April as Parliamentary Law Month. \[Mayor Rigby\]
4. CITIZEN COMMENT (Generally limited to five minutes per person; in accordance with state law, the time
may be reduced if there is a high number of speakers or other considerations.)
Chuck Rosa spoke about financial assistance to local businesses closed for COVID-19.
5. CONSENT AGENDA (Approval of Consent Agenda items authorizes each to be implemented in accordance
with staff recommendations provided. An item may be removed from the consent agenda and added to the
Statutory Agenda for full discussion upon request by a member of the Council present at this meeting.)
a.Approve the minutes of the April 13, 2020, Council meeting. \[Mayor Rigby\]
b. Approve the appointments of James Walter to Position 3 on the La Porte Planning and Zoning
Commission and John Blakemore to an open position on the La Porte Zoning Board of
Adjustment. \[Mayor Rigby and Mayor Pro Tem Bill Bentley\]
c.Approve the purchase of a Hino 338 Trash Truck with Heavy Brush Dump Bed from Rush Truck
Center under BuyBoard Contract 601-19, in the amount of $99,345.00. \[Ray Mayo, Director of
Public Works\]
Councilperson Engelken moved to approve the consent agenda items; the motion was adopted, 9-0.
Page 1 of 3
April 27, 2020, Council Meeting Minutes
6.STATUTORY AGENDA
a.Presentation, discussion, and possible action to provide staff direction on how to move forward
with livestreaming City Council meetings via Facebook for the short term. \[Corby Alexander, City
Manager\]
Councilperson Garza moved to direct staff move forward with livestreaming City Council meetings via
Facebook through Zoom until Zoom meetings are no longer occurring or until citizens are permitted into
the meetings; the motion was not adopted, 1-8, Councilperson Garza voting in support.
b. Presentation, discussion, and possible action to reschedule or cancel the May 25, 2020, City
Council meeting due to the Memorial Day holiday. \[Mayor Rigby\]
Councilperson Garza moved to hold the May 25, 2020, City Council meeting on May 26, 2020; the motion
was not adopted, 2-7, Councilpersons Garza and Gillett voting in support.
Councilperson Engelken moved to cancel the May 25, 2020, City Council meeting for the Memorial Day
holiday and hold a special meeting if necessary. Councilperson Garza moved to amend the motion by
was not seconded and was not considered. The main motion was adopted 8-1, Councilperson Garza
voting against.
7. REPORTS
a. Receive report on the La Porte Development Corporation Board meeting. \[Councilperson Ojeda\]
Councilperson Ojeda reported the Board did not take action on a proposed COVID grant program for
small businesses.
8. ADMINISTRATIVE REPORTS
City Council meeting, May 11
City Manager Alexander said there were no reports.
9. COUNCIL COMMENTS regarding matters appearing on the agenda; recognition of community
members, city employees, and upcoming events; inquiry of staff regarding specific factual
information or existing policies.
Councilpersons
shared concern that the City was allowing the Harris County J on masks to be followed; noted
displeasure over the misuse of social media for personal attacks; thanked the City staff for maintaining
services in spite of the pandemic; requested that HR share compensation information in advance with all
Councilpersons for Charter officer reviews; reminded all of the CDC recommendations as local cases
continued to increase and to respect each other by following the guidelines; expressed disappointment over
current behavior of Councilpersons; announced the Off
received one of the eighteen inaugural Office of Excellence awards from the Texas Municipal Clerks
Association, Inc. (TMCA); issued a reprimand concerning derogatory comments about the City on social
media.
ADJOURN Without objection, Mayor Rigby adjourned the meeting at 7:14 p.m.
Page 2 of 3
April 27, 2020, Council Meeting Minutes
_______________________________
Lee Woodward, City Secretary
Page 3 of 3
April 27, 2020, Council Meeting Minutes
REQUEST FOR CITY COUNCIL AGENDA ITEM
Appropriation
Agenda Date Requested: May 11, 2020
Source of Funds: 009
Requested By: Shelley Wolny, Treasurer
Department: Finance
Account Number: 9999 Special Programs
Amount Budgeted: $0
Report Resolution Ordinance
Amount Requested: $99,345
Exhibits: Ordinance, Exhibits A & B and Detail Information
Budgeted Item: Yes No
SUMMARY
The City Council adopted the Fiscal Year 2019-20 Budget on September 9, 2019.
th
At the April 27 City Council meeting, Council approved the purchase of the
replacement trash truck at a cost of $99,345. With this expenditure, staff is requesting
Council to approve a budget amendment. The Summary of Funds, which is shown
below, represents the amendments which Council previously approved to the FY 2019-
20 Budget. (*denotes funds with current changes)
FY 2020 Proposed FY 2020
Original Budget Amended Budget
General Fund $ 54,659,634 $ 54,659,634
Grant Fund 8,857,843 8,857,843
Street Maintenance Sales Tax Fund 3,195,000 3,195,000
Emergency Services District Sales Tax Fund 1,273,334 1,273,334
Hotel/Motel Occupancy Tax 809,777 809,777
Economic Development Corporation 2,929,197 2,929,197
Tax Increment Reinvestment Zone 5,383,569 5,383,569
Utility 8,287,115 8,287,115
Airport 90,680 90,680
La Porte Area Water Authority 2,307,665 2,307,665
Motor Pool 2,834,770 2,934,115 *
Insurance Fund 9,043,630 9,043,630
Technology Fund 278,828 278,828
General Capital Improvement 8,925,869 8,925,869
Utility Capital Improvement 1,715,000 1,715,000
Sewer Rehabilitation Capital Improvement 350,000 350,000
Drainage Improvement Fund 480,000 480,000
General Debt Service 4,657,119 4,657,119
Total of All Funds $116,079,030$116,178,375
RECOMMENDED MOTION
I move to approve the adoption of ordinance 2020-3789 approving an amendment to the
Ci-20 Budget for $99,345 in the Motor Pool Fund to purchase a
replacement trash truck.
Approved for the City Council meet
ing agenda
Corby D. Alexander, City Manager Date
ORDINANCE2020-3789
AN ORDINANCE APPROVING AN AMENDMENT TO THE BUDGET FOR THE CITY OF LA PORTE, TEXAS,
FOR THE PERIOD OF OCTOBER 1, 2019 THROUGH SEPTEMBER 30, 2020; FINDING THAT ALL THINGS
REQUISITE AND NECESSARY HAVE BEEN DONE IN PREPARATION AND PRESENTMENT OF SAID
BUDGET; FINDING COMPLIANCE WITH THE OPEN MEETINGS LAW; AND PROVIDING AN EFFECTIVE
DATE HEREOF.
WHEREAS, the Charter of the City of La Porte, Texas, and the Statutes of the State of Texas, require that an
annual budget be prepared and presented to the City Council of the City of La Porte, Texas, prior to the beginning
of the fiscal year of said City, and that a public hearing be held prior to the adoption of said Budget; and
WHEREAS, the Budget for the fiscal year October 1, 2019, through September 30, 2020, has heretofore been
presented to the City Council and due deliberation had thereon, was filed in the office of the City Secretary on
July 23, 2019, and a public hearing scheduled for September 9, 2019 was duly advertised and held, and said
Budget was finally approved by ordinance on September 9, 2019;
WHEREAS, Subsection (b) of Section 102.009 of the Texas Local Government Code provides that, after final
adoption of the budget, the governing body of the municipality may spend municipal funds only in strict
compliance with the budget, except in emergency, where in such cases the governing body of the municipality
may authorize an emergency expenditure as an amendment to the original budget only in the case of grave
public necessity to meet an unusual and unforeseen condition that could not have been included in the original
budget through the use of reasonably diligent thought and attention;
WHEREAS, Section 102.010 of the Texas Local Government Code provides that the governing body of a
municipality may make changes to its budget for municipal purposes;
WHEREAS, the adoption of this ordinance and the amendment of the Budget is necessary for and in the best
interest of the health, safety and general welfare of the inhabitants of the City;
NOW THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE:
SECTION 1. A grave public necessity exists and to meet an unusual and unforeseen condition that could not
have been included in the original budget through the use of reasonably diligent thought and attention, the Budget
must be amended and revised with respect to those appropriations set forth in Exhibit B, attached hereto by
reference and made part hereof. In support thereof, the City Council finds that additional expenditures are
necessary for 1) $99,345.00 for the replacement of a trash truck lost in accident. Such additional expenditures
are more specifically described on Exhibit C.
SECTION 2: That the Budget for the City of La Porte, Texas, now before the said City Council for consideration,
a complete copy of which is on file with the City Secretary and a summary of which is attached hereto by
reference as Exhibit "A", is hereby amended as reflected on the amended budget summary document, attached
hereto by reference as , as the Budget for the said City of La Porte, Texas, for the period of October
1, 2019, through September 30, 2020.
SECTION 3. The several amounts stated in Exhibit C as the amended expenditures are hereby appropriated to
and for the objects and purposes therein named, and are found to be for municipal purposes.
SECTION 4. The amended and revised expenditures contained in the Budget, do not exceed the resources of
each fund, as so amended and revised.
SECTION 5: The City Council finds that all things requisite and necessary to the adoption of said Budget and
the amendments made hereto have been performed as required by charter or statute.
SECTION 6. Upon the passage and adoption of this ordinance, a copy of the ordinance shall be filed with the
City Secretary, who shall attach a copy of same to the original budget.
SECTION 7: The City Council officially finds, determines, recites and declares that a sufficient written notice of
the date, hour, place and subject of this meeting of the City Council was posted at a place convenient to the
public at the City Hall of the City for the time required by law preceding this meeting, as required by the Open
Meetings Law, Chapter 551, Texas Government Code; and that this meeting has been open to the public as
required by law at all times during which this Ordinance and the subject matter thereof has been discussed,
considered and formally acted upon. The City Council further ratifies, approves and confirms such written notice
and the contents and posting thereof.
SECTION 8: This Ordinance shall be in effect from and after its passage and approval.
PASSED AND APPROVED this the 11th day of May, 2020.
CITY OF LA PORTE, TEXAS
Louis R. Rigby, Mayor
ATTEST:
Lee Woodward, City Secretary
APPROVED AS TO FORM:
ClarkT. Askins, Assistant City Attorney
EXHIBIT A
(ADOPTED BUDGET)
City of La Porte
Consolidated Summary of All Funds
FY 19-20FY 19-20
RevenuesExpenses
Governmental Fund Types:
General Fund$ 50,777,377 $ 54,429,634
Grant Fund 8,449,254 8,857,843
Street Maintenance Sales Tax 1,400,000 3,195,000
Emergency Services District 1,380,000 1,273,334
Hotel/Motel Occupancy Tax 765,000 809,777
Economic Development Corporat 2,800,000 2,929,197
Tax Increment Reinvestment 5,508,293 5,383,569
Total Governmental Types 71,079,924 76,878,354
Enterprise:
Utility 8,318,050 8,287,115
Airport 66,500 90,680
La Porte Area Water Authority 1,586,656 2,307,665
Total Enterprise 9,971,206 10,685,460
Internal Service
Motor Pool 3,657,278 2,834,770
Insurance Fund 8,887,771 9,043,630
Technology Fund 437,736 278,828
Total Internal Service 12,982,785 12,157,228
Capital Improvement:
General 8,445,950 8,695,869
Utility 625,000 1,715,000
Sewer Rehabilitation 303,500 350,000
Drainage Improvement Fund 286,500 480,000
Total Capital Improvement 9,660,950 11,240,869
Debt Service:
General 4,686,664 4,657,119
Total Debt Service 4,686,664 4,657,119
Total All Funds 108,381,529 115,619,030
EXHIBIT B
(AMENDED BUDGET)
City of La Porte
Consolidated Summary of All Funds
FY 19-20FY 19-20
RevenuesExpenses
Governmental Fund Types:
General Fund$ 50,777,377$ 54,659,634
Grant Fund 8,449,254 8,857,843
Street Maintenance Sales Tax 1,400,000 3,195,000
Emergency Services District 1,380,000 1,273,334
Hotel/Motel Occupancy Tax 765,000 809,777
Economic Development Corporat 2,800,000 2,929,197
Tax Increment Reinvestment 5,508,293 5,383,569
Total Governmental Types 71,079,924 77,108,354
Enterprise:
Utility 8,318,050 8,287,115
Airport 66,500 90,680
La Porte Area Water Authority 1,586,656 2,307,665
Total Enterprise 9,971,206 10,685,460
Internal Service
Motor Pool 3,657,278 2,934,115
Insurance Fund 8,887,771 9,043,630
Technology Fund 437,736 278,828
Total Internal Service 12,982,785 12,256,573
Capital Improvement:
General 8,675,950 8,925,869
Utility 625,000 1,715,000
Sewer Rehabilitation 303,500 350,000
Drainage Improvement Fund 286,500 480,000
Total Capital Improvement 9,890,950 11,470,869
Debt Service:
General 4,686,664 4,657,119
Total Debt Service 4,686,664 4,657,119
Total All Funds 108,611,529 116,178,375
REQUEST FOR CITY COUNCIL AGENDA ITEM
Appropriation
Agenda Date Requested:April 27, 2020
Requested By: Ray Mayo, Director Source of Funds: 009 -Motor Pool Fund
Department:
Public Works
Account Number:009-7072-532-8050
Amount Budgeted: -0-
Report Resolution Ordinance
Amount Requested: $99,345.00
Budgeted Item: YesNo
Exhibits: BuyBoard Quote for Heavy Trash Truck
Replacement
SUMMARY
The City of La Porte’s trash truck (unit 72-56) was involved in a roll-over accident while
dumping a load at the Green Shadow landfill in September 2019. Inspection by TML
adjusters showed major frame damage resulting in a total loss. Staff is requesting to
have this piece of equipment replaced. This equipment was not programmed in the
budget to be replaced at this time. The Finance Department will come forward at the
next City Council meeting, May 11, 2020 with a budget amendment to allow
replacement.
Following the incident, our staff performed in-depth research to determine available
truck and body options to prevent a recurrence of this type of accident. The replacement
equipment is quoted with those options that include: extra heavy-duty frame with
overweightfront axle, oversizedrear helper springs and a rear suspension stabilizer
package. TML has issued an insurance claim check in the amount of $48,873.65. The
balance of the replacement cost ($50,471.35) will be funded in the Motor Pool Fund for
replacement trash truck. Staff is requesting approval for the purchase of a Hino 338
Trash Truck with Heavy Brush Dump Bed from Rush Truck Center, which is under the
BuyBoard Contract #601-19 in the amount of $99,345.
RECOMMENDED MOTION
I move to approve the purchase of a Hino 338 Trash Truck with Heavy Brush
Dump Bed from Rush Truck Center under BuyBoard Contract 601-19 for
$99,345.00
Approved for the City Council meeting agenda
Corby D. Alexander, City Manager Date
TEXAS LOCAL GOVERNMENT PURCHASING COOPERATIVE--BUYBOARD
Remit P.O.'s To: munisales@rushenterprises.com
VendorDate Prepared
Contact for Vendor: Phone(830) 320-5219
End User:
End User Contact:Phone/Fax
Product Description:
A: Base Price in Bid/Proposal Number:601-19 Series: 338/L7$ 57,725.00
B: Published Options(Itemize Below)
DESCRIPTIONAMOUNT OPT #DESCRIPTIONAMOUNT
HinoVIN Tag De-Rate to 25,950$ 131.00Hino Back Up Alarm/BR 11R22.5 R250ED$ 264.00
Hino Left & Right side Tow Hooks/120K PSI Frame$ 878.00Hino BR Lug 11R22.5 M770/Fendor Mirrors$ 286.00
Hino J08E-VB 260 HP/Allison 3500 RDS-P Transmission$ 5,893.00 Hino 4 Keys Keyed Alike/Fire Extinguisher/Safety Triangles$ 154.00
Hino Meritor MFS14K Front Axle/4K Rear Helper Springs$ 1,741.00 RTC-0051 OEM+ Safety Analysis$ 1,236.00
Hino Rear Suspension Stabilizer/Driver Controlled Diff Lock$ 1,890.00 RTC-0122 Refuse Body Prep$ 3,934.00
Hino Sythetic Rear Axle Lube/Air Brakes$ 2,008.00 RTC-0004 Dump Body$ 20,820.00
Subtotal Column 1:$ 12,541.00 Subtotal Column 2:$ 26,694.00
Published Options added to Base Price(Subtotal of "Col 1" & "Col 2")
$ 39,235.00
C: Subtotal of A + B$ 96,960.00
D: Non Published Options
Subtotal Column 1:$ -Subtotal Column 2:$ -
Unpublished Options added to Base price (Subtotal "Col 1 + Col 2")
$ -
E: Contract Price Adjustment (If any, explain here)
F: Total of C + D +/- E $ 96,960.00
G: Quantity ordered Units: 1.00x $ 96,960.00
H: BUYBOARD Administrative Fee
$ 400.00
I: Non-Equipment Charges & Credits (I.e.: Ext. Warranty, Trade-In, Delivery, etc.)
