HomeMy WebLinkAbout09-04-2002 Board Meeting
LA PORTE DEVELOPMENT CORPORATION BOARD
COMMITTEE MEETING AGENDA
LA PORTE DEVELOPMENT CORPORATION BOARD MEETING OF CITY OF LA PORTE
TO BE HELD, SEPTEMBER 4, 2002 IN THE COUNCIL CHAMBERS OF CITY HALL,
604 WEST FAIRMONT PARKWAY, LA PORTE, TEXAS BEGINNING AT 5:30 P.M.
CALL TO ORDER
2. CONSIDER APPROVAL OF MINUTES OF MEETING OF OCTOBER 24, 2001
ADMINISTER OATH OF OFFICES
4. RECEIVE FINANCIAL REPORT
a. STATEMENT OF EXPENDITURES COMMUNITY LIBRARY
b. AUGUST 31, 2002 (UNAUDITED)
FUTURE PROJECTS
A. FUND SUMMARY (FY 2002 BUDGET)
B. PROJECT REPORTS
a. BAY AREA BOULEVARD
b. CANADA ROAD
c. SENS ROAD
PROPOSED DEBT ISSUANCE
PRESENTATION OF PROPOSED BUDGET
a. FUND SUMMARY
b. STATEMENT OF REVENUE
c. LONG RANGE DEBT SERVICE PLAN
BOARD ACTION
9. ADJOURNMENT
THIS FACILITY HAS DISABILITY ACCOMMODATIONS AVAILABLE. REQUESTS FOR
ACCOMMODATIONS OR INTERPRETIVE SERVICES AT MEETINGS SHOULD BE MADE
48 HOURS PRIOR TO THIS MEETING. PLEASE CONTACT CITY SECRETARY'S OFFICE
AT 281-471-5020 OR TDD LINE 281-471-5030 FOR FURTHER INFORMATION.
A possible quorum of city council members may be present at this meeting and participate in discussions
but will not take any action.
CITY OF LA PORTE DEVELOPMENT CORPORATION
604 W. FAIRMONT PKWY, LA PORTS, TEXAS 77571
To: President and Board Members
Robert T. Herrera, City Manager
John Joerns, Acting City Manager
Michael Dolby, Assistant Finance Director
Martha Gillett, City Secretary y
From: Cynthia Alexander, Director of Finance
Date: August 30, 2002
Subject: Board Meeting
The next meeting of the La Porte Development Corporation is scheduled for Wednesday,
September 04, 2002 at 5:30 p.m. The meeting will be held in the Council Chambers at La Porte
City Hall. Attached is the agenda for the meeting.
Snacks will be provided in the Council Chambers.
i
LA FORTE DEVELOPMENT CORPORATION
SEPTEMBER 4, 2002
5:30 PM
LA FORTE CITY HALL
•
A Meeting of the La Porte Development Corporation
To be held Wednesday, September 4, 2002 at 5:30 pm
La Porte City Hall
604 W. Fairmont Pkwy, La Porte, Texas 77571
1. Call to Order
2. Consider approval of minutes of meeting of October 24, 2001
3. Administer Oath of Offices
4. Receive Financial Report
a. Statement of Expenditures Community Library
b. August 31, 2002 (unaudited)
Future Projects
A. Fund Summary (FY 2002 budget)
B. Project Reports
a. Bay Area Boulevard
b. Canada Road
c. Sens Road
6. Proposed Debt Issuance
7. Presentation of Proposed Budget
a. Fund Summary
b. Statement of Revenue
c. Long Range Debt Service Plan
8. Board Action
9. Adjournment
•
MINUTES OF THE LA PORTE DEVELOPMENT CORPORATION
OCTO$ER 24, 2001
1. Call to Order/Introductions
Pat Muston called the meeting to order at 6:40 p.m.
Present: Ed Matuszak, Deborah Johnson, Chuck Engelken, Bill Love, Pat Muston, City
Secretary Martha Gillett, Finance Director Cynthia Alexander, City Manager Robert T.
Herrera, Jerry Clarke and Assistant Finance Director Mike Dolby.
Members Absent: Peter Griffiths.
Others Present: None.
2. Consider approval of minutes of meeting of March 22, 2000.
Motion was made by Chuck Engelken to approve the minutes as presented. Seconded by
Jerry Clarke. The motion carried
Ayes: Pat Muston, Ed Matuszak, Chuck Engelken, Deborah Johnson, Bill Love, and
Jerry Clarke.
