HomeMy WebLinkAboutF101 INTERLOCAL AGREEMENTCITY OF LA PORTE
Interoffice Memorandum
ORIGINAL
TO
FROM
Mayor and City Council
Robert T Herrera City Mana
John Joems Assistant City
SUBJECT F101 Interlocal Agreement with s County Flood Control District
DATE September 1 1998
On July 14 1998 City Council approved an Ordinance authorizing an Interlocal
Agreement between the City of La Porte and Harris County Flood Control District for
drainage improvements to the F101 Watershed in the Lomax area
We have received from HCFCD a fully executed copy of the Agreement signed by
Commissioners Court on August 12 1998 The original will go to the vault as a
permanent record
C Martha Gillett City Secretary original
Doug Kneupper Director of Planning copy
Knox Askins City Attorney
JJ dly
e n 1i Wli
1ll1 11998
CERTIFIED MAIL 9113892
RETURN RECEIPT REQUESTED 9900 Northwest Freeway
Houston Texas 77092
713 684 4000
ASST CITY MANAGER
OFFICE Harris County
flood Control District
August 31 1998
City of La Porte
P O Box 1115
La Porte Texas 77572 1115
Attention Assistant City Manager
Reference Interlocal Agreement for drainage improvements for the
Harris County Flood Control Unit F1 01 00 00 watershed
HCFCD Project ID F101 00 00 E004
Gentlemen
Please find enclosed one 1 fully executed original of the above referenced agreement between
the City of La Porte and Harris County Flood Control District This agreement is being transmitted
for your use and files
Should you require any additional information please contact me or Ms Brenda Trevino
Sincerely
eOJw i
Carolyn Rausin
Engineering Contracts
cr
Enclosure Agreement
cc Contract File
Brenda Trevino
98EC004 WPD
e
INTERLOCAL AGREEMENT
THE STATE OF TEXAS i
i
COUNTY OF HARRIS i
THIS AGREEMENT is made and entered into pursuant to the Interlocal Cooperation Act TEX
GOVT CODE ANN Chapter 791 by and between the CITY OF LA PORTE TEXAS a municipal
corporation under the laws of the State of Texas hereinafter designated City and the HARRIS
COUNTY FLOOD CONTROL DISTRICT a body corporate and politic under the laws of the State
of Texas hereinafter designated Districf or HCFCD
WIT N E SSE T H
WHEREAS on August 2 1988 the District and the City entered into an Interlocal Agreement to
provide drainage improvements for the HCFCD Unit F1 01 00 00 watershed and
WHEREAS the District and the City acknowledge that improvements to the portion of the
F1 01 00 00 watershed upstream of Union Pacific Railroad s Strang Yard are part of a long range
plan to be implemented in phases and the portion of the F101 00 00 watershed upstream from
Sens Road to P Street continues to experience flooding and drainage problems and
WHEREAS the District and the City now desire to proceed with Phase II of improvements to Unit
F1 01 00 00 and
WHEREAS the District and the City desire to cooperate by providing channel enlargements
pipeline relocations and other improvements to Unit F1 01 00 00 from Union Pacific Railroad s
Strang Yard to the north right of way of North P Street hereinafter referred to as the Projecf
and
WHEREAS it is to the mutual benefit of the District and the City to undertake the Project in order
to provide relief to the affected area and
WHEREAS the District and the City desire to share the cost of the Project and are each willing
to furnish funds for their respective commitments described herein and
WHEREAS in support of the Project the District is willing to administer the design and construction
of the Project at its own expense and
WHEREAS in support of the Project the City is willing to acquire additional right of way needed
to complete the Project and adjust all City owned utilities affected by the Project at its own
expense
NOW THEREFORE in consideration of the mutual covenants agreements and benefits to the
parties herein the parties agree as follows
e
ARTICLE I
The location of the Project is generally identified by the attached Exhibit A The Project is more
specifically defined by drawings prepared by landev Engineers Inc and extends from the west
line of the Union Pacific Railroad approximate station 78 00 to the north right of way line of North
P Street approximate station 11 00
ARTICLE II
The District shall coordinate preparation of the metes and bounds descriptions and tract maps
depicting the right of way acquisitions and construction plans and specifications The District shall
also administer bidding construction inspection materials testing and surveying for the Project