Extended Warranty Aftertreatment (6/250)$ 700.00x1$ 700.00
Extended Warranty Engine (6/250)$ 460.00x1$ 460.00
Freight$ 825.00x1$ 825.00
$ 1,985.00
J: TOTAL PURCHASE PRICE INCLUDING (G+H+I)$ 99,345.00
REQUEST FOR CITY COUNCIL AGENDA ITEM
Appropriation
Agenda Date Requested: May 11, 2020
Requested By: Ray Mayo, Director Source of Funds: 033 - Street Maintenance
Department: Public Works
Account Number: 033-7071-531-5110
Amount Budgeted: $630,000.00
Report Resolution Ordinance
Amount Requested: $630,000.00
Exhibits: Bid #20012 Tabulation, Bid Notification and Access
Budgeted Item: Yes No
Report, Map of Project Areas, Angel Brothers Bid
SUMMARY
Advertised sealed bid #20012 for the FY 2020 Street Overlay project was opened and read
publicly via ZOOM meeting at 2:00 p.m. on Thursday, April 16, 2020. Four hundred fifty-nine
(459) vendors were notified of the bid opportunity with thirty-one (31) accessing the bid and
twenty-five (25) bidders downloading the bid documents. Bid requests were advertised in the
Bay Area Observer, posted on the City of La Porte website site and Public Purchase, with three (3)
contractors returning bids.
Angel Brothers Enterprises Ltd. submitted the lowest bid in the amount of $841,216.00 for the
Base Bid. This project was bid with the intent to award on a unit pricing basis using work order
assignments combined to not exceed the budget amount for this fiscal year. The estimated
quantities in the bid can be increased or decreased to provide the best benefit for the City.
Angel Brothers and City staff has negotiated and mutually agreed to revise the work estimate
th
by removing the reconstruction of S. 5 Street. This brings the total costs of the proposed work
to $605,628. asphalt prices indicate a 22% increase over last years price.
Staff recommends that the project be awarded to Angel Brothers Enterprises Ltd. in the amount
of $605,628 with a contingency amount of $24,372 (4%), for a total authorization of $630,000.
Streets indicated on the map were selected for overlay using past and current assessment
information.
tƩƚƆĻĭƷ .ĻƓĻŅźƷƭͲ \[źğĬźƌźƷźĻƭͲ ğƓķ hƦĻƩğƷźƓŭ /ƚƭƷʹ
.ĻƓĻŅźƷƭʹ
The proposed project provides maintenance and rehabilitation of existing public
facilities anticipated by the residents with the street tax renewal.
\[źğĬźƌźƷźĻƭ ƚŅ ağźƓƷğźƓźƓŭ ƷŷĻ {ƷğƷǒƭ vǒƚʹ
The scope and cost of the proposed work would likely increase if the proposed
resurfacing work is deferred for an extended period of time.
RECOMMENDED MOTION
I move to award Bid #20012 to Angel Brothers Enterprises Ltd. and authorize the
City Manager to execute a contract establishing unit prices for asphalt street
reconstruction and overlay in the amount of $605,628 with a contingency amount
of 24,372.00 for a total authorization of 630,000.00.
Approved for the City Council meeting agenda
Corby D. Alexander, City Manager Date
Bid Tabulation to Sealed Bid #20012 - FY 20 Asphalt Reconstruction and Overlay Project
Angel BrothersHayden Paving, Inc.Forde Constructions
ItemUnit of
Item DescriptionQTYUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
No.Measur
Mobilization: includes payment and performance bonds,
insurance and cost to move equipment to project as
required by these plans and specifications; NOT TO
30,000.00$30,000.0025000$25,000.0034000$34,000.00
EXCEED 4% of total project cost
LS
11
16,000.00$16,000.0010000$10,000.0051300$51,300.00
2Traffic Control, as specified1LS
8$56,712.007$49,623.006$42,534.00
36" Pavement and subgrade removal7089SY
3$47,334.002$31,556.002$31,556.00
42" Milling and removal15778SY
105$367,500.00110$385,000.00102$357,000.00
52" Type D Asphalt3500TON
101$196,950.00100$195,000.00100$195,000.00
64" Type A Asphalt1950TON
120$60,000.00150$75,000.00128$64,000.00
7Black base, as needed for repair500TON
187$28,050.00200$30,000.00172$25,800.00
8Lime, 8%150TON
5$38,670.0015$116,010.008$61,872.00
98" Lime stabilized subgrade7734SY
$841,216.00$917,189.00$863,062.00
TOTAL Base Bid, Items 1 - 9 only
22867
20$457,340.00
ADD High Density Mineral Bond, as specifiedSY NO BIDNO BIDNO BIDNO BID
$841,216.00$1,374,529.00$863,062.00
Total Bid Items 1-9, plus ADDITIVE
Project award shall be based on Unit Pricing, in an amount not to exceed the Fiscal Year budget. Bid tab does not indicate any type of award as other
considerations may apply.
Sealed Bid #20012 Notifications and Access Report
NOTIFICATIONS ACCESS
Vendor NameReasonVendor NameAccessed Documents
#20012 FY2020 Asphalt Reconstruction and
2GS, LLCBid NotificationAAA Asphalt Paving
#20012 FY2020 Asphalt Reconstruction and
2L Construction L.L.C.Bid NotificationAngel Brothers Enterprises, Ltd.
#20012 FY2020 Asphalt Reconstruction and
A J Commercial ServicesBid NotificationBidClerk
#20012 FY2020 Asphalt Reconstruction and
A&S UndergroundBid NotificationBrannan Paving Co., Ltd
#20012 FY2020 Asphalt Reconstruction and
A. Ortiz Construction & Paving, Bid NotificationBraun Intertec Corporation
#20012 FY2020 Asphalt Reconstruction and
A.M.S.R. Inc.Bid NotificationCity of La Porte
AAA Asphalt Paving Inc.Bid NotificationCMD
Aaron Concrete Contractors, LPBid NotificationCMS
#20012 FY2020 Asphalt Reconstruction and
Abel's Paving & ConstructionBid NotificationConstructConnect
#20012 FY2020 Asphalt Reconstruction and
Acadia Services, LLCBid NotificationConstruction Journal
#20012 FY2020 Asphalt Reconstruction and
Adept Facilities & Design, Inc.Bid NotificationConstruction Software Technologies
#20012 FY2020 Asphalt Reconstruction and
Advance Sealcoat & StripesBid NotificationDale Dobbins
#20012 FY2020 Asphalt Reconstruction and
Advanced Facility MaintenanceBid NotificationDodge Data & Analytics
#20012 FY2020 Asphalt Reconstruction and
Advanced PavingBid NotificationDurba Construction
#20012 FY2020 Asphalt Reconstruction and
AE ConsultingBid NotificationForde Construction Company
#20012 FY2020 Asphalt Reconstruction and
Affordable Concrete LLC Bid NotificationHayden Paving Inc.
#20012 FY2020 Asphalt Reconstruction and
AGC AustinBid NotificationHearn Company
#20012 FY2020 Asphalt Reconstruction and
Aggieland ConstructionBid NotificationHolbrook Asphalt
AGH2O Holdings, LLCBid NotificationIMS
AHRG, CorporationBid NotificationL & L Asphalt Corp
#20012 FY2020 Asphalt Reconstruction and
Alegria Construction LLCBid NotificationL&L Supplies
#20012 FY2020 Asphalt Reconstruction and
All Materials Construction LLCBid NotificationNorth America Procurement Council
#20012 FY2020 Asphalt Reconstruction and
All State StripingBid NotificationOnvia
#20012 FY2020 Asphalt Reconstruction and
Allen Butler Construction, Inc.Bid NotificationPerkens WS Corporation
#20012 FY2020 Asphalt Reconstruction and
ALLTEX CORING & SAWINGBid NotificationSAMES, INC.
#20012 FY2020 Asphalt Reconstruction and
ALS 88 DESIGN BUILD LLCBid NotificationSchool Wholesale Supplies LLC
#20012 FY2020 Asphalt Reconstruction and
AMC TXCI TX CONSTRUCTIO Bid NotificationSmartProcure
American Custom Homes & ReBid NotificationSO
#20012 FY2020 Asphalt Reconstruction and
American Pavement SolutionsBid NotificationThe Blue Book Building & Constructio
AMSCO Property Services, LLCBid NotificationTukmol General Contractor
Anchor Contracting, LLCBid NotificationWayne Enterprises
#20012 FY2020 Asphalt Reconstruction and
Anderson Asphalt & Concrete P Bid NotificationWebtech
Anderson Columbia Co.,, Inc.Bid Notification
Andromeda Contracting Bid Notification End Of Access Report Info
Angel Brothers Enterprises, LtdBid Notification
APAC-Texas, IncBid Notification
Apex Construction Inc.Bid Notification
ARCADIS US, Inc.Bid Notification
Archer Western Construction LBid Notification
Ark Contracting Services, LLCBid Notification
Arreguin Group IncBid Notification
Ashco ContractingBid Notification
Asphalt Patch Enterprises, IncBid Notification
Associated Construction Partne Bid Notification
AUI ContractorsBid Notification
Austin Bridge & Road, LPBid Notification
Austin Engineering Company, IBid Notification
Austin Traffic Signal Constructio Bid Notification
BakerCorpBid Notification
Barricades UnlimitedBid Notification
Bartek ConstructionBid Notification
Basic IDIQ, Inc.Bid Notification
BATTERY WAREHOUSEBid Notification
Baukus ElectricBid Notification
Bay LtdBid Notification
Bega Paving, IncBid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
Belaire ConstructionBid Notification
Bell Contractors Inc Bid Notification
Bentex Sweeping Inc.Bid Notification
Bergeron Emergency Services, Bid Notification
BidClerkBid Notification
Black Canyon ConstructionBid Notification
Blackrock ConstructionBid Notification
BMC ConsolidatedBid Notification
Boring & Tunneling Company o Bid Notification
Boyd Construction Services, LLBid Notification
Brannan Paving Co., LtdBid Notification
Braun Intertec CorporationBid Notification
Brazos Point ConstructionBid Notification
BRETT CONSTRUCTION CO., Bid Notification
Brooks Concrete IncBid Notification
Brownstone Companies LLCBid Notification
BrushmastersBid Notification
C & M Concrete ContractingBid Notification
C&C Industrial Services, Inc.Bid Notification
C&S ConstructionBid Notification
CADCon Corp.Bid Notification
CAM-CRETE CONTRACTING, Bid Notification
CAO Concrete L.L.C.Bid Notification
Capps-Capco Construction, IncBid Notification
Cardno ATCBid Notification
Cash ConstructionBid Notification
Castle Enterprises, LLCBid Notification
Catalyst Advisors, LLCBid Notification
Category 5 Restorations & Con Bid Notification
Cayo LLCBid Notification
CCC Blacktopping LLCBid Notification
CD BUILDERS, INCBid Notification
CDC NewsBid Notification
CDM Holdings, LLC.Bid Notification
Central Road and Utiltiy LtdBid Notification
Central State ResourcesBid Notification
Ceres Environmental Services, Bid Notification
CH2M HILLBid Notification
Champion Infrastructure LLCBid Notification
CI PavementBid Notification
Clark Construction of Texas, InBid Notification
Clearfield Construction, LLC.Bid Notification
Clore Construction LLCBid Notification
CMC Construction ServicesBid Notification
coast to coastBid Notification
Cody Stanley Construction LLCBid Notification
Colair, Inc.Bid Notification
Concrete Raising CorporationBid Notification
Constar ConstructionBid Notification
ConstructConnectBid Notification
construction companies groupBid Notification
Construction Companies Group Bid Notification
Construction JournalBid Notification
Construction Masters of Housto Bid Notification
Construction Software TechnoloBid Notification
CONTECH Construction Produ Bid Notification
Cornerstone EngineeringBid Notification
Craig Olden, Inc.Bid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
Crockett ConstructionBid Notification
Cruz EnterprisesBid Notification
Cubit Contracting, LLCBid Notification
Cummings Paving and Recyclin Bid Notification
Curran Contracting CompanyBid Notification
CW&W CONTRACTORS, INC.Bid Notification
D & A TECHNOLOGY & DEVEBid Notification
D & W Contractors Inc.Bid Notification
D DavilaBid Notification
D Guerra Construction LLCBid Notification
D J Site Construction Inc.Bid Notification
Dale DobbinsBid Notification
Dalrymple Gravel & Contracting Bid Notification
Dannenbaum EngineeringBid Notification
DCCS, LLCBid Notification
DCI Contracting, Inc.Bid Notification
Delta Prime Specialty Services Bid Notification
derk harmsen const. co incBid Notification
DezTex Industrial Service LLC Bid Notification
DFW Services LLCBid Notification
DIJ Construction, IncBid Notification
Dixon Paving, Inc.Bid Notification
DNT Construction LLCBid Notification
Dodge Data & AnalyticsBid Notification
Doggett Heavy Machinery Serv Bid Notification
Don's Trucking & AssociatesBid Notification
Dorame General Repair and La Bid Notification
Dorazio Enterprises, Inc.Bid Notification
Dort & O'Connor ContractorsBid Notification
Duininck, Inc.Bid Notification
DUO CONSTRUCTION, LLCBid Notification
DURAN CONCRETE & CONST Bid Notification
Durba ConstructionBid Notification
Durwood Greene Construction Bid Notification
E Contractors usa,LLCBid Notification
E W Wells Group Bid Notification
E Z Bel Construction,LLCBid Notification
Eagle Eye Consulting and Cons Bid Notification
Earth Builders, LPBid Notification
ECM International, Inc.Bid Notification
Ed Bell Construction CompanyBid Notification
Enterprise Commercial PavingBid Notification
EPCS Environmental LLCBid Notification
ERS, Inc.Bid Notification
Estrada Concrete Co. LLCBid Notification
Exposed Floor Design Group LBid Notification
E-Z Bel Construction, LLC.Bid Notification
Fantastic Concrete, L.P.Bid Notification
FD CONCRETE LLCBid Notification
Fire Line Services, Inc. Bid Notification
Florida Traffic Control Devices, Bid Notification
Flow-Line Construction, Inc.Bid Notification
FNH CONSTRUCTION LLCBid Notification
Forde Construction CompanyBid Notification
Foremost Paving, Inc.Bid Notification
Fort Worth Civil Constructors, LBid Notification
Fritcher Construction ServicesBid Notification
Fugro Consultants, Inc.Bid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
G & L Young Construction, LtdBid Notification
G&T PAVING, LLCBid Notification
Gallo PavingBid Notification
Garland Concrete LLPBid Notification
Garner Paving and Constructio Bid Notification
Garrett Construction CompanyBid Notification
Gary W Purser Construction, LtBid Notification
Gayle JuraschekBid Notification
Gibson & Associates, Inc.Bid Notification
Gilbert May Inc.Bid Notification
Gilco Contracting, Inc.Bid Notification
GME Consulting ServicesBid Notification
Graham County Land Company Bid Notification
Greco Construction, Inc.Bid Notification
GRod Construction, LLCBid Notification
GT Construction Inc.Bid Notification
Guard Construction LLCBid Notification
Guido Brothers Construction Co Bid Notification
Gunter IndustriesBid Notification
GW Phillips Construction, INC. Bid Notification
h & b contractorsBid Notification
H. W. Lochner, Inc.Bid Notification
Haas-Anderson Construction, LBid Notification
Harper BrothersBid Notification
HARRIS CONSTRUCTION CO Bid Notification
Hart Constractors of Texas, LLCBid Notification
Hayden Paving, Inc.Bid Notification
HBT, IncBid Notification
HD Supply White CapBid Notification
HDR Engineering, Inc.Bid Notification
Hearn CompanyBid Notification
Heartland Asphalt Materials, IncBid Notification
Herrcon, LLCBid Notification
High Sky Construction & Mainte Bid Notification
Highway Technologies, Inc.Bid Notification
Hilbrick IncorporatedBid Notification
Hill Country Bridge, Inc.Bid Notification
HJD Capital Electric, Inc.Bid Notification
Holbrook AsphaltBid Notification
Holy Contractors LLCBid Notification
Horns Crew TruckingBid Notification
HQS Construction, LLCBid Notification
ICON Diversified, LLCBid Notification
Innovative Roadway, LLCBid Notification
Intermountain Slurry Seal, Inc.Bid Notification
Interstate Highway Construction Bid Notification