Nays: None
Abstain: None
3. Administer Oaths of Office
City Secretary Martha Gillett Administered the Oaths of Office to Pat Muston, Ed
Matuszak, Chuck Engelken, Deborah Johnson, Bill Love and Jerry Clarke.
4. Election Of Officers
Motion was made by Chuck Engelken to reappoint Pat Muston as President and Ed
Matuszak as Vice President. Seconded by Bill Love. The motion carried unanimously.
Ayes: Pat Muston, Ed Matuszak, Chuck Engelken, Deborah Johnson, Bill Love, and
Jerry Clarke.
Nays: None
Abstain: None
5. Receive Report on Financial Matters
Finance Director Cynthia Alexander presented and discussed the unaudited balance sheet
through September 30, 2001. Fund balance is $1,458,268. In addition reviewed
revenues, expenditures and changes in fund balance. Library expenses were reviewed
and it was reported the Library project is significantly completed.
6. Future projects were discussed.
Finance Director Cynthia Alexander reported future projects would include Bay Area
Boulevard and extension of Canada Road from Spencer to Fairmont Parkway.
Page 2
C~
7. Board Action - It was agreed upon there would be three meetings in 2002.
8. Adjournment
There being no further business to come before the Development Corporation, the
meeting was duly adjourned at 7:22 p.m.
Respectfully submitted,
art a A. Gillett
City Secretary/La Porte Development
~j' Corporation Secretary
Passed and approved on this ,~ 61 day of '- ' '~1 %,%L002.
1 1
~ ~ ~~~~
Pat Muston, resident
•
•
OATH OF OFFICE
I, ~~-~: ~ ~ ~ • ~~ (I t~r~f~is , do solemnly swear (or affum), that
I will faithfully execute the duties of the office of Gc oa~-~ ~
Jc~l nnrn~r~~ C t r7o(~ra , of the City of La Porte,
State of exas, and will to the best of my ability preserve, protect
and defend the constitution and laws of the United States and of this
State and the Charter and ordinances of this City; and I furthermore
solemnly swear (or affirm) that I have not directly or indirectly paid,
offered, or promised to contnbute any money, or valuable thing, or
promised any public office or employment, as a reward to secure my
appointment or the confirmation thereof. So help me God.
i
~---~
Sworn to and subscribed before me this the ~~`~" day of
~L~P~mh~~ ,~~v~
Notary Public in and for the
State of Texas
~nnn{ununnnnnnnnnnnnnnnnunnll
2os""Y °°B<~ MARTHA GILLETTE
i ~ ,, NOTARY PUBLIC
STATE OF TEXAS
- ~~'>E o~ ~E+~y Comm. Exp. OS-22-2005
ijtI11N{11111111-1111i1~~tllllllllillllllllllllllllii
~GC~~ ~f~te of ~e~cac.~
~~;a~e~n.en~ of Appa~a.~ad C.~f~icer
I, ~~~'-{ `~" t' ~ = ~~ { ~ ~~ ~~"~5 , do soternnly ewesl~r for ettlrm). tl-a1 i tYwe not directly
or Indlredly geld, offered, arotnlsed fo Pay, cantrltwfed. ar Promised to contribute any money or Ihing of valise, or
Prestnlsed any Public o~flCe Or BnIDIOS~tgP-Jlt. 89 6 rCWei~d 10 BecUrC tAY 8ap01nlment Or canflrrnatloh lbereot, so help tyre Gott.
f~
Aftiant's 5lanature
La Porte Development Corporation
Otfiae to Wh(ch fl~olnted
La Porte / Harris
Clt~ enQ/or CAUnty ~
,/
an on s `~ ~ ~ da of ,~-~ ' _ ; .2 -t` r/ ~~~~ ~ ir,.