at the District s sole expense The District intends to bid and award construction of the Project in
the manner utilized by the District for similar projects and to award the contract in accordance with
applicable competitive bidding laws The District also is responsible for all pipeline relocations
ARTICLE III
The City agrees to acquire at its expense the tracts identified on the attached Exhibit A or suitable
alternatives The City further agrees to grant drainage easements to the District in a form approved
by both parties The City may request that the District obtain a portion of the Project right of way
for the City if the City notifies the District at least nine months before the start of construction If
the District agrees to obtain the right of way for the City the City shall pay the District for all right
of way costs within 30 days of receiving a cost statement from the District The District recognizes
that the City would like to retain the rights to utilize the right of way for other purposes such as but
not limited to landscaping pedestrianequestrian trails hike and bike trails and utility installations
which rights shall be subordinate to the District s right to use the right of way for drainage and flood
control purposes The City also agrees to relocate any City owned utilities affected by the Project
at the City s sole expense
ARTICLE IV
After the City has acquired the necessary right of way and after the City has conveyed drainage
easements to the District the District shall pursue the bidding and construction phase of the
Project The District agrees to utilize its best efforts to complete the Project within six months after
the date the easements are delivered to the District The District shall notify the City in writing of
the bid price of the Project within thirty 30 days after verifying and accepting a legal bid for the
Project
ARTICLE V
Either party may rescind this Agreement by giving thirty 30 days written notice to either party as
provided for in Article X of the Agreement if an acceptable bidder does not respond to the
advertisement fails to execute the construction contract or fails to provide the bonds required by
law
ARTICLE VI
The District shall have the right to make any changes in the plans and specifications it may deem
necessary or desirable during the construction of the Project in consultation with the City
However neither party shall be obligated to expend any funds in excess of those herein specifically
allocated for the Project as a result of any change in said plans or specifications except as
provided in Article VIII
2
e
ARTICLE VII
The City shall give the District the right and the District shall enter the property to maintain the
channel of Unit F101 00 00 after completion of the Project subject to the availability and
certification of funds The cost of such maintenance shall not be offset against the cost of the
Project
ARTICLE VIII
The City has been advised by the District and the City clearly understands and agrees that the
District shall have available the total maximum sum of 2 000 000 specifically allocated to fully
discharge any and all liabilities that may be incurred by the District pursuant to the terms of the
Agreement and that the total maximum sum the District shall become liable to pay hereunder shall
not under any conditions circumstances or interpretations hereof exceed the total maximum sum
provided for in this article and certified as available therefor by the County Auditor
Upon taking bids in the event the bid amount of the lowest and best bidder exceeds 2 000 000
the parties hereto shall have the following options
1 The District may after consultation with the City reject all bids and re advertise for bids
for the construction of the Project in accordance with the drawings and specifications
and in compliance with applicable compet tive bidding laws
2 At the option of either party the District shall reject all bids and elect not to proceed with
the letting of the construction contract and terminate this Agreement and the Project
without further obligation to the City or District unless otherwise specifically provided in
this Agreement
3 By amendment to this Agreement the parties may agree to share the additional cost
and proceed to let the construction contract and continue with the Project
4 By Agreement of the parties the District may amend the drawings and specifications