Iowa Bridge & Culvert, LCBid Notification
ISI Contracting, Inc.Bid Notification
J M DavidsonBid Notification
J Squared Construction Service Bid Notification
J&G Concrete ProductsBid Notification
J. Carroll Weaver, Inc.Bid Notification
J. W. Kelso Company, Inc.Bid Notification
J.D. Abrams, L.P.Bid Notification
Jackson Construction, Ltd.Bid Notification
JacobsBid Notification
James Construction Group, LLCBid Notification
Jasco Services LLCBid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
Jasiri Construction, L.L.C.Bid Notification
Jay Mills Contracting, Inc.Bid Notification
JCD Construction, LLCBid Notification
JE Construction Services, LLCBid Notification
Jenn Energy Services, LLCBid Notification
Jerdon Enterprise, L.P.Bid Notification
Jericho Foundation Repairs, IncBid Notification
Jeske ConstructionBid Notification
JESSE L. HERRERA CONSTR Bid Notification
JFS SERVICES LLCBid Notification
JHL CONSTRUCTIONBid Notification
JHM constructionBid Notification
Jim Bowman Construction Com Bid Notification
JIm Kodam Inc.Bid Notification
JJG DEVELOPMENT LLCBid Notification
JK General Contractors & Cons Bid Notification
JLB Contracting,LLCBid Notification
Joe Funk Construction, Inc.Bid Notification
John & Marcus Contractors LLCBid Notification
John Reed and Company LLCBid Notification
Johnson Bros. Corporation, a S Bid Notification
Jordan Foster ConstructionBid Notification
joshua dade contractorsBid Notification
Juan NoriegaBid Notification
KALTEK ENGINEERING INCBid Notification
KC Commercial, LLCBid Notification
KEGLEY, Inc.Bid Notification
Ken-Do Contracting LP Bid Notification
Kessler PaintingBid Notification
Kickapoo Empire LLCBid Notification
Kilgore IndustrialBid Notification
KlutzConstruction, LLCBid Notification
KNS LLCBid Notification
Kwest GroupBid Notification
L & L Asphalt CorpBid Notification
L&L SuppliesBid Notification
L.H. Lacy Company, Ltd.Bid Notification
Landmark ServicesBid Notification
LaSalle Afforadble BuildersBid Notification
Lee Construction and MaintenaBid Notification
Leland Bradlee ConstructionBid Notification
LEMCO Construction ServicesBid Notification
Let's Talk Network IncBid Notification
Levy CompanyBid Notification
Lone Star EquipmentBid Notification
Lone Star Grading & MaterialsBid Notification
Lone Star Trucking & ExcavatioBid Notification
Longhill Group IncBid Notification
Lowman Land ImprovementsBid Notification
L-Sync LLC Bid Notification
Lyness ConstructionBid Notification
M & M Weatherization Co. dba Bid Notification
M&C Fonseca Construction Co Bid Notification
M. C. Ethridge Co.Bid Notification
M-5 Texas Enterprises, LLCBid Notification
MAC, Inc.Bid Notification
MACBBid Notification
Magnum Electrical Contractors Bid Notification
Mann Robinson & Son, Inc.Bid Notification
MARC III General Contractors, Bid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
MAR-CON SERVICES, LLCBid Notification
Margaret RussoBid Notification
Marg-Tiff IncBid Notification
Mas-Tek Engineering & AssociaBid Notification
Matrix DemolitionBid Notification
McCarthy Building Companies, Bid Notification
McClendon Construction Co., InBid Notification
McGraw-Hill Construction Dodg Bid Notification
McKenzie Jackson ConstructioBid Notification
Mclean ConstructionBid Notification
McMahon Contracting LPBid Notification
Meiners Construction Inc.Bid Notification
Metro City ConstructionBid Notification
MGC Contractors IncBid Notification
Midasco LLCBid Notification
Missouri Petroleum Products C Bid Notification
Mitchell Enterprises, Ltd.Bid Notification
Moab Construction Company, IBid Notification
Mobil Construction CorporationBid Notification
Momentum ConcreteBid Notification
Morales Construction ServicesBid Notification
MORGAN REMINGTON INCBid Notification
Myers Concrete Construction LBid Notification
NBG Constructors, Inc.Bid Notification
Nelson Lewis, Inc.Bid Notification
New York Real Estate, Inc.Bid Notification
NNAC Construction Inc.Bid Notification
North America Procurement CoBid Notification
North American Paving, Inc.Bid Notification
NORTH TX CONSTRUCTION R Bid Notification
O.G. Construction Co.,LLCBid Notification
OHL USABid Notification
Oldcastle Pavement SolutionsBid Notification
On Guard Veteran ServicesBid Notification
OnviaBid Notification
Padre Island Property Managem Bid Notification
Paradigm Traffic Systems, Inc.Bid Notification
Patin ConstructionBid Notification
Pavecon Public WorksBid Notification
Pavecon Public Works, LPBid Notification
Pavement Maintenance Unlimit Bid Notification
Perkens WS CorporationBid Notification
Pesado ConstructionBid Notification
Pfeiffer & Son, Ltd.Bid Notification
Presidio Contracting LLCBid Notification
Primoris Services CorporationBid Notification
Professional Coating Technolog Bid Notification
Professional RestorationBid Notification
Professional Traffic ControlBid Notification
Proficient Constructors, LLCBid Notification
Progressive Structures, Inc.Bid Notification
QC Laboratoires, Inc.Bid Notification
Quality Excavation, Ltd.Bid Notification
Quanta Building Group, LLCBid Notification
R J Construction Company, IncBid Notification
R.D. Howard, LLCBid Notification
MARC III General Contractors, Bid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
R.K. Hall, LLC.Bid Notification
Raba Kistner InfrastructureBid Notification
Raba Kistner, Inc.Bid Notification
RAC Industries, LLCBid Notification
Ragle Inc.Bid Notification
RAGLE INC.Bid Notification
Rambo Contracting, INCBid Notification
RANGER Excavating, LPBid Notification
RBR Infrastructure & Road, LLCBid Notification
Rebcon, INcBid Notification
Recio UtiliitesBid Notification
Red Baron Building Municipal P Bid Notification
Red Baron Supply CoBid Notification
Redi-Mix ConcreteBid Notification
Redro Construction LLCBid Notification
Redwood Industries Bid Notification
RELIABLE COMMERCIAL CONBid Notification
Reliance ConstructionBid Notification
Rexco Inc.Bid Notification
Reyes GroupBid Notification
REYES GROUPBid Notification
Reynolds & Kay, Ltd.Bid Notification
Reynolds Asphalt & Constructio Bid Notification
Reytec Construction Resources Bid Notification
Reytech Services LLCBid Notification
Rimkus Consutling Group, Inc. Bid Notification
Rise Up refuse LLC Bid Notification
Roth Excavating Inc.Bid Notification
Royal Media Network Inc.Bid Notification
RP GlobalBid Notification
R-Tex ServicesBid Notification
Rucoba & Maya Construction, LBid Notification
S.J. Louis Construction of Texa Bid Notification
Salinas Construction TechnologBid Notification
SAMES, INC.Bid Notification
SANTOS CONSTRUCTION INCBid Notification
School Wholesale Supplies LLCBid Notification
Scott Tucker Construction ComBid Notification
SCR Civil Construction, LLCBid Notification
SDM Construction and Develop Bid Notification
SER Construction Partners, LLCBid Notification
Shallow Ford Construction Co., Bid Notification
Sherwood Design EngineersBid Notification
Shorty, Inc.Bid Notification
Silver Creek Construction, Inc.Bid Notification
SJ&J CONSTRUCTION, LLCBid Notification
SKE Construction, LLCBid Notification
SmartProcureBid Notification
Smith ContractingBid Notification
South Houston Asphalt & Conc Bid Notification
South Ranger Construction IncBid Notification
South Texas Steel Service ComBid Notification
Southern Road & BridgeBid Notification
SpawGlass Civil Construction, Bid Notification
SpawGlass Contractors, Inc.Bid Notification
SPI Asphalt LLCBid Notification
Stabile & Winn, Inc.Bid Notification
NOTIFICATIONS, cont'd
Vendor NameReason
Steve JordanBid Notification
Stoic Civil Construction, Inc.Bid Notification
Storm Reconstruction services, Bid Notification
Strategic Partnerships, Inc.Bid Notification
Structural AssuranceBid Notification
Sundt Construction, Inc.Bid Notification
Superior GroutingBid Notification
SYB CONSTRUCTION COMPA Bid Notification
T&TBid Notification
Tandem Services, LLCBid Notification
Taylor & Taylor ConstructionBid Notification
Teamwork Construction Service Bid Notification
Tejas Premier Building Contrac Bid Notification
Texas Cordia Construction, LLCBid Notification
texas diamond construction llcBid Notification
Texas Standard Construction, LBid Notification
Texas Sterling ConstructionBid Notification
TexOp Construction LPBid Notification
TFR Enterprises, IncBid Notification
The Bid CalendarBid Notification
The Blue Book Building & Cons Bid Notification
The Fain Group, Inc.Bid Notification
The Fierro GroupBid Notification
The Sandoval Group LLCBid Notification
Thirty-O-SixBid Notification
Thyssen-Laughlin, Inc.Bid Notification
Tierra Lease ServiceBid Notification
TIKON GROUP INC.Bid Notification
TLC EngineeringBid Notification
TLC Trucking & Contracting, InBid Notification
TNSBid Notification
TOPCOR Companies, LLCBid Notification
Trevway, Inc.Bid Notification
Tri-Con ServicesBid Notification
Triple OG Enterprises LLCBid Notification
Tropical Contracting, LLCBid Notification
TTG Utilities, LPBid Notification
Twincrest, Inc.Bid Notification
TX Hydro Industrial Services, LBid Notification
UFL Inc.Bid Notification
United Electrical Contractors InBid Notification
urban infraconstruction llcBid Notification
V.K. Knowlton Construction & U Bid Notification
Vick Operating Co, LLCBid Notification
Viking Construction, IncBid Notification
W.G. Yates & Sons Constructio Bid Notification
Walenta's ConstructionBid Notification
Walter P Moore and Associates Bid Notification
Water Experts of Texas Irrigatio Bid Notification
Webber LLCBid Notification
WebtechBid Notification
Westar Construction Inc.Bid Notification
Woody Contractors, Inc.Bid Notification
WP MURPHY INCBid Notification
WPM Construction Services, InBid Notification
xit paving and construction, incBid Notification
Yes America Now, IncBid Notification
Yoko Excavating, LLCBid Notification
BSFB!2
BSFB
BSFB!2
QMBOOFE!GPS
NJMM!BOE!PWFSMBZ
BSFB!3!
QMBOOFE!GPS!
DPNQMFUF!SFDPOTUSVDUJPO
REQUEST FOR CITY COUNCIL AGENDA ITEM
Appropriation
Agenda Date Requested: May 11, 2020
Source of Funds: N/A
Requested By: Mayor Rigby
Department: City Council
Account Number:
Amount Budgeted:
Report Resolution Ordinance
Amount Requested:
Exhibits: N/A
Budgeted Item: Yes No
SUMMARY
Following the consideration of appointments at the April 27 Council meeting, it was
noted that in the past the ZBOA custom has frequently been to move Alternate seat
holders up, if they feel comfortable doing so, and appointing a new member to the
remaining Alternate seat. Planning has confirmed that the Alternates are happy to move
up.
The motion at the April 27 meeting was to appoint Mr. Blakemor
on the Board. Mr. Blakemore was notified of the consideration and stands ready to
serve in any capacity.
RECOMMENDED MOTION
Should the wish be to make a motion in accordance with the ZBOA
appointments, otherwise the motion can be modified as the maker wishes and made
that way instead. - I move the appointment of Alternate 1 Phillip Hoot to the
Position 1, Alternate 2 Pat McCabe to Alternate 1, and John Blakemore to the
Alternate 2 position on the La Porte Zoning Board of Adjustment. \[This motion
does not require a second.\]
REQUEST FOR CITY COUNCIL AGENDA ITEM
Appropriation
Agenda Date Requested: May 11, 2020
Requested By: Source of Funds: N/A
Jason Weeks, Asst City Mgr
Department:
Administration/CMO
Account Number: N/A
Amount Budgeted: $61,547,698
Report Resolution Ordinance
Amount Requested: N/A
nd
Exhibits: CIP 2 Quarter Update
Budgeted Item: Yes No
SUMMARY
stth
through September 30. The City of La Porte
Capital Improvement Plan (CIP) program for the second quarter of fiscal year 2019-20,
which includes activity from October 1, 2019 through March 31, 2020 has been included
for you to review; therefore, the report is cumulative as the fiscal year progresses.
The attached CIP Update includes several documents:
Spreadsheet summary listing all outstanding Capital Projects as of October 1,
2019, with activity through March 31, 2020. This spreadsheet is broken down
between the different types of Capital Projects:
o SEW Sewer Projects
o AI Airport Projects
o DR Drainage Projects
o EMS EMS Project
o F216 F216 Drainage Project
o FD Fire Department Project
o UTL Utility Projects
o GEN General CIP Projects
o GC Golf Course Projects
o AD Administration Projects
o SM Street Maintenance Projects
o PR Parks & Recreation Projects
o PW Public Works Projects
o STR Street Projects
Individual Project sheets, which include: 1) project number & name; 2) account
number; 3) funding summary by fiscal year for budget, expenditures,
encumbrances and remaining budget; 4) project description; and 5) narrative of
quarter activity including any photos or diagrams.
The City of La Porte prior to FY 2019-20 had budgeted $39.6 million for capital projects
city-wide. In FY 2019-20, the City Council allocated $21.9 million for capital projects,
which brought the total budget for the CIP program to $62 million. Prior to FY 2019-20
the City had spent $12.3 million on these capital projects. As of March 31, 2020, the
City had spent/encumbered $6.5 million on capital projects this fiscal year. Project to-
date, the City has spent $18.8 million on the CIP programed projects included in this
update. As of March 31, 2020, the remaining budget to spend on these projects was
$42.7 million. Below is a summary of the City of La Porte CIP program by CIP Type.
Budget Thru FY 2019-20 Total Project To-Budget
CIP Type FY19 Budget Budget Date Spent Balance
Administration $0 $375,919 $375,919 $175,954 $199,965
Airport $530,000 $0 $530,000 $362,862 $167,138
$847,000 $9,505,000 $10,352,000 443,846 $9,908,154
Drainage
EMS $0 $583,000 $583,000 $67,910 $515,090
F216 $2,360,864 $0 $2,360,864 $1,005,632 $1,355,232
Fire Field $0 $1,200,000 $1,200,000 $9,500 $1,190,500
Golf Course $79,000 $169,000 $248,000 $50,675 $197,325
General CIP $4,978,432 $663,000 $5,641,432 $3,812,378 $1,829,054
M Street TIRZ $0 $1,500,000 $1,500,000 $0 $1,500,000
Parks & Rec $5,248,287 $893,950 $6,142,237 $1,596,001 $4,546,236
Public Works $21,090,860 $2,685,000 $23,775,860 $5,372,203 $18,403,657
Sewer $0 $300,000 $300,000 $178,732 $121,268
Street Maint $2,710,000 $1,060,000 $3,770,000 $3,335,143 $434,857
Street $139,340 $2,545,000 $2,684,340 $505,363 $2,178,977
Utility $1,629,046 $455,000 $2,084,046 $1,913,129 $170,919
TOTAL $39,612,829 $21,934,869 $61,547,698 $18,829,328 $42,718,372
nd
The CIP 2 Quarter Update document is attached to provide City Council with more
ram. Staff will be available to answer any questions
City Council may have concerning specific CIP Projects. Additionally, staff welcomes
any feedback on future formatting and/or added detail needed for the quarterly CIP
updates.
RECOMMENDED MOTION
No action is needed. Staff welcomes questions and feedback about the format
of the presentation.