SWORN TO and subscribed befiore me by af'fl t 1hl y
IIItI111111111111111111111111111111I111111111111111111
~ 201 nRY `°B<~ MARTHA GILLETTE
NOTARY PUBLIC
-_ STATE OF TEXAS -_
- ~~TE Of ZE+'y Comma Exp. OS-22-2005 =
liunlllntlnllllnlninlnlnlnlnlnlnllulull
rt
r'`
two ~f Persoa~ Adminircerhta Oath
k1~c~ r~1f~ c~.~~ ~ I~ ~- i
Primed tiamc f
1
C... ~ ~ y 5~-~ ~'~~'`fu r-~
gab I'
.~___..__..___ww__-~~_~_ ___-----_~_.., _.~~_~J
•
•
Financial Report
• •
City of La Porte, Texas
Statement of Expenditures -Community Library
August 30, 2002
Expenditures:
Legal/Advertising
Architects
Audiovisual/Other Equipment
Construction
$ 1,122.25
247,610.74
120,573.61
2,639,643.44
Total Expenditures $ 3,008,950.04
•
•
La Porte Development Corporation
Fund (038)
Future Projects
•
Section 4B Sales Tax
At this time, the City can issue up to $10 million from this revenue source. A bond
election is not needed for this project if approved by Council, and bonds could be issued
in FY 2003 and 2004.
At this time, we are recommending the following projects for your consideration:
Bay Area Boulevard
Tentative
Date Project Amount
Mar-Jun 2003 Roadway (50% Participation) $4,400,000
Canada Road
Tentative
Date Project Amount
March 2003 Install Utilities $ 700,000
June 2003 Roadway (50% Participation) $1,900,000
Sens Road
Tentative
Date Project Amount
January 2004 Improvements plus Utilities $2,200,000
Both the Bay Area Boulevard and Canada Road Projects are based on anticipated
participation by Harris County. Additionally, we are proposing to complete the
Installation of the Bay Area Blvd Sanitary Sewer trunk in January -March of 2003 at a
proposed cost of $1,515,000. This portion of the Bay Area Boulevard Project will be
funded directly by the La Porte Development Corporation (Section 4B Sales Tax) Fund
and is included in this year's Proposed Budget.
The total amount of the potential debt issues is $9,200,000. The Debt will be issued in
two separate increments/packages of $7,000,000 and $2,200,000; which will include an
adequate amount for contingency for the proposed projects.
FY 2002-2003 Proposed Budget
Lai Ls~ Loe _ ~e~ ~~
BAY AREA BOULEVARD -TRUNK SEtiVER
These funds will be utilized to design and construct a trunk
sewer main from Fairmont Parkway, through Spencer
Highway, to North "D" Street. This project is intended to
provide sewer service to unnerved areas along the Bay Area
Boulevard extension and eventually provide relief to the
sewer systems in the Lomax area. Upon completion of this
project, an existing lift station at the corner of Sens Road
and North ``D" Street can be eliminated. In addition, this
trunk sever main will be deep enough to be extended, in the
future, all the way to North "L" Street.
Proposed Budget $1,515,000
Proposed Debt Issuance
Series 2003
Certificates Of Obligation
$7,000,000
_ .......- --.-_w
Series 203 Certificates of ~bliga~ion
BAY AREA BOULEVARD
These funds `~~ill be utilized for the City's share of this major
road~`~ay extension from Fairmont Parkway to Spencer
High`~~ay. An agreement with Harris County stipulates a
50150 sharing of the costs associated with this project.
Design of this project has been completed by Harris County.
Right-of ~~•ay acquisition is a component the City has agreed
to undertake.
Proposed Budget $4,400,000
eANADA ROAD
PAVING AND DRAINAGE
These fiords will be utilized t® design and construct Canada
Road from Fairmont Park`vay to Spencer Highway. The
roadway will be four-lane concrete with curb and gutter and
underground storm sewer. Major components of this
project, other than the road itself, include right-of way
acquisition, pipeline adjustments, and power line
adjustments. The proposed budget is based on 50% funding
from Harris County `which the City is currently pursuing.
Proposed Budget X1,900,000
_..~.:' ...:~3 .._~ a ~ ': _._._.~s
°-:~"~ ~
CAN~D~ ROAD -UTILITIES
Water and sewer service does not exist to areas beriveen
Fairmont Parkway and the Pecan Plantation Mobile Home
Park, including the City's 33-acre park site. This project
includes the design and installation of water and sewer lines
that `will provide service to the Canada Road area.