so as to reduce the scope of the Project and negotiate with the lowest qualified bidder
or re advertise for bids
If the parties fail to agree under which option to proceed within sixty 60 days after the opening of
bids then this Agreement shall terminate without further obligation to either party
ARTICLE IX
Neither the District nor the City shall make in whole or in part any assignment of this Agreement
or any obligation contained herein without the prior written consent of the other party
ARTICLE X
Notices and communications to either party under this Agreement shall be sent by certified mail
return receipt requested or delivered to the following respective addresses
DISTRICT Harris County Flood Control District
9900 Northwest Freeway
Houston Texas 77092
Attn Executive Director
3
CITY
e
City of La Porte
P O Box 1115
La Porte Texas 77572 1115
Attn Assistant City Manager
ARTICLE XI
This instrument contains the entire Agreement between the District and the City relating to the
rights herein granted and the obligations herein assumed and may only be amended by written
instrument of like dignity executed by the parties hereto
ARTICLE XII
This Agreement supersedes the Agreement of August 2 1988 and the terms of this Agreement
control if any provision conflicts with a similar provision in the August 2 1988 Agreement in
connection with this portion of the Project
IN WITNESS WHEREOF this instrument in multiple countergarts each havin force and effect
of any original has been executed by the parties on the 1 y day of fio 1998
ArrEST
APPROVED AS TO FORM
CITY OF LA PORTE
S T lc
City Manager
City of La Porte Texas
City Attorney
City of La Porte Texas
HARRIS COUNTY FLOOD CONTROL DISTRICT
4
e e
ORDER AUTHORIZING EXECUTION OF INTERLOCAL AGREEMENT BETWEEN
THE HARRIS COUNTY FLOOD CONTROL DISTRICT
AND THE CITY OF LA PORTE
THE STATE OF TEXAS I
I
COUNTY OF HARRIS S
On this the I day of 16r 1998 the
Commissioners Court of Harris County Texas silting as tm mJ dy of the Harris County
Flood Control District uprle motion of Commissioner seconded by
Commissioner tV tl l t
I duly put and carried
IT IS ORDERED that County Judge Robert Eckels be and he is hereby authorized to
execute for and on behalf of the Harris County Flood Control District an Interlocal Agreement with
the City of La Porte to provide interim improvements to Harris County Flood Control District Unit
Fl 01 00 00 for a maximum fee to be paid by the District of 2 000 000 said Agreement being
incorporated herein by reference for all purposes as though fully set forth verbatim herein
98EC004 WPD
Presented to Commllsion rs Coon
AUG 111998
APPROVE
Recorded Vol Page
EXHIBIT
A
F10l
OO
OO
WATERSHED
EXl5nNG
CHANNEL
S
II
PROPOSED
RIGHT
OF
WAY
ACQUISmON
1997
I
I
I
Ii
I
I
I
ii
I
E
BRINSONA
5
II
4
diL
u
Ii
I
Ii
Ji
Ji
Ji
Ji
II
I
OIl
iii
hH
t
II
or
1
u
Ii
e
Ii
II II
Ii
II
e
co pic
ORDINANCE NO 98 2262
AN ORDINANCE APPROVING AND AUTHORIZING AN INTERLOCAL AGREEMENT
BETWEEN THE CITY 01 LA PORTE AND THE BARRIS COUNTY PLOOD CONTROL
DISTRICT TO PROVIDE DRAINAGE IMPROVEMENTS POR THE BARRIS COUNTY
PLOOD CONTROL DISTRICT UNIT 1101 00 00 WATERSHED MAKING VARIOUS
PIRDINGS AND PROVISIONS RELATING TO THE SUBJECT PIRDING COMPLIANCE
WITH THE OPEN MEETINGS LAW AND PROVIDING AN EPFECTIVE DATE HEREOP
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LA PORTE
SectioD 1 The City Council hereby approves and authorizes
the contract agreement or other undertaking described in the
title of this ordinance in substantially the form as shown in the
document which is attached hereto and incorporated herein by this
reference The City Manager is hereby authorized to execute such
document and all related documents on behalf of the City of La
Porte The City Secretary is hereby authorized to attest to all
such signatures and to affix the seal of the City to all such
documents
SectioD 2 The City Council officially finds determines
recites and declares that a sufficient written notice of the date
hour place and subject of this meeting of the City Council was
posted at a place convenient to the pUblic at the City Hall of the
City for the time required by law preceding this meeting as
required by the Open Meetings Law Chapter 551 Texas Government
Code and that this meeting has been open to the public as required
by law at all times during which this ordinance and the subject
matter thereof has been discussed considered and formally acted
upon The City Council further ratifies approves and confirms