Approved for the City Council meeting agenda
Corby D. Alexander, City Manager Date
List of Outstanding Capital Projects as of October 1, 2019 - With activity through March 31, 2020
BudgetExpendituresBalance
ProjectBudget thruActual thruActualEncumbrancesProjectBudget
Proj NumProject DescriptionFundLeaderFY 18-19FY 19-20TotalFY 18-19FY 19-20FY 19-20to DateFY 19-20
AD0004Upgrade Outdoor Warning Sirens & Control Unit015Gauither - 189,000 189,000 - - 175,954
175,954 13,046
AD0005Upgrade Flashing Roadway Signs015Gauither - 108,000 108,000 - - -
-108,000
AD0006City Hall Conference Room Expansion015Epting - 48,919 48,919 - - -
-48,919
AD0007Council Chambers AV Upgrade (Year 1)015Parker - 30,000 30,000 - - -
-30,000
Administration Total
- 375,919 375,919 - - 175,954 175,954 199,965
AIR001Runway, Taxi, Tie Down Rehabilitation Design010/032Mayo 300,000 - 300,000 19,538 136,899 -
156,437 143,563
AIR002Runway, Taxi, Tie Down Rehabilitation Construction010/015Mayo 200,000 - 200,000 192,283 -
- 192,283 7,717
AIR003Construct Drainage Improvements010Mayo 30,000 - 30,000 14,142 - - 14,142
15,858
Airport Total 530,000 - 530,000 225,963 136,899 - 362,862 167,138
DR0001TV Insprection of Storm Sewer System019Mayo 60,000 30,000 90,000 40,671 820 19,180 60,671
29,329
DR0004Drainage Materials (in-house)019Mayo 120,000 75,000 195,000 64,288 5,503 - 69,791 125,209
C DR0005Verify City Elevation Benchmarks019Mayo 27,000 - 27,000 - 15,360 9,140 24,500
2,500
DR0006Brookglen Drainage - Design & Construction (HMGP)015/019Mayo 275,000 4,000,000 4,275,000 - -
- -4,275,000
DR0007Bayside Terrace Drainage Improvements Design (HMGP)015/019Mayo 100,000 2,200,000 2,300,000 - - 252,383
252,383 2,047,617
DR0008F101 Lomax Drainage Improvements Design (HMGP)015/019Mayo 150,000 3,200,000 3,350,000 - - -
-3,350,000
DR0009Batleground Estates Drainage Improvements Design019Mayo 65,000 - 65,000 - -
- -65,000
C
DR0010Bob's Gully Drainage Analysis019Mayo 50,000 - 50,000 35,720 - 780 36,500
13,500
Drainage Total 847,000 9,505,000 10,352,000 140,680 21,683 281,483 443,846 9,908,154
EMS001EMS Headquarter Expansion015Mayo - 583,000 583,000 - - 67,910 67,910 515,090
F216F216 Phase 2 - Little Cedar Bayou Drainage019/032/050Mayo 2,360,864 - 2,360,864 908,888 - 96,744
1,005,632 1,355,232
FD0002Fire Field Propane Project015Gifford - 1,200,000 1,200,000 - 9,500 - 9,5001,190,500
GC0002Golf Maintenance Building Improvement015Stoker 51,000 - 51,000 35,000 - 15,675
50,675 325
GC0003Clubhouse Repairs015Stoker 28,000 - 28,000 - - - -28,000
GC0004Golf Course Land Improvements015Stoker - 169,000 169,000 - - -
-169,000
Golf Course Total 79,000 169,000 248,000 35,000 - 15,675 50,675 197,325
GEN620Dr. Martin Luther King, Jr. Park Replacement015Epting 95,000 - 95,000 66,787 43 -
66,830 28,170
GEN641SunGard ONE Solution - Phase I015 Dolby 50,000 - 50,000 28,938 - -
28,938 21,062
GEN656Emergency Prepardness/Generators015Mayo 2,400,000 - 2,400,000 2,184,806 - - 2,184,806 215,194
GEN661Golf Course Fairway Upgrade015Stoker 170,000 - 170,000 128,893 - - 128,893
41,107
1
List of Outstanding Capital Projects as of October 1, 2019 - With activity through March 31, 2020
BudgetExpendituresBalance
ProjectBudget thruActual thruActualEncumbrancesProjectBudget
Proj NumProject DescriptionFundLeaderFY 18-19FY 19-20TotalFY 18-19FY 19-20FY 19-20to DateFY 19-20
GEN671Infill Sidewalk015Mayo - 223,000 223,000 - - - -223,000
GEN675Community Coop Projects015Weeks 30,000 - 30,000 9,161 - - 9,16120,839
*GEN683Concrete Repair Slab Jacking033Mayo - 40,000 40,000 - - 15,898 15,898
24,103
GEN684Concrete Repair (Small Sections)033Mayo 1,050,000 200,000 1,250,000 493,665 - 8,737 502,402 747,598
GEN693City Hall Renovations015Epting 75,763 - 75,763 45,561 - - 45,561 30,202
GEN927Handicap Ramp/sidewalks033Mayo 700,000 200,000 900,000 530,215 58,996 25,408 614,619 285,381
GEN993Enhancement Grants015Weeks 407,669 - 407,669 215,270 - - 215,270 192,399
General Total 4,978,432 663,000 5,641,432 3,703,297 59,038 50,043 3,812,378 1,829,054
MSTRM Street - TIRZ Project015Mayo - 1,500,000 1,500,000 - - - -1,500,000
PR0006Northwest Pool Improvements015Epting 905,435 - 905,435 787,680 - - 787,680
117,755
PR0007Wave Pool Renovation (Year 2)015Epting 660,000 250,000 910,000 481,494 - - 481,494
428,506
PR0008Design Services for Recreation Center Expansion015Epting 3,202,152 - 3,202,152 44,562 25,051 223,635
293,247 2,908,905
PR0011Decorative Broadway Lighting (EDC Funded)015Epting 480,700 - 480,700 - 22,499 11,081
33,580 447,120
PR0012Park Lighting Project (Year 1 - Northwest Park)015Epting - 523,950 523,950 - -
- -523,950
PR0013Library Improvements015Epting - 120,000 120,000 - - -
-120,000
Parks & Recreation Total 5,248,287 893,950 6,142,237 1,313,735 47,550 234,716 1,596,001 4,546,236
C
PW0002Sens Road Utility Relocation003Mayo 160,000 - 160,000 - - 160,000 160,000
-
PW0006Design & Replacement for Hillridge Booster Pump003Mayo 100,000 - 100,000 93,895 - -
93,895 6,105
PW0009Coupland Drive Improvements019/033/051Mayo 1,310,000 - 1,310,000 117,907 1,786 60,713 180,406 1,129,594
PW0012Lomax Lift Station Consolidation 051/052Mayo 10,195,000 - 10,195,000 505,441 145,220 39,691 690,352 9,504,648
PW0015Restroom/Pavilion at Five Points015Mayo 400,000 350,000 750,000 23,109 50,036 28,964 102,109 647,891
C PW0016Parking Spaces at Pecan Park015Mayo 350,000 - 350,000 295,197 - 18,252 313,449 36,551
C PW0017Fairmont Parkway Signalization Project015Mayo 1,500,000 - 1,500,000 - - -
-1,500,000
PW0018Drainage Interconnect at Lakes at Fairmont Green015Mayo 250,000 - 250,000 - - -
-250,000
PW0020Fencing on Spencer Highway015Mayo 680,400 560,000 1,240,400 57,314 - 372,661 429,975 810,425
PW0023Commercial Water Meter Replacement003Mayo 95,000 25,000 120,000 46,068 - -
46,068 73,932
PW0027Design for Drainage Improvements (6th St/N Madison & W. Main)051/032Mayo 400,000 - 400,000 55,131 43,809
26,721 125,661 274,340
003/015/050
/051
C PW0028Design Somerton ImprovementsMayo 2,350,000 - 2,350,000 921,223 253,837 79,905 1,254,964 1,095,036
PW0029Main Street Sidewalk Repairs015Mayo 15,000 - 15,000 - - 15,000 15,000
-
PW0032Construct N. 6th/Main to Tyler and Main St Drainage003/050Mayo 990,000 - 990,000 - -
- -990,000
PW0033Hillridge Pump Station Construction Phase 1003Mayo 1,235,460 - 1,235,460 7,875 3,944 1,087,953 1,099,771
135,689
PW0034Aerial Crossings003Mayo 165,000 50,000 215,000 12,916 - - 12,916 202,084
PW0041Public Works Facility Assessment015Mayo 65,000 75,000 140,000 24,435 19,054 5,896 49,385 90,615
2
List of Outstanding Capital Projects as of October 1, 2019 - With activity through March 31, 2020
BudgetExpendituresBalance
ProjectBudget thruActual thruActualEncumbrancesProjectBudget
Proj NumProject DescriptionFundLeaderFY 18-19FY 19-20TotalFY 18-19FY 19-20FY 19-20to DateFY 19-20
PW0043East Main Street Sidewalk (Prefunding)015Mayo 430,000 - 430,000 29,839 8,168 278,120 316,127
113,873
PW0044Replace Ground Tank - Collegeview Water Plant003Mayo 350,000 - 350,000 20,000 297,250 35,550 352,800
(2,800)
PW0046Pumps & Equipment Replacement003Mayo 50,000 50,000 100,000 9,500 - - 9,50090,500
PW004725th Street Water Plant Generator (HMGP)015\\032Mayo - 425,000 425,000 - - -
-425,000
PW0048Lift Station 40 Generator (HMGP)015/032Mayo - 235,000 235,000 - - -
-235,000
PW0049Replace Ground Tank - Hillridge Water Plant003Mayo - 300,000 300,000 - 20,000 10,000
30,000 270,000
PW0050Coating Lomax Water Tower003Mayo - 600,000 600,000 - 50,000 25,000 75,000 525,000
C
PW0051Replace Heaters in Dewatering Building - WWTP003Mayo - 15,000 15,000 - 14,825 -
14,825 175
Public Works Total 21,090,860 2,685,000 23,775,860 2,219,849 907,929 2,244,425 5,372,203 18,403,657
*SEW669Sanitary Sewer Rehabilitation 018Mayo - 300,000 300,000 - 29,948 148,784 178,732 121,268
*SM0002Asphalt Street Surfacing033Mayo - 630,000 630,000 - 318,005 - 318,005 311,995
SM0003Street Repair Material (in-house)033Mayo 150,000 50,000 200,000 124,063 3,097 5,903 133,063 66,937
C
SM0004Pinebluff Subdivision Improvements033/051Mayo 2,000,000 - 2,000,000 1,950,544 6,304 22,705 1,979,553 20,447
SM0007Construct Sylvan and Jefferson Paving and Construction015/003/033Mayo 560,000 380,000 940,000 3,662 4,184 896,676
904,522 35,478
Street Maintenance Total 2,710,000 1,060,000 3,770,000 2,078,269 331,590 925,285 3,335,143 434,857
STR7THSouth 7th Street Paving and Drainage003/033Mayo 139,340 2,435,000 2,574,340 139,340 173,557 192,466 505,363 2,068,977
STRLCBLittle Cedar Bayou Drive Concrete Paving033Mayo - 110,000 110,000 - - -
-110,000
STR Total 139,340 2,545,000 2,684,340 139,340 173,557 192,466 505,363 2,178,977
UTL655Meter Replacement Program003Dolby 1,489,046 350,000 1,839,046 1,452,536 40,952 309,048 1,802,536 36,511
UTL697Valve Replacement Program (In-House)003Mayo 140,000 25,000 165,000 79,054 11,377 - 90,431
74,569
*UTL760Lift Station Improvements003Mayo - 35,000 35,000 - - 15,524 15,524 19,476
*UTL898In House Waterline Replacement 003Mayo - 45,000 45,000 - 4,638 - 4,63840,362
Utility Total 1,629,046 455,000 2,084,046 1,531,589 56,967 324,572 1, 913,129170,917
39,612,829 21,934,869 61,547,698 12,296,609 1,774,661 4,758,057 18,829,327 42,718,371
CCompleted Projects - will be closed out at end of fiscal year.
*Budget allocated for these projects does not roll forward each year.
Expenditures reported for FY19-20 were incurred prior to March 31, 2020. Expenditures posted after this date will be reflected on the next monthly report.
3
Project AD0004 – Upgrade Outdoor Waring Sirens & Control Unit
Account Number: 0156054-510Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 189,000$ -$ 175,954
Total$ 189,000$ -$ 175,954 $ 13,046
P ROJECT D ESCRIPTION
The City has a total of thirteen (13) outdoor warning sirens. In 2000, the City began replacing one
original siren a year over an 11-year period. During this time, the LEPC purchased two (2)
additional sirens for the City, making a total of thirteen (13). The last siren upgrade was completed
in 2012. Some of our current sirens are nearly 20 years old. The equipment is outdated and
maintenance intensive. Staff has been working to maintain the sirens each year, but believes it is
time for an upgrade of the system. One siren was substantially upgraded in 2018, so staff is
proposing replacement or significant repairs of the remaining twelve (12) sirens in the next fiscal
year. Also, staff is proposing that the City purchase a control unit that will allow staff the
opportunity to monitor the status of the sirens from Dispatch 24/7. This will allow the City to quickly
identify when there is an issue with one of the sirens, so that it can be addressed in a more timely
and effective manner. The sirens were discussed as part of OEM’s presentation at the Council
budget retreat.
F IRST Q UARTER FY19-20
During the first quarter, staff worked with the Purchasing Department to develop a scope of work
and Request for Proposals (RFP) for this project. This process was completed, and one vendor
responded with a proposal. Staff will bring this item before City Council on January 27, 2020. The
image below shows each siren location and coverage area. Siren #7 was not included in this
scope of work due to substantial upgrades over the last two years.
S ECOND Q UARTER FY19-20
The Request for Proposal was approved by City Council on January 27, 2020. Once
approved, Purchasing staff began working to develop and execute a contract with the vendor.
The contract was been signed by both parties. The vendor then ordered parts for all repairs,
and stated it could take approximately eight (8) weeks to receive all parts. Staff contacted the
th
vendor for a status update on April 7, and was told the parts had not yet been delivered.
Other than potential delays in shipping, this project has not been impacted by the current
situation related to COVID-19. According to the vendor, the work is not on hold, and will begin
as soon as the parts are received.
4
5
Project AD0005 – Upgrade Flashing Roadway Signs
Account Number: 0156054-510Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 108,000$ -$ -
Total$ 108,000$ -$ -$ 108,000
P ROJECT D ESCRIPTION
In 2008, the LEPC purchased and installed nine (9) Flashing Roadway Signs for the City of La
Porte at various locations throughout the city. These signs were intended to alert drivers to an
emergency situation, and direct them to AM 830 to listen for more information. Today, the signs
are not in good working order, and the process of referring drivers to AM 830 is outdated. The
radio station is not managed by the City of La Porte, so the City cannot ensure it is always working
properly. In addition, staff feels it would be more effective to provide an emergency announcement
to drivers, including protective actions that should be taken. While the signs can be used for
emergency situations (i.e. Shelter in Place, Flash Flood Warning, Tornado Warning, Mandatory
Evacuation Order, etc.), they can also be used for day-to-day community messaging. This would
allow the City to promote various events and City activities along roadways throughout the City.
This initial request is to upgrade six (6) of the original signs, but the system can be expanded in
the future, if desired. The signs would be used to promote citywide events and to attract visitors to
La Porte to stay and shop. Staff feels this project would be beneficial, not only for public
communications, but also for improving aesthetics at the proposed locations.
F IRST Q UARTER FY19-20
This first quarter of FY 19-20, the Office of Emergency Management staff have been working with
the IT Manager and Marketing Coordinator to establish the pole and sign design before moving
forward with the purchasing process. The goal is to ensure consideration of the sign’s aesthetics in
order to be consistent with other decorative poles in the city. Staff will be meeting with the
Purchasing Department again before the end of January 2020 to begin the purchasing process.
S ECOND Q UARTER FY19-20
Staff continued to work with the IT Manager and Marketing Coordinator to seek various
options for the design of the signs. Staff intends to present each option to City Council for
consideration. The options do vary in terms of cost. Since the signs will be in place
indefinitely, staff felt it was important to spend more time considering the overall look and
functionality of the signs. Staff received initial pricing for the different options. Prior to the
COVID-19 pandemic, the IT Manager had been working with CenterPoint to get a quote for
how much it would cost to ensure the availability of electricity at each site. To date, staff has
not received this information from CenterPoint. The IT Manager is following up with
CenterPoint, but staff understands this aspect of the project may be put on hold for reasons
associated with COVID-19. Once staff receives all pricing information, we can work to present
the project to City Council for further consideration.