Proposed Budget $700,000
~. ,. ~ :.::~ .... _ ,. u.
r..~ ~._~.:~ ~.. _ .
i •
Proposed Debt Issuance
Series 2004
Certificates Of Obligation
$2,200,000
Series 2004 Certificates of Obligation
SENS ROAD IMPROVEMENTS
(PROPOSED)
Although no commitments have been made, the City and
Harris County have been in discussion regarding the
reconstruction of Sens Road from West Main (Spencer
Highway) to State Highway 225. The project is currently
estimated at 12 million dollars and we hope that Harris
County will sponsor and complete this project with a
contribution of 2 million dollars from La Porte.
Estimated Commitment from La Porte $2,200,000
La Porte Development Corporation
Fund (038)
Proposed Budget
October 1, 2002 -September 30, 2003
As presented to City Council
During
Budget Workshops
August 19 - 20, 2002
City of La Porte
La Porte Development Corporation (038) Fund Summary
(Section 4B Sales Tax)
Working Capital 9/30/01
Plus Estimated 01-02 Revenues
Less 01-02 Expenditures and Commitments
Equals Estimated Working Capital 9/30/02
Plus 02-03 Revenues:
1/2 Cent Sales Tax
Administrative Transfer from 2000 Certificates of Obligation Fund*
Interest Income
Total Revenues
1,656,913
1,025,959
311,050
2,371,822
900,000
295,650
49,810
1,245,460
Equals Total Resources 3,617,282
Less 02-03 Expenditures:
Operations 5,000
Debt Service Transfer 301,050
Debt Service Transfer for Potential Bond Issue 145,833
Transfer to General CIP Fund (Canada Road) 193,000
Transfer to Utility CIP Fund (Bay Area/Canada Road) 249,450
Bay Area Boulevard 1,515,000
Contingency 200,000
Total Expenditures 2,609,333
Equals Estimated Working Capital 9/30/03 1,007,949
*Pending Board Approval
City of La Porte
La Porte Development Corporation Fund (038)
Statement of Revenues
Object Description
Charges for Services:
403.02-00 1/2 Cent Sales Tax
Charges for Services Subtotal
Administrative Transfers:
480.01-42 Transfer from 2000 C of O Fund
Administrative Transfers Subtotal
Interest:
483.01-00 Interest Income
Interest Subtotal
Total La Porte Development Corp Fund Revenues
Actual Budget Revised Projected
2000-01 2001-02 2001-02 2002-03
955,499 900,000 978,088 900,000
955,499 900,000 978,088 900,000
- - - 295,650
- - - 295,650
62,428 50,000 47,871 49,810
62,428 50,000 47,871 49,810
1,017,927 950,000 1,025,959 1,245,460
Beg Working Capital Balance
Plus Revenues:
Transfer from Fund 41
Sales Tax
Interest
Total Revenue
Less Expenses:
Operations
$3Million Cos
Transfer to General CIP Fund
Transfer to Utility CIP Fund
Potential 7.0 Issue 2003
Potential 2.2 Issue 2004
Contingency
Bay Area Trunk Sewer
Total Expenses
Ending Balance
Days of Working Capital
City of La Porte, Texas
Long Range Projection for the La Porte Development Corporation
Section 4B 1/2 Cent Sales Tax
Estimated Projected Projected Projected Projected Projected Projected Projected Projected
2001-02 2002-03 2003-04 2004-OS 2005-06 2006-07 2007-08 2008-09 2009-]0
],656,913 2,371,822 1,007,949 930,537 752,381 632,673 572,035 571,108 630,547
295,650
978,088 900,000 922,500 945,563 969,202 993,432 1,018,267 1,043,724 1,069,817
47,871 49,810 51,055 52,332 53,640 54,981 56,355 57,764 59,208
1,025,959 1,245,460 973,555 997,894 1,022,841 1,048,413 1,074,623 1,101,488 1,129,026
5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000
311,050 301,050 290,550 280,050 269,550 259,050 248,550 238,050 228,900
193,000
249,450
145,833 691,250 673,750 656,250 638,750 621,250 603,750 586,250
64,167 217,250 211,750 206,250 200,750 195,250 189,750
200,000
1,515,000
311,050 2,609,333 1,050,967 1,176,050 1,142,550 1,109,050 1,075,550 1,042,050 1,009,900
2,371,822 1,007,949 930,537 752,381 632,673 572,035 571,108 630,547 749,672
2,783 141 323 234 202 188 194 221 271
,~
Assumptions:
Annual growth of the 1 /2 cent Sales Tax will be at 2.5% per year.
Interest will be earned at 2.5% on average balance