6
Project AD0006 – City Hall Conference Room Expansion
Account Number: 0150156060-510Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20 48,919 - -
Total$ 48,919$ -$ -$ 48,919
P ROJECT D ESCRIPTION
This project is to create additional space in the conference room across from the City Manager’s
Suite and to add four additional office spaces in the Planning hallway. There is limited availability to
have large group meetings in City Hall. Twice a month, the City Manager’s Office has executive staff
meetings that are required to be held at Fire Station #1 due to limited space within City Hall.
Additionally, on Tuesday pre-development meetings, the space within City Hall continues to be a
problem with standing room only and not enough space for all needed staff to attend the meeting.
Based on the current layout of City Hall the best option was to double the conference room space in
the conference room across from the City Manager’s suite and then remove the cubicle area along
the Planning hallway and convert those to four (4) office spaces.
F IRST Q UARTER FY 19-20
No update this quarter.
S ECOND Q UARTER FY19-20
Quote forms were sent out for build-out contractors and electricians. No quotes have been received.
During the third quarter, staff will add dimensions to the drawings and resend the quotes forms.
7
Project AD0007 – Council Chambers AV Upgrade (Year1)
Account Number: 0155051-522Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 30,000$ -$ -
Total$ 30,000$ -$ -$ 30,000
P ROJECT D ESCRIPTION
Due to aging equipment, the Information Technology Department with CSO input has planned to
upgrade the City Council Chambers audio video equipment. This is a planned 2-year project with
partial funding in FY 2019-20 and the remaining funding coming in FY 2020-21. Staff will be starting
this project in FY 2020-21 during the month of December 2020. The thought behind waiting was to
ensure there is no interruption of any scheduled City Council and/or Board meetings. The scope of the
project will be to replace the audio system with a newer more user-friendly system. The new system
will be relocated into the back storage closet instead of under the City Council dais. Along with
upgrading the audio equipment, staff will upgrade the City Council microphones, audience-facing
speakers and include City Council and audience facing cameras. Also, staff will work with the City’s
Facility Maintenance Department to create a more user-friendly dais, which will allow a better writing
surface and allow the existing display monitors to be recessed into the current wells. Additionally, staff
will update the existing three audience video displays with a newer larger set. This will allow the
audience to see presentations clearer in the future meetings.
F IRST Q UARTER FY19-20
No activity during first quarter FY 2019-20.
S ECOND Q UARTER FY 19-20
Due to the COVID-19 pandemic, staff has been working remotely; therefore, there has been no activity
during the second quarter FY 2019-20. However, staff worked to provide a solution to remote meetings
due to the social distancing requirements of COVID-19. Staff set-up a Zoom application account to
allow remote meetings to occur at staff and City Council level. In addition, staff utilized a security
camera in the Council Chambers to broadcast live meetings in the Council Chambers. With the Zoom
application subscription there is capability for the Council meetings to be broadcast on Facebook,
which will be discussed at a future City Council meeting.
8
Project AIR002 – Runway, Taxi, Tie Down Rehabilitation Construction
Account Number: 010/0157077-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 200,000$ -$ -
Fiscal Year 18-19 - 192,283 -
Fiscal Year 19-20 - - -
Total$ 200,000$ 192,283$ -$ 7,717
Project Description
This project includes design for the rehabilitation of the Airport runways, taxiways, and tie downs.
The condition of the runways is fair. However, with pro-active maintenance, the extremely high
cost to completely remove existing material and replace can be avoided. The total budget is
$200,000 with supplemental funding in Fund 015 (Utility Fund) in the amount of $7,717. The
overall total project budget is $2,000,000. The project is grant funded and the City’s share is 10%.
The remainder of the funding is located in Fund 032 (Grand Fund) and Fund 015 (Utility Fund).
Future Operating Impact: Completing rehabilitation in the next few years will help the City avoid
a very costly complete reconstruction of the runways, taxiways, etc. in the future.
First Quarter FY 19-20
During the first quarter FY 19-20, the project was awarded to Maxwell Asphalt Inc. The ‘Notice to
Proceed’ was issued on December 16, 2019. Staff anticipates onsite work to begin week of
January 27, 2020.
Second Quarter FY 19-20
Approximately 70% of pavement repairs were completed at the airport during the second quarter.
9
Project AIR003 – Construct Drainage Improvements
Account Number: 0107077-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 30,000 $ -$ -
Fiscal Year 18-19 - 14,142 -
Fiscal Year 19-20 - - -
Total$ 30,000 $ 14,142$ -$ 15,858
Project Description
This project will fund future drainage improvements, as identified by the drainage study.
Future Operating Impact: None.
First Quarter FY 19-20
During the first quarter FY 19-20, the project was awarded to Maxwell Asphalt Inc. The ‘Notice to
Proceed’ was issued on December 16, 2019. Staff anticipates onsite work to begin week of
January 27, 2020.
Second Quarter FY 19-20
During the second quarter, the airport drainage improvements were 80% completed. Contractors
have install reinforced concrete pipe at Spencer Hwy. Airport detention pond is 50% complete.
10
Project AIR003 – Construct Drainage Improvements – Cont’d.
11
Project DR0001 – TV Inspection of Storm Sewer System
Account Number: 0199881-690Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 20,000 $ 23,029$ -
Fiscal Year 17-18 20,000 1,286 -
Fiscal Year 18-19 20,000 16,356 -
Fiscal Year 19-20 30,000 820 19,180
Total$ 90,000 $ 41,491$ 19,180$ 29,329
Project Description
This project will fund the continuation of a program initiated in mid-FY13. The goal is to inspect
and video the entire city storm sewer system over a 5-year time frame. The funding is to be utilized
for contract inspection and video.
Future Operating Impact: None
First Quarter FY 19-20
During the first quarter FY 2019-20, College View and Fairmont Park West were inspected, while
thth
“D” Street (South 8Street to South 5 Street) was completed.
Second Quarter FY 19-20
Hillridge was completed during the second quarter on March 24, 2020.
12
Project DR0004 – Drainage Materials (in-house)
Account Number: 0199881-690Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 60,000 $ 18,593$ -
Fiscal Year 18-19 60,000 45,695 -
Fiscal Year 19-20 75,000 3,692 -
Total$ 1 95,000$ 67,980$ -$ 127,020
Project Description
This project funds the purchase of materials for in-house drainage work.
Future Operating Impact: None
First Quarter FY 19-20
During the first quarter FY 19-20, staff purchased 48” HDPE materials for B106.
13
Project DR0004 – Drainage Materials (in-house), continued
Second Quarter FY 19-20
No activity this quarter.
14
Project DR0005 – Verify City Elevation Benchmarks
Account Number: 0199881-690Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19 27,000 - -
Fiscal Year 19-20 - 15,360 9,140
Total$ 27,000 $ 15,360$ 9,140$ 2,500
P ROJECT D ESCRIPTION
The National Flood Insurance Program Community Rating System requires that all City elevation
benchmarks be verified every 5 years. Currently, the City has 50 benchmarks requiring verification.
Participation in NFIP’s CRS program provides discounts to flood policy within La Porte.
Future Operating Impact: None
F IRST Q UARTER FY19-20
During the first quarter FY19-20 this project was completed. Surveyor recovered and updated
twenty-five (25) benchmarks. Other benchmarks were either redundant or not recovered.
However, recovered benchmarks provide necessary coverage across the entire City. All
associated files have been delivered and saved to the project files.
S ECOND Q UARTER FY 19-20
Project completed during second quarter FY 2019-20.
15
Project DR0006 – Brookglen Drainage – Design and Construction (HMGP) – City’s
Grant Match
Account Number: 0199881-690Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19 275,000 - -
Fiscal Year 19-20 4,000,000 - -
Total$ 4,275,000$ -$ -$ 4,275,000
P ROJECT D ESCRIPTION
This project will design and construct drainage improvements to mitigate the effect of flooding in
the Brookglen subdivision. Cost for this phase of the project is estimated at $4,000,000. The main
focus is along Willow Springs Bayou between Spencer Highway and Fairmont Parkway. Also, this
project will consider the effects of the planned drainage improvements downstream, adjacent to
the Pasadena Convention Center.
Future Operating Impact: None
F IRST Q UARTER FY 19-20
No activity this quarter.
S ECOND Q UARTER FY 19-20
Staff began coordinated local improvements with potential Harris County Flood Control District
(HCFCD) improvements. No progress this quarter.
16
Project DR0007 – Bayside Terrace Drainage Improvement – Design and
Construction (HMGP) – City’s Grant Match
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 100,000$ -$ -
Fiscal Year 19-20 2,200,000 - 252,383
Total$ 2,300,000$ -$ 252,383 $ 2,047,617
Project Description
This project will design and construct the needed improvements to redirect, provide adequate
capacity and improve drainage in the Bayside Terrace Subdivision. Total cost for this project is
estimated at $2,200,000. One-half of the 25% match is remaining portion in Fund 019.
Future Operating Impact: None
First Quarter FY 19-20
No update this quarter. However, at the December 9, 2019 City Council meeting, the City Council
authorized staff to utilize the grant match funds to initiate this project in lieu of waiting for potential
grant award.
S ECOND Q UARTER FY 19-20
During the second quarter the consultant issued “Notice To Proceed” for feasibility and preliminary
engineering. Also, the surveying was performed for feasibility and Preliminary Engineer Report.
17
Project DR0008 – F-101 Lomax Drainage Improvements - Design
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 150,000$ -$ -
Fiscal Year 19-20 3,200,000 - -
Total$ 3,350,000$ -$ -$ 3,350,000
Project Description
This project designs the improvements identified by the feasibility study conducted in 2018 by
KSA Engineers related to drainage improvements located in Lomax along F-101. Total project
cost estimated at $3,200,000.
Future Operating Impact: None
First Quarter FY 19-20
No update this quarter. Currently, Harris County is leading this project; City of La Porte will assist
as project develops.
S ECOND Q UARTER FY 19-20
Harris County has procured a consultant and has initiated the preliminary engineering report
phase. City will assist as project develops.
18
Project DR0009 – Battleground Estates Drainage Improvements Design
Account Number: 0199881-669Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 65,000 $ -$ -
Fiscal Year 19-20 - - -
Total$ 65,000 $ -$ -$ 65,000
Project Description
The drainage improvement project is focused on the Lomax Area north of “P” Street. Mitigation
efforts include adjustments to existing roadside ditches, increasing culvert sizes and drainage
channel improvements.
Future Operating Impact: None
First Quarter FY 19-20
No update this quarter. Awaiting grant award notification.
S ECOND Q UARTER FY 19-20
Again, no progress this quarter; staff awaiting grant award notification.
19
Project DR0010 – Bob’s Gully Drainage Analysis
Account Number: 0199881-669Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 50,000 $ 35,720$ 780
Fiscal Year 19-20
Total$ 50,000 $ 35,720$ 780$ 13,500
Project Description
This project will provide recommendations for drainage improvements to mitigate the effort of
flooding in East La Porte. Drainage in “B” Street ROW flows downstream to Bob’s Gully and
outfalls to Galveston Bay.
Future Operating Impact: None
First Quarter FY 19-20
This project was completed during the first quarter FY 19-20. Report evaluated the capacity of
Bob’s Gully and determined that Bob’s Gully has capacity for the 100-year event using the latest
rainfall data. A ponding analysis determined that local conveyance features impede the efficiency
of flows in the surrounding areas and contributes to localized ponding. The study indicates that
improvements to the local drainage network would also require improvements to Bob’s Gully.
S ECOND Q UARTER FY 19-20
This project was completed during the second quarter.
20
Project EMS001 – EMS Headquarter Expansion
Account Number: 0155059-522Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20 583,000 - -
Total$ 583,000$ -$ -$ 583,000
P ROJECT D ESCRIPTION
EMS Headquarters located at 10428 Spencer Highway was renovated in 2007 to house EMS
operations. EMS Headquarters is in need of expanding and remodeling in order to address an
outdated co-ed dormitory design and the lack of any training room area for paramedics to train.
F IRST Q UARTER FY 19-20
During first quarter FY 19-20, staff have been negotiating with a consultant for design phase and
construction phase services.
21
Project F216 – Phase 2 & 3 – Little Cedar Bayou Drainage
Account Number: 0159090-519Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 12-13$ 1,500,000$ 34,180$ -
Fiscal Year 13-14 - 345 -
Fiscal Year 14-15 - (1,845) -
Fiscal Year 15-16 - 175,404 -
Fiscal Year 16-17 35,864 196,372 -
Fiscal Year 17-18 56,868 -
Fiscal Year 18-19 825,000 447,564 -
Fiscal Year 19-20 - - 96,744
Total$ 2,360,864$ 908,888$ 96,744$ 1,355,232
P ROJECT D ESCRIPTION
This CDBG Ike grant funded project (round 2.1) will provide for the second phase of the Little
Cedar Bayou drainage improvements. Phase I was completed in 2011 and included a 28 acre
regional detention basin south of W. Main Street. Phase II consists of 1.3 miles of bayou widening
between W. Main and Sens Road. While the entire project is not contemplated in the upcoming
budget, the project scope will be derived from the 1.5 million of funds available from the grant.
The current scope will provide engineering of the entire project as well as acquisition and
construction of approximately 1000 linear feet working northward from W. Main Street. Tree
mitigation survivability contract signed for environmental clearance to proceed with ROW
acquisition.
Phase III – This project will fund construction for F216 improvements upstream of Madison Street
F IRST Q UARTER FY 19-20
No update this quarter. However, at the December 9, 2019 City Council meeting, City Council
authorized staff to utilize the grant match funds to initiate this project in lieu of waiting for potential
grant award.
S ECOND Q UARTER FY 19-20
No progress this quarter. However, Harris County Flood Control District (HCFCD) was in the
procurement phase of this project. Staff has been coordinating with HCFCD so that engineering
efforts are not duplicated.
22
Project FD0002 – Fire Field Propane Project
Account Number: 0155051-522Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 1,200,000$ 9,500$ -
Total$ 1,200,000$ 9,500$ -$ 1,190,500
P ROJECT D ESCRIPTION
Changes in National Fire Protection Association (NFPA) codes and the fact that the community is
growing toward the fire field, the La Porte Fire Department feels that it is time to upgrade the facilities
to propane. There are many advantages to using propane as oppose to ‘Class A’ type fuels. The
biggest advantage is propane props are safer than ‘Class A’ type fuels. Also, propane is better for the
environment and has no irritating smell.
F IRST Q UARTER FY19-20
During the first quarter of FY 2019-20, the fire field building had an NFPA inspection and everything
looked good for the project to proceed. La Porte Fire Department personnel met with four (4) venders
to walk the project and give insight to the scope and needs of the fire department. LPFD staff are in
the process of writing up specifications that will be used by the Purchasing Department to include in
formal bid package. The goal is to have bid package ready to go by the middle of January 2020.
S ECOND Q UARTER FY 19-20
Second quarter of FY 2019-20 has seen limited progress on the project due to the COVID-19
pandemic. Bid package has been put together and should be ready to send out by the end of April
2020.
23
Project GC0002 – Golf Maintenance Building Improvements
Account Number: 0156049-551Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 51,000$ -$ -
Fiscal Year 18-19 - 35,000 -
Fiscal Year 19-20 - - 15,675
Total$ 51,000$ 35,000$ 15,675$ 325
P ROJECT D ESCRIPTION
These funds will fund the replacement of the maintenance barn walls/roof and replacement of
base plates/doors. The proposed components for replacement are approximately 25 years old.
The total cost of the projects is $45,000. However, savings from FY 15-16 project to re-skin the
cart barn yielded substantial savings, which will be incorporated into the Maintenance Barn
project.
F IRST Q UARTER FY19-20
Staff has been working to construct an addition of an overhang to the North end of the
maintenance building to allow large equipment to be parked outside and protected from the
everyday weather. With this addition, it will relieve overcrowding in the maintenance facility. This
project is expected to be completed in second quarter FY 2019-20.
S ECOND Q UARTER FY 19-20
The overhang for the maintenance building is complete. Staff can now park larger equipment
underneath the overhang to eliminate overcrowding equipment in the maintenance facility.
Before Photos:
24
Project GC0002 – Golf Maintenance Building Improvements, continued
After Photos:
25
Project GC0003 – Clubhouse Repairs
Account Number: 0156049-551Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 28,000$ -$ -
Fiscal Year 19-20 - - -
Total$ 28,000$ -$ -$ 28,000
P ROJECT D ESCRIPTION
This project is to fund painting the Clubhouse for $20,000 and replacing counters and cabinets
for $8,000. These funds will be used to freshen up the Clubhouse. The outside and inside of the
clubhouse are in need of fresh paint.
F IRST Q UARTER FY19-20
No update this quarter.
S ECOND Q UARTER FY 19-20
Currently, staff is receiving quotes to have the interior and exterior of the clubhouse painted.
26
Project GC0004 – Golf Course Land Improvements
Account Number: 0156049-551Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 169,000$ -$ -
Total$ 169,000$ -$ -$ 169,000
P ROJECT D ESCRIPTION
This project will be used to address necessary infrastructure improvements at the golf course
including bridge replacement at Hole #8, cart path repair, culvert repair, bulkhead repair, and
an aeration system for the pond at the clubhouse entrance. These funds will be used to repair
existing bulkhead on Hole #11 and #15. Also reroute the cart path on Hole #11 so the bulkhead
can be tied into the bank for better stability. The culvert on Hole #17/18 will be repaired and
aeration system will be added to hole #1 one to circulate the water to help eliminate the algae
build up in the pond.
F IRST Q UARTER FY19-20
No update this quarter.
S ECOND Q UARTER FY 19-20
Staff will soon begin seeking quotes for bulkhead repair and cart path construction.
27
Project 620 – Dr. Martin Luther King, Jr. Park
Account Number: 015-9892-620Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 14-15$ 60,000$ 31,788$ -
Fiscal Year 15-16 35,000 34,999 -
Fiscal Year 16-17 - - -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - 1,772 -
Fiscal Year 19-20 - 43 -
Total$ 95,000$ 68,602$ -$ 26,398
P ROJECT D ESCRIPTION
This project will fund the replacement of playground equipment at Dr. Martin Luther King, Jr. Park.
Future Operating Impact: None
F IRST Q UARTER FY 19-20
The remaining funds from this project will be used for any additional expenses associated with the
Historic School House Project or sidewalks in the park. There is no update during the first quarter of
FY 19-20.
S ECOND Q UARTER FY19-20
The remaining funds from this project will be used for any additional expenses associated with the
Historic School House Project or sidewalks in the park. Staff continually looks for items to be
displayed in the Historic Schoolhouse.
28
Project 641 – SunGard ONE Solution – Phase 1
Account Number: 0159892-641Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 12-13$ 50,000 $ 28,938$ -
Fiscal Year 13-14 - - -
Fiscal Year 14-15 - - -
Fiscal Year 15-16 - - -
Fiscal Year 16-17 - - -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
$ 50,000 $ 28,938$ -$ 21,062
P ROJECT D ESCRIPTION
ONE Solution replaced the existing Naviline application by SunGard as the City’s primary business
application. ONE Solution is a Windows-based application, which provides greater functionality than
Naviline, while also allowing for a more intuitive and modern user experience. It is designed to be a
more streamlined application that takes advantage of current technology now available. Phase I
included implementation of Finance, Human Resources and Purchasing applications. Following
successful implementation of the Finance module, Community Service will be the next business
function to transition.
F IRST Q UARTER FY 19-20
Remaining funds will be used for future training for COGNOS upgrades. No activity during First
Quarter FY 2019-20.
S ECOND Q UARTER FY19-20
Remaining funds will be used for future training for COGNOS upgrades. The COGNOS training is yet
to be scheduled; we will train our accounting technicians:
29
Project 656 – Emergency Preparedness/Generators
Account Number: 0159892-656Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 12-13$ 1,100,000$ 135,104$ -
Fiscal Year 13-14 1,300,000 1,805,301 -
Fiscal Year 14-15 - 184,879 -
Fiscal Year 15-16 - 35,445 -
Fiscal Year 16-17 - 23,777 -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - 300 -
Fiscal Year 19-20 - - -
Total$ 2,400,000$ 2,184,806$ -$ 215,194
Project Description
This project is for the purchase of fixed generators at the Waste Water Treatment Plant to
improve resident return time after an emergency.
Future Operating Impact: An annual maintenance contract will be implemented once the
generators are in place; however, the cost is undetermined at this time.
First Quarter FY 19-20
The plan is to install a generator plug on the expansion side of treatment plant; however, staff is
awaiting an electrician to schedule this step.
30
Project 656 – Emergency Preparedness/Generators Cont.
Second Quarter FY 19-20
Generator plug has been installed at the treatment plant. No other activity during the second
quarter.
31
Project 661 – Golf Course Fairway Upgrade
Account Number: 0159892-661Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 12-13$ 170,000 $ 12,442$ -
Fiscal Year 13-14 - 28,007 -
Fiscal Year 14-15 - 33,843 -
Fiscal Year 15-16 - 22,665 -
Fiscal Year 16-17 - 17,200 -
Fiscal Year 17-18 - 14,736 -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
Total$ 170,000 $ 128,893$ -$ 41,107
P ROJECT D ESCRIPTION
This project was designed to renovate and level all fairways and add new irrigation where
necessary. This is an ongoing project that will be an annual project for several summers.
F IRST Q UARTER FY19-20
Staff anticipates that June 22-25of 2020, fairway #1 will be renovated. The hole will be set up as
a Par 3 to avoid closing the hole. This renovation is projected for 21,000 Bermuda grass so (50
pallets) and 120 yards of yellow bank sand.
S ECOND Q UARTER FY 19-20
Fairway renovation is still on schedule for June 22-25, 2020. Currently, staff is securing quotes
for sod. Once the project starts, staff will include pictures to highlight as the project progresses.
32
Project 671 – Infill Sidewalk
Account Number: 0159892-671Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 223,000$ -$ -
Total$ 223,000$ -$ -$ 223,000
Note: This project does not roll forward each year. A new amount is budgeted each year.
Project Description
This will be the first year of a multi-year project to extend/install sidewalk city-wide in areas of
need for infill.
Future Operating Impact: None
First Quarter FY 19-20
Staff began preparing bid package during first quarter FY 2019-20.
Second Quarter FY 19-20
During second quarter, staff still working on preparing bid package.
33
Project 675 – Community Coop Projects
Account Number: 015-9892-675Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 3 0,000$ 9,161$ -
Fiscal Year 19-20 - - -
Total$ 3 0,000$ 9,161$ -$ 20,839
P ROJECT D ESCRIPTION
Technically, this project is not a Capital Improvement Plan project for the City of La Porte. This
is more of a capital contribution that funds partnerships with neighborhood groups to complete
various community/neighborhood improvements. Projects should 1) benefit the entire
neighborhood, 2) consist of a number of categories such as beautification, landscaping,
safety/security, signage, electrical work for community amenities, recreational equipment and
lighting, and 3) those items that do not fit within these parameters will be evaluated on a case-
by-case basis, but must be used for public good. Moreover, these funds can’t be used for
ongoing maintenance to the neighborhood. Each project is considered on a first come, first
served basis and will be awarded a maximum of $5,000. However, in order for the
organization/association to be awarded the $5,000, they must spend $10,000 since this is a
50/50 matching project, with $5,000 as the maximum funded. Furthermore, no organization or
association may be funded twice in the same fiscal year, but may be awarded twice in the
same fiscal year. This is due to timing of request and completion of the project. Funding is
provided on a reimbursement basis and provided upon completion of the project.
Future Operating Impact: None.
F IRST Q UARTER FY 19-20
No activity in second quarter FY 2019-20.
S ECOND Q UARTER FY19-20
No activity in second quarter FY 2019-20.
34
Project 683 – Concrete Slab Jacking
Account Number: 0339892-683Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 40,000 $ -$ 15,898
Total$ 40,000 $ -$ 15,898$ 24,103
Note: This project does not roll forward each year. A new amount is budgeted each year.
Project Description
This annual program includes slab jacking at locations where settling has occurred on roadway
slab sections at locations throughout the City.
Future Operating Impact: None
First Quarter FY 19-20
No update this quarter.
Second Quarter FY 19-20
No Activity this quarter.
35
Project 684 – Concrete Repair (Small Sections)
Account Number: 0339892-684Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 13-14$ 100,000 $ -$ -
Fiscal Year 14-15 150,000 2,529 -
Fiscal Year 15-16 200,000 4,011 -
Fiscal Year 16-17 200,000 263,949 -
Fiscal Year 17-18 200,000 - -
Fiscal Year 18-19 200,000 223,176 -
Fiscal Year 19-20 200,000 - 8,737
Total$ 1,250,000$ 493,665$ 8,737$ 747,598
Project Description
This project includes funding for concrete repair on small sections of streets.
Future Operating Impact: None.
First Quarter FY 19-20
No update this quarter.
Second Quarter FY 19-20
This project is preparing to re-bid in third quarter.
36
Project 693 – City Hall Renovations
Account Number: 015-9892-693Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 14-15$ 20,000 $ -$ -
Fiscal Year 15-16 - - -
Fiscal Year 16-17 70,000 - -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 (14,237) - -
Fiscal Year 19-20 - 45,561 -
Total$ 75,763 $ 45,561$ -$ 30,202
P ROJECT D ESCRIPTION
In March 2013, a security assessment was completed by the La Porte Police Department on City
Hall. At that time, $20,000 was originally budgeted to address some of the security deficiencies that
were identified by the assessment. Initial plans were to secure and relocate the Inspections customer
service counter to the front lobby. After engaging an architect to provide plans for this relocation, it
became clear that additional changes were necessary. The project scope allows the City to enhance
the customer service experience by consolidating all customer related services in the front lobby,
allows staff to be more secure, and provides for relocation of staff that are currently working in remote
City facilities. The additional funding requested in FY17 budget added to those that have been
previously allocated and the City’s General Fund contingency account.
Future Operating Impact: None. The building footprint remains unchanged.
F IRST Q UARTER FY 19-20
No update this quarter. However, during the City Hall conference room and office space expansion,
this project will be considered as Phase II of that project with implementation of some security
features within City Hall.
S ECOND Q UARTER FY19-20
No update this quarter. However, during the City Hall conference room and office space expansion,
this project will be considered as Phase II of that project with implementation of some security
features within City Hall.
37
Project 927 – City Wheelchair Ramp/Sidewalk
Account Number: 0339892-927Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 300,000 $ 126,375$ -
Fiscal Year 17-18 200,000 285,621 -
Fiscal Year 18-19 200,000 118,220 -
Fiscal Year 19-20 200,000 58,996 25,408
Total$ 900,000 $ 589,212$ 25,408$ 285,380
P ROJECT D ESCRIPTION
This project will fund the replacement of sidewalks and installation of handicap ramps throughout
the City. This funding has been increased from previous years to allow the City to address more
areas of need per year.
Future Operating Impact: Minimal.
F IRST Q UARTER FY 19-20
Though this project is ongoing, staff has repaired a total of 9,685 SF of sidewalk in first quarter.
S ECOND Q UARTER FY19-20
During second quarter, 8,730 SF of sidewalk was replaced.
38
Project 693 – City Hall Renovations
Account Number: 015-9892-693Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 14-15$ 20,000 $ -$ -
Fiscal Year 15-16 - - -
Fiscal Year 16-17 70,000 - -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 (14,237) - -
Fiscal Year 19-20 - 45,561 -
Total$ 75,763 $ 45,561$ -$ 30,202
P ROJECT D ESCRIPTION
In March 2013, a security assessment was completed by the La Porte Police Department on City
Hall. At that time, $20,000 was originally budgeted to address some of the security deficiencies that
were identified by the assessment. Initial plans were to secure and relocate the Inspections customer
service counter to the front lobby. After engaging an architect to provide plans for this relocation, it
became clear that additional changes were necessary. The project scope allows the City to enhance
the customer service experience by consolidating all customer related services in the front lobby,
allows staff to be more secure, and provides for relocation of staff that are currently working in remote
City facilities. The additional funding requested in FY17 budget added to those that have been
previously allocated and the City’s General Fund contingency account.
Future Operating Impact: None. The building footprint remains unchanged.
F IRST Q UARTER FY 19-20
No update this quarter. However, during the City Hall conference room and office space expansion,
this project will be considered as Phase II of that project with implementation of some security features
within City Hall.
S ECOND Q UARTER FY19-20
Due to COVID-19 pandemic, staff had to utilize some funding from this project to install protective
glass at City Hall permit counter; however, the project will not be completed until next quarter. Again,
during the City Hall conference room and office space expansion, this project will be considered as
Phase II of that project with implementation of some other security features within City Hall.
39
Project MSTR- M Street – TIRZ Project
Account Number: 0157071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 1,500,000$ -$ -
Total$ 1,500,000$ -$ - $ 1,500,000
Project Description
This project will provide for the development of the “M” Street right-of-way between SH 146 and
th
S 16
Street. The project will consist of the construction approximately 1600 linear feet of concrete
pavement, 1,300 linear feet of twelve-inch (12”) waterline, 500 linear feet of eight-inch sanitary
sewer line, and 1,000 linear feet of storm sewer.
First Quarter FY 19-20
Staff reviewing the 30% plan submittal during first quarter FY 2019-20.
Second Quarter FY 19-20
No activity this quarter. Staff is awaiting 60% plans from consultant.
40
Project PR0006 – Northwest Pool Improvements
Account Number:0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 9 05,435$ 32,069 -
Fiscal Year 18-19 -755,610 -
Fiscal Year 19-20 - - -
Total$ 9 05,435$ 787,679$ -$ 117,756
P ROJECT D ESCRIPTION
The current buildings (restrooms, storage, pump house and guard room) are in very poor shape. The
building foundation has issues and the walls were starting to crack at the joints and between the
cinderblocks. Additionally, replastering the pool and re-decking the concrete are critical items as well.
The total project budget is $905,435 with supplement funding provided by Fund 038 (EDC).
F IRST Q UARTER FY 19-20
The remaining funds will be repurposed and used to purchase additional loungers and provide repairs
to the motor at the Wave Pool.
S ECOND Q UARTER FY19-20
No update this quarter.
41
Project PR0007 – Wave Pool Renovation
Account Number: 0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 410,000$ 67,680$ -
Fiscal Year 18-19250,000413,814 -
Fiscal Year 19-20250,000 - -
Total$ 910,000$ 481,494$ -$ 428,506
P ROJECT D ESCRIPTION
This project will fund replastering of the pool, replacement of tiles and decking, installation of a shade
structure with concrete pads, new umbrellas, and restroom upgrades. Included in this project is re-
plastering the pool, removing a cracked beam, changing the pool to a zero depth entry instead of a
small step down, installing drains, repairing coping, and repairing.
F IRST Q UARTER FY 19-20
No update this quarter. The City budgets $250,000 a year, for four years, to be set aside as prefunding
for the construction of a spray park feature in the Wave Pool area.
S ECOND Q UARTER FY19-20
No activity this quarter.
42
Project PR0008 – Design Services for Recreation Center Expansion
Account Number: 0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 500,000$ 30,475$ -
Fiscal Year 18-192,702,15214,087 -
Fiscal Year 19-20 - 25,051 223,635
Total$ 3,202,152$ 69,613$ 223,635$ 2,908,904
P ROJECT D ESCRIPTION
This project will increase the size of the facility to alleviate congestion during the busy times of the
day. Based on funding, the expansion request includes: tripling the size of the current cardio
equipment room, doubling the current size of the weight room, doubling the current of the aerobics
room, adding on additional basketball court, expanding the locker rooms as needed for anticipated
usage, adding storage, and upgrading HVAC so that it can sufficiently maintain the facility.
Future Operating Impact: Possible increased usage, increased utilities, increased cleaning need,
additional equipment and repairs, and additional staffing to keep up with the increased facility size
and attendance.
F IRST Q UARTER FY 19-20
This quarter staff worked with the consultant on a needs assessment for the current Recreation &
Fitness Center.
S ECOND Q UARTER FY19-20
Staff worked with the consultant regarding a membership survey, different property possibilities, and
different layouts. Staff also worked with the consultant for their presentation that will be made to City
Council.
43
Project PR0011 – Decorative Lighting
Account Number: 0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 480,700$ -$ -
Fiscal Year 19-20 - 22,499 11,081
Total$ 480,700$ 22,499$ 11,081$ 447,120
P ROJECT D ESCRIPTION
Decorative lighting, similar to the ones we currently have on the San Jacinto Trail, will be installed on
Broadway between Wharton Weems and Dwire. The length of the section is approximately 440 linear
feet and the lights would be spaced approximately every 100 feet.
F IRST Q UARTER FY 19-20
This quarter staff received the 100% design drawings. Staff will be reviewing the design drawings in
the second quarter and then go out to bid for the project.
S ECOND Q UARTER FY19-20
During second quarter this project went out for bid. However, due to COVID-19 pandemic, the bid
opening has been pushed to the third quarter FY 2019-20.
44
Project PR0012 – Park Lighting Project (year 1 – Northwest Park)
Account Number: 0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 523,950$ -$ -
Total$ 523,950$ -$ -$ 523,950
P ROJECT D ESCRIPTION
The current lighting poles are made of wood and many are leaning. This project would include 23 new
galvanized steel poles and 109 lights with 750W LED light Fixtures with visors. The new lights would
include a 10-year maintenance-free warranty. Once installed, the lights will be operated electronically
and have the ability to be scheduled when they are needed.
F IRST Q UARTER FY 19-20
Staff worked on the specifications for this project during the first quarter of FY 19-20. Staff will be
going out to bid during the second quarter of FY 19-20.
S ECOND Q UARTER FY19-20
During this quarter, staff contracted Huitt-Zollars for engineering services related to this project.
45
Project PR0013 – Library Improvements
Account Number: 0158080-552Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 120,000$ -$ -
Total$ 120,000$ -$ -$ 120,000
P ROJECT D ESCRIPTION
This project is to replace all flooring and repaint the Library. Currently, the carpet is worn, torn, and
stained. The vinyl composition tile is also outdated and worn. This project includes replacing all carpet
with carpet tiles that can be changed out individually when needed.
F IRST Q UARTER FY 19-20
Staff met with the painter and flooring company during the first quarter of FY 19-20. Staff anticipates
going out to bid during the second quarter of FY 19-20.
S ECOND Q UARTER FY19-20
During this quarter City Staff met with Library Staff to discuss how Library Staff would like to
reconfigure their shelving units. We also discussed room usage and flooring options.
46
Project PW0002 – Sens Road Utility Relocation
Account Number: 003-9890-697Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 14-15$ 160,000 $ -$ -
Fiscal Year 15-16 - - -
Fiscal Year 16-17 - - -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - -
Fiscal Year 19-20 - - 160,000
Total$ 160,000 $ -$ 160,000 $ -
Project Description
This project was authorized by City Council in February 2014 via an interlocal agreement with
Harris County in the amount of $158,792.03. The funding is necessary to reimburse Harris County
for the cost to remedy 70(+) city-owned utility conflicts associated with the proposed Harris
County projects to widen Sens Road. The proposed utility relocations include water services, fire
hydrants, water valves and sanitary sewer manhole rims to be adjusted to final grade.
Future Operating Impact: No additional operational impacts identified.
First Quarter FY 19-20
This project was completed during first quarter FY 19-20; however, staff is waiting for an invoice
from Harris County. Harris County extended timeline of project with change order.
47
Project PW0006 – Design and Replacement for Hillridge Booster Pump
Account Number: 0037085-533Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 15-16$ 100,000 $ -$ -
Fiscal Year 16-17 - 78,482 -
Fiscal Year 17-18 - 15,413 -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
Total$ 100,000 $ 93,895$ -$ 6,105
Project Description
This project will fund the proposed replacement of the Hillridge Booster Pumps and design a new
building. The current pumps are original and are approximately 50 years old. The new equipment will
add pumping capacity.
Future Operating Impact: None.
First Quarter FY 19-20
This project was awarded to W.W. Payton, Inc. The “Notice to Proceed” was issued on November
11, 2019. The project time for substantial completion is 350 days. Staff is in the process of
reviewing pump and motor submittals and anticipates field work to begin next quarter.
Second Quarter FY 19-20
During the second quarter the design was completed. Construction phase services are underway.
48
Project PW0009 – Coupland Drive Improvements.
Account Number: 019/033/051-7071-533Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 15-16$ 200,000$ 17,021$ -
Fiscal Year 16-17 1,110,000 12,096 -
Fiscal Year 17-18 - 27,960 -
Fiscal Year 18-19 - 60,830 -
Fiscal Year 19-20 - 1,786 60,713
Total$ 1,310,000$ 117,907$ 60,713 $ 1,129,594
Project Description
This project funds the design for proposed improvements on Coupland Drive, as well as the
acquisition of the required right-of-way for the project. The total project budget for design is
$200,000, which is shared between the Drainage Fund ($100,000) and the Street Maintenance
Fund ($100,000). Staff presented the construction phase of the project in the FY2017 budget for
consideration.
Future Operating Impact: None.
First Quarter FY 19-20
The project design is approximately 70% complete. Construction on this project to be completed
in conjunction with the Lomax Sanitary Sewer project.
Second Quarter FY 19-20
No update this quarter.
49
Project PW0012 – Lomax Lift Station Consolidation Design
Account Number: 051/052-7086532Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 15-16$ 195,000$ -$ -
Fiscal Year 16-17 - 8,205 -
Fiscal Year 17-18 500,000 308,971 -
Fiscal Year 18-19 9,500,000 188,265 -
Fiscal Year 19-20 - 145,220 39,691
Total$ 10,195,000$ 650,661$ 39,691 $ 9,504,648
Project Description
This multi-year sanitary sewer project has been approved for funding through the Texas Water
Development Board’s (TWDB) Clean Water State Revolving Fund Program. The project
encompasses planning, design, and construction costs. The project consists of replacement of
over 20,000 feet of gravity sewer and more than 50 manhole. Also planned, is construction of one
regional lift station and 10,000 feet of new sewer force main. This project will eliminate eight (8)
aging stations in the area.
Future Operating Impact: Improvements will be sized for ultimate build-out of the area, reduce
sanitary sewer surcharging in West Lomax. The replacement of aging infrastructure will improve
efficiency and reduce maintenance costs.
First Quarter FY 19-20
During the first quarter FY 2019-20 the Preliminary Engineering Report was completed. The
TWDB has released design funds; design is approximately 50% complete.
Second Quarter FY 19-20
For the second quarter the design was60% completed. Plans and technical specifications are
currently under review.
50
Project PW0015 – Restroom/Pavilion at Five Points
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 400,000$ -$ -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - 23,109 -
Fiscal Year 19-20 350,000 50,036 28,964
Total$ 750,000$ 73,145$ 28,964 $ 647,891
Project Description
This project will include the installation of a covered, open-air outdoor pavilion and a restroom
facility at Five Points Park at the corner of Main Street and Broadway Street in downtown La
Porte. The restroom facility will serve the park during recurring events such as Movie in the Park,
Mardi Gras on Main, Christmas on Main, Summer Party on Main and numerous parade activities
(larger events will supplement the restrooms available with portable units). The pavilion will serve
as an additional outdoor programming. This project is funded by the La Porte Development
Corporation.
Five Points Park space is in need of a covered pavilion with restrooms and storage area. The first
portion of the project was funded in FY 16-17. Project scope has expanded outside of a design-
build platform. Additional funds were budgeted in FY 19-20 to meet construction costs.
Future Operating Impact: Minimal
First Quarter FY 19-20
The preliminary design phase was completed during the first quarter FY 2019-20. The consultant
has initiated final design efforts, with 50% design documents pending.
Second Quarter FY 19-20
The consultant has prepared 90% design and bidding documents. Also, they are preparing 95%
documents to be submitted for permitting.
51
Project PW0016 – Parking Spaces at Pecan Park
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 350,000$ 45,535$ -
Fiscal Year 17-18 - 46,063 -
Fiscal Year 18-19 - 203,599 -
Fiscal Year 19-20 - - 18,252
Total$ 350,000$ 295,197$ 18,252 $ 36,551
Project Description
This project includes the installation of 123 additional parking spaces at Pecan Park. The parking
at this park has consistently been an issue. The proposed spaces will be located as both infill
spaces and in locations that were currently underutilized. This project was funded by the La Porte
Development Corporation.
Future Operating Impact: Minimal.
First Quarter FY 19-20
Project was included in contract for Somerton Project. This portion of work has been completed,
but Somerton scope of work is still under construction.
Second Quarter FY 19-20
This project has been completed.
52
Project PW0017 – Fairmont Parkway Signalization Project
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 1,500,000$ -$ -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
Total$ 1,500,000$ -$ -$ 1,500,000
Project Description
This project includes the City’s share of a joint effort with Harris County to completely re-design
th
and re-configure the traffic signals along Fairmont Parkway. The limits of the project are 7 Street
to the western City limits along Fairmont Parkway. The signals will be replaced, re-programmed,
and some intersections will be re-configured to allow for better traffic flow today and in the future
once Fairmont Parkway is widened. The total project budget if $5.5 million.
Future Operating Impact: None. All signals are owned and operated by Harris County.
First Quarter FY 19-20
At the conclusion of the first quarter FY 19-20 the project was still under construction. However,
substantial completion was projected to be completed by December 31, 2019.
Second Quarter FY 19-20
This project has been completed.
53
Project PW0018 – Drainage Interconnect at Lakes at Fairmont Green
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 250,000$ -$ -
Fiscal Year 17-18 - - -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
Total$ 250,000$ -$ -$ 250,000
Project Description
The drainage infrastructure improvement is necessary to convey storm water runoff from the
currently undeveloped area to the north, to its ultimate outfall location within Taylor Bayou, as
recommended in an earlier citywide Drainage Study. The proposed project area is located in La
Porte, north of Wharton Weems Boulevard, and will allow the conveyance of storm water runoff
to an existing detention facility located within the Lakes at Fairmont Green Subdivision, south of
Wharton Weems Boulevard.
Future Operating Impact: Minimal.
First Quarter FY 19-20
During the first quarter FY 19-20, work is being performed by private developer. The restrictor
has been installed at Taylor Bayou outfall and interconnect is installed beneath Wharton
Weems.
Second Quarter FY 19-20
This project has been completed by the private developer.
54
Project PW0020 – Fencing at Spencer Highway
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 340,200$ -$ -
Fiscal Year 17-18 340,200 40,906 -
Fiscal Year 18-19 - 16,408 -
Fiscal Year 19-20 560,000 - 372,561
Total$ 1,240,400$ 57,314$ 372,561 $ 810,525
Project Description
To provide feasibility, planning, survey and design services for constructing an eight foot precast
concrete fence and sidewalk. The concrete fence will be constructed along the south side of
Spencer Highway from Farrington to Myrtle Creek and along the norths side from Farrington to
Valleybrook. The proposed sidewalk will extend from Farrington to Underwood Road.
Future Operating Impact: Minimal maintenance cost. Meets goals of comprehensive plan.
First Quarter FY 19-20
Trees and vegetation have been cleared from northern ROW/property line. The utility conflicts
with CenterPoint, AT&T, and Comcast have been identified. Currently, staff is coordinating with
utility owners to resolve utility conflicts.
55
Project PW0020 – Fencing at Spencer Highway, continued
Second Quarter FY 19-20
Contractor began construction on west end, where there were minimal utility conflicts.
Approximately 400 feet of fencing has been installed. Contractor continues construction from the
west while utility conflicts are resolved on eastern end of the project.
56
Project PW0023 – Commercial Water Meter Replacement
Account Number: 0037085-533Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 50,000$ 37,694$ -
Fiscal Year 17-18 30,000 6,805 -
Fiscal Year 18-19 15,000 1,569 -
Fiscal Year 19-20 25,000 - -
Total$ 120,000$ 46,068$ -$ 73,932
Project Description
This project funds the replacement of commercial water meters.
Future Operating Impact: Maintains revenue collection.
First Quarter FY 19-20
During the first quarter FY 19-20, staff replaced two (2) commercial meters (a 3” and 4” meter).
Defective meters are being sent in for cleaning, refurbishing and/or repair for future usage.
2nd QuarterFY 19-20
During the 2nd quarter FY 19-20, staff replaced 1 commercial meter. Defective meters are being
sent in for cleaning, refurbishing and/or repair for future usage.
57
th
Project PW0027 – Design for Drainage Improvements (6 Street/N. Madison and
W. Main)
Account Number: 051/0327071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 150,000$ 11,777 $ -
Fiscal Year 17-18 - 25,353 -
Fiscal Year 18-19 250,000 18,000 -
Fiscal Year 19-20 - 43,809 26,721
Total$ 400,000$ 98,939 $ 26,721 $ 274,340
Project Description
Currently, the drainage structures serving this area are approximately 60 years old. This project
will fund a preliminary engineering report for future improvements to enhance drainage.
Future Operating Impact: None.
First Quarter FY 19-20
This past quarter staff reviewed the draft of Preliminary Engineering Report. Staff is expected
return comments to consultant by January 10, 2020.
Second Quarter FY 19-20
During the second quarter, the consultant completed Preliminary Engineer Report. Staff has
requested proposal for design, bidding, and construction phase services.
58
Project PW0028 – Design Somerton Improvements/Construction
Account Number: 003/015/050/051-7071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 150,000$ 78,836$ -
Fiscal Year 17-18 2,200,000 79,741 -
Fiscal Year 18-19 - 762,646 -
Fiscal Year 19-20 - 253,837 79,905
Total$ 2,350,000$ 1,175,060$ 79,905$ 1,095,035
Project Description
This project funds design services for the future replacement of water line and street improvement
on Somerton from Bandridge to Spencer Highway. Staff included the construction budget in the
FY18 CIP. This project funds construction for the replacement of water line and street
improvement on Somerton in Fund 003 (Utility Fund), Fund 015 (General CIP), and Fund 050
(Drainage Improvement).
Future Operating Impact: None.
First Quarter FY 19-20
The project was substantially completed during the first quarter FY 2019-20. However, staff is
awaiting completion of punch-list and close-out documents.
Second Quarter FY 19-20
During the second quarter the punch-list was completed. Still awaiting warranty letter in order to
issue retainage payment.
59
Project PW0029 – Main Street Sidewalk Repairs
Account Number: 0157070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 15,000 $ -$ -
Fiscal Year 18-19 - - 15,000
Fiscal Year 19-20 - - -
Total$ 15,000 $ -$ 15,0000
Project Description
This project will fund small sidewalk repair to level dangerous locations along Main Street. Infill
sidewalks and repair of ADA ramps are also included in this project.
Future Operating Impact: None.
First Quarter FY 19-20
Work orders were issued to contractor during the first quarter FY 19-20 for ADA Ramps and short
section infill. In-house staff are making repairs at areas challenged by tree placement.
Second Quarter FY 19-20
In-house staff are underway working on this project. However, no activity has occurred from the
contractor this quarter.
60
th
Project PW0032 – Construct N. 6/Main to Tyler and Main St Drainage
Account Number: 003/050-7071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 990,000 $ -$ -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 - - -
Total$ 990,000 $ -$ -990,000
Project Description
Currently, the drainage structures serving this area are approximately 60 years old. This project
will fund construction of drainage improvements, in these two areas. The construction budget is
$990,000 with supplemental funding in Fund 050 (950,000).
Future Operating Impact: Minimal.
First Quarter FY 19-20
Staff reviewed the draft of Preliminary Engineering Report during the first quarter FY 19-20. Staff
expects comments to be returned to consultant by January 10, 2020.
Second Quarter FY 19-20
Consultant completed Preliminary Engineer Report. Staff has requested proposal for design,
bidding, and construction phase services.
61
Project PW0033 – Hillridge Pump Station Construction Phase 1
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 535,000 $ -$ -
Fiscal Year 18-19 700,460 7,875 -
Fiscal Year 19-20 - 3,944 1,087,953
Total$ 1,235,460$ 11,819$ 1,087,953 135,688
Project Description
The first portion of this project was funded in FY 17-18 for the construction of a new pump station
on the existing site. The Hillridge Pump Station is over 50 years old and in need to repair.
Future Operating Impact: None.
First Quarter FY 19-20
During the first quarter FY 19-20 the project was awarded to W. W. Payton Company. The “Notice
to Proceed” was issued November 11, 2019. The major equipment has been ordered and no site
work has begun at this time. Existing facility to remain in service until new facility is constructed.
Second Quarter FY 19-20
Multiple submittals are being received on this project. Long lead-time materials and equipment
have been ordered. Staff anticipates construction activities to begin in third quarter.
62
Project PW0034 – Aerial Crossings
Account Number: 0037071-532Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 25,000 $ 10,916$ -
Fiscal Year 18-19 140,000 2,000 -
Fiscal Year 19-20 50,000 - -
Total$ 215,000 $ 12,916$ -202,084
Project Description
This will be the second year of a multi-year project will address maintenance of exposed water
and wastewater pipes that cross drainage channels. Both in-house and contract forces to be
utilized. The main focus will be replacement of an aging waterline crossing over Little Cedar Bayou
th
at S. 8 Street.
Future Operating Impact: None.
First Quarter FY 19-20
No progress this quarter. However, the painting and recoating portion of the projects will
commence in warmer weather.
Second Quarter FY 19-20
th
No progress on the replacement of an aging waterline crossing over Little Cedar Bayou at S. 8
Street this quarter. Currently awaiting consultant’s proposal to design. The painting and
recoating portion of other projects will commence in the third quarter.
63
Project PW0041 – Public Works Facility Assessment
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 65,000$ 24,435$ -
Fiscal Year 19-20 75,000 19,054 5,896
Total$ 140,000$ 43,489$ 5,896 $ 90,615
Project Description
In FY 18-19 City Council asked that staff begin a needs assessment of the current Public Works
Service Center. The current facility is 37 years old and does not meet wind-loading requirements.
The assessment will provide direction for future design and improvements to the service center.
Future Operating Impact: None
First Quarter FY 19-20
The existing building assessment has been completed. Additionally, the current and future space
program has been completed to. However, the parking and equipment storage area needs to be
analyzed. The first rough draft of floor plan is provided below. Input and comments from each
division manager has been provided to the consultant.
64
Project PW0041 – Public Works Facility Assessment, continued
Second Quarter FY 19-20
For second quarter, the consultant has prepared a draft layout utilizing comments from all
departments. However, this deliverable is under staff review.
65
Project PW0043 – East Main Street Sidewalk
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 430,000$ 29,839$ -
Fiscal Year 19-20 - 8,168 278,120
Total$ 430,000$ 38,007$ 278,120$ 113,873
Project Description
This project will fund design and construction of sidewalk on the south side of East Main from S.
Broadway to S. Blackwell Street.
First Quarter FY 19-20
During the first quarter FY 19-20 the project has been bid and scheduled to be awarded on
January 13, 2020.
Second Quarter FY 19-20
Approximately 800 feet of sidewalk was poured in the second quarter. Construction still is
underway.
66
Project PW0044 – Replace Ground Tank – Collegeview Water Plant
Account Number: 0037085-533Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 350,000$ 20,000$ -
Fiscal Year 19-20 - 297,250 35,550
Total$ 350,000$ 317,250$ 35,550$ (2,800)
Project Description
This project will fund design and replacement of a 50 year old water storage tank at the Bandridge
Water Plant. The opportunity exists to increase the height to standard 24 foot.
First Quarter FY 19-20
During the first quarter FY 2019-20 the project was awarded to Schier Construction Company.
The demolition and replacement to take place during January 2020. TCEQ acknowledged
planned increase in storage capacity.
Second Quarter FY 19-20
Construction was 90% completed in the second quarter. Staff anticipate final completion within
30 days after end of second quarter, pending weather.
67
Project PW0044 – Replace Ground Tank – Collegeview Water Plant, continued
68
Project PW0046 – Pumps & Equipment Replacement
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 50,000$ 9,500$ -
Fiscal Year 19-20 50,000 - -
Total$ 100,000$ 9,500$ -$ 90,500
Project Description
This project replaces aging pumps and motors within the Wastewater Treatment Plant and Water
Production facilities.
First Quarter FY 19-20
During the first quarter FY 19-20, staff replaced the booster pump #2 at plant #7 as well as
purchased two (2) SCBA Airpaks with accessories. However, there was no activity at the
treatment plant due to priority of items still being defined.
69
Project PW0046 – Pumps & Equipment Replacement, continued
Second Quarter FY 19-20
Treatment plant RAS & WAS totalizer meters have been ordered and received.
Installation anticipated in Third quarter.
70
th
Project PW0047 – 25Street Water Plant Generator (HMGP)
Account Number: 015/0327070-530Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 425,000$ -$ -
Total$ 425,000$ -$ -$ 425,000
Project Description
This project will design and construct a natural-gas powered standby generator with automatic
transfer switch for this water facility. Currently the facility has a manual switch for a portable
generator. Total project cost is estimated at $425,000.
Future Operating Impact: None
First Quarter FY 19-20
At the end of the first quarter of FY 19-20 the Texas Division of Emergency Management (TDEM)
had not awarded this grant; therefore, project is pending re-distribution of available funds.
(December 2019)
Second Quarter FY 19-20
Grant notification pending. No activity this quarter.
71
Project PW0048 – Lift Station 40 Generator (HMGP)
Account Number: 015/0327086-532Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 235,000$ -$ -
Total$ 235,000$ -$ -$ 235,000
Project Description
This project will design and construct a natural-gas powered standby generator with automatic
transfer switch for this wastewater conveyance facility. Currently the facility has a manual switch
for a portable generator. Total project cost is estimated at $235,000.
Future Operating Impact: None
First Quarter FY 19-20
At the end of the first quarter of FY 19-20 the Texas Division of Emergency Management (TDEM)
had not awarded this grant; therefore, project is pending re-distribution of available funds.
(December 2019)
Second Quarter FY 19-20
Grant notification pending. No activity this quarter.
72
Project PW0049 – Replace Ground Tank – Hillridge Water Plant
Account Number: 0037085-533Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 300,000$ 20,000$ 10,000
Total$ 300,000$ 20,000$ 10,000$ 270,000
Project Description
This project funds design and replacement of a 45 year old water storage tank at the Hillridge
Water Plant.
Future Operating Impact: Decreased maintenance costs.
First Quarter FY 19-20
The specifications and bid documents were being prepared at the conclusion of the first quarter
FY 19-20.
Second Quarter FY 19-20
This project has been awarded to WW Payton Corporation. Submittals have been submitted to
Dunham Engineering for review.
73
Project PW0050 – Coating Lomax Water Tower
Account Number: 0037085-533Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 600,000$ 50,000$ 25,000
Total$ 600,000$ 50,000$ 25,000$ 525,000
Project Description
This project funds the replacement of interior coating, repair work and over-coating the exterior
for the 750,000 gallon elevated water tank.
Future Operating Impact: Routing maintenance will extend the life of the structure.
First Quarter FY 19-20
The specifications and bid documents were being prepared at the conclusion of the first quarter
FY 19-20.
Second Quarter FY 19-20
During the second quarter the project was awarded to Maguire Iron. Anticipate construction
activities to begin by the end of April 2020.
74
Project PW0051 – Replace Heaters in Dewatering Building - WWTP
Account Number: 0037087-532Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 15,000 $ 14,825$ -
Total$ 15,000 $ 14,825$ -$ 175
Project Description
Currently, heaters are 20 years old and in need of replacement.
Future Operating Impact: Reduces maintenance on aging building heater.
First Quarter FY 19-20
During the first quarter FY 2019-20 at the Treatment Plant, staff replaced heaters in dewatering
building. This project has been completed.
75
Project 669 – Sanitary Sewer Rehabilitation
Account Number: 0189881-669Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 300,000$ 29,948$ 148,784
Total$ 300,000$ 29,948$ 148,784 $ 121,268
Project Description
Public Works Department will perform in-house rehabilitation of sewers by slip line, point repairs,
manhole sealing, smoke testing, and TV inspection. This program is mandated by the Texas
Commission on Environmental Quality (TCEQ). Note: This project does not roll forward each
year. A new amount is budgeted each year.
Future Operating Impact: None
First Quarter FY 19-20
Numerous portions of this project were completed in first quarter FY19-20: 14 lift stations were
cleaned by in-house staff; 40 point repairs were completed by in-house staff; 118 vertical feet of
manhole repairs were completed by in-house staff; 17,397 feet of sanitary sewer main was smoke
tested by in-house staff; 96 manholes were inspected by in-house staff; 3 cleanouts and/or
cleanout shoes were installed by in-house staff; one dye flood test was performed by in-house
staff; and 19 feet of sanitary sewer main was removed and replaced by in-house staff; 2 manholes
and a cleanout were located by in-house staff. In addition, 7550 feet of sanitary sewer main was
cleaned by in-house staff, in regards to trouble spot areas. Additionally, 14,448 feet of sanitary
sewer main was cleaned by in-house staff. Contractors cleaned and televised 1159 feet of
sanitary sewer main.
76
Project 669 – Sanitary Sewer Rehabilitation, continued
77
Project 669 – Sanitary Sewer Rehabilitation, Cont’d
2nd Quarter FY 19-20
Public Works completed numerous portions of this project by in-house staff during the second
quarter: 17 lift station wet wells were cleaned; 24 point repairs, 36 vertical feet of manhole repairs
and 24,467 feet of sanitary sewer main was smoke tested; 145 sanitary manholes were inspected
and four cleanouts were installed; and 8 sanitary manholes were located and 7 sanitary manholes
were cleaned. Also, our staff installed a new sanitary manhole and 305 feet of sanitary sewer. In
addition, 17,093 feet of sanitary sewer main was cleaned by staff, in regards to trouble spot areas.
Contracted vendors cleaned and televised 15,883 feet of sanitary sewer main and sealed 68.6
vertical feet of sanitary manholes.
78
Project 669 – Sanitary Sewer Rehabilitation, Cont’d
79
Project 669 – Sanitary Sewer Rehabilitation, Cont’d
80
Project SM0002 – Asphalt Street Surfacing
Account Number: 0337071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20 630,000 318,005 -
Total$ 630,000 $ 318,005$ -$ 311,995
Project Description
This project funds the annual program to resurface streets throughout the City with asphalt. Note:
This project does not roll forward each year. A new amount is budgeted each year.
Future Operating Impact: Minimal.
First Quarter FY 19-20
No update this quarter. This project will typically bid second quarter to allow construction during
late spring/summer months.
Second Quarter FY 19-20
Currently, this project was out for bid at the end of the second quarter.
81
Project SM0003 – Street Repair Material (in-house)
Account Number: 0337071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 50,000$ 50,205$ -
Fiscal Year 17-18 50,000 38,992 -
Fiscal Year 18-19 50,000 34,866 -
Fiscal Year 19-20 50,000 3,097 5,903
Total$ 200,000$ 127,160$ 5,90366,937
Project Description
This project funds the purchase of materials for repairs that are completed by in-house street
crews.
Future Operating Impact: None.
First Quarter FY 19-20
Some materials purchased for concrete truck during the first quarter FY 19-20; however, more will
nd
be purchased during the 2 quarter.
First Quarter FY 19-20
No activity this quarter.
82
Project SM0004 – Pinebluff Subdivision Construction (Angel Brothers)
Account Number: 033/051-7071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 16-17$ 2,000,000$ -$ -
Fiscal Year 17-18 - 1,125,294 -
Fiscal Year 18-19 - 825,250 -
Fiscal Year 19-20 - 6,304 22,705
Total$ 2,000,000$ 1,956,848$ 22,705 $ 20,447
Project Description
This project includes pavement replacement and drainage improvements for the subdivision. The
total project budget is $2,000,000 with supplemental funding in Fund 050 (Drainage Fund) in the
amount of $1,792,687.
Future Operating Impact: None.
First Quarter FY 19-20
This project was completed during the first quarter FY 2019-20. Staff is awaiting final invoice for
retainage.
Second Quarter FY 19-20
Project has been completed and retainage paid during the second quarter.
83
Project SM0007 – Construct Sylvan and Jefferson
Account Number: 015/003/0337071-531Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 17-18$ 560,000$ 3,662$ -
Fiscal Year 18-19 - - -
Fiscal Year 19-20 380,000 4,184 896,676
Total$ 940,000$ 7,846$ 896,676 $ 35,478
Project Description
This is a previous-year CIP project with scope that has expanded during design. Revised scope
will include intersection alignment and concrete pavement on Jefferson, east of Bayshore Drive.
Additional construction costs are estimated at 330,000. Additional funds to be provided by Fund
003 and 033.
Future Operating Impact: Improved street surface and improved area drainage.
First Quarter FY 19-20
In the first quarter FY 2019-20 the project was awarded to Tandem Services, LLC. Currently, the
construction contract is being executed.
Second Quarter FY 19-20
Approximately 30% of the construction has been completed during the second quarter. Project
still underway.
84
th
Project STR7TH – South 7 Street Paving and Drainage
Account Number: 003/0337071-531Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 18-19$ 139,340$ 139,340$ -
Fiscal Year 19-20 2,435,000 173,557 192,466
Total$ 2,574,340$ 312,897$ 192,466 $ 2,068,977
Project Description
(003) Utility Fund – This project will fund water main adjustments needed for drainage system on
th
South 7
Street from Main Street to Fairmont Parkway. Total costs for Design and Construction
is estimated at $5,300,000.
(033) Drainage Fund – This project will fund design and construction of improved drainage with
th
concrete curt and gutter with sidewalks on South 7 Street from Main Street to Fairmont Parkway.
Total costs for Design and Construction is estimated at $5,300,000
Future Operating Impact: Improved street surface and improved area drainage.
First Quarter FY 19-20
During the first quarter FY 2019-20 the Preliminary Engineering report and surveying were
completed. Additionally, the design is at 30% completion.
Second Quarter FY 19-20
Approximately 60% of the design was completed in the second quarter.
85
Project STRLCB – Little Cedar Bayou Drive Concrete Paving
Account Number: 0337071-531Budget
BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 110,000$ -$ -
Total$ 110,000$ -$ -$ 110,000
Project Description
This project included funding for replacement of park entrance road with concrete paving from
th
South 8 Street to the park entrance.
Future Operating Impact: None
First Quarter FY 19-20
Staff began preparing specifications and bid documents during the first quarter FY 19-20.
Second Quarter FY 19-20
No update this quarter.
86
Project 655 – Meter Replacement Program
Account Num 0039890-655Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 12-13$ 80,000$ 79,141$ -
Fiscal Year 13-14 90,000 85,102 -
Fiscal Year 14-15 290,000 110,163 -
Fiscal Year 15-16 180,000 285,591 -
Fiscal Year 16-17 250,000 317,186 -
Fiscal Year 17-18 299,046 275,671 -
Fiscal Year 18-19 300,000 299,682 -
Fiscal Year 19-20 350,000 40,952 309,048
Total$ 1,839,046$ 1,493,487$ 309,048 $ 36,511
P ROJECT D ESCRIPTION
This funds the annual program to continue replacing water meters, which includes the purchasing of
electronic components, meters and meter boxes.
Future Operating Impact: Reduced maintenance on old, broken water meters.
F IRST Q UARTER FY19-20
During the first quarter, 200 residential meters were ordered.
S ECOND Q UARTER FY19-20
A total of 122 meters were installed during the second quarter.
87
Project 697 – Valve Replacement Program (in-house)
Account Number: 0039890-697Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 14-15$ 40,000 $ 24,479$ -
Fiscal Year 15-16 25,000 6,273 -
Fiscal Year 16-17 25,000 8,034 -
Fiscal Year 17-18 25,000 24,847 -
Fiscal Year 18-19 25,000 15,421 -
Fiscal Year 19-20 25,000 11,377 -
Total$ 165,000 $ 90,431$ -$ 74,569
Project Description
This project is for material cost for City crews to replace non-functioning water main valves.
Future Operating Impact: Improved efficiency
First Quarter FY 19-20
During the first quarter FY 19-20, staff replaced four (4) gate valves.
2nd Quarter FY 19-20
No activity this quarter.
88
Project 760 – Lift Station Improvements
Account Number: 0039892-760Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 35,000 $ -$ 15,524
Total$ 35,000 $ -$ 15,524$ 19,476
Note: This project does not roll forward each year. A new amount is budgeted each year.
Project Description
This project will fund general repairs to the City’s various lift stations. Improvements may include
replacing and repairing pumps, piping, and control panels.
Future Operating Impact: Improvements will lessen future maintenance and operating costs.
First Quarter FY 19-20
During the first quarter FY 2019-20, staff replaced suction line on pump at lift station #32.
Second Quarter FY 19-20
During second quarter, staff ordered submersible pumps for lift stations #37 and #10 (1 each)and
purchase orders have been issued.
89
Project 898- In-house Waterline Replacement
Account Number: 0039890-898Budget
Funding:BudgetExpendituresEncumbrancesRemaining
Fiscal Year 19-20$ 45,000$ 4,638$ -
Total$ 45,000$ 4,638$ -$ 40,362
Project Description
This project funds the replacement of small steel lines in the alleys of La Porte where numerous
leaks and failures continue to occur. Note: This project does not roll forward each year. A
new amount is budgeted each year.
Future Operating Impact: Reduction is leak repairs.
First Quarter FY 19-20
thth
During the first quarter FY 19-20, staff replaced 190 feet of waterline between N. 4/5Streets.
2nd Quarter FY 19-20
th
During the 2nd quarter FY 19-20, staff replaced 472 feet of waterline on S. 5 St. & Lobit St.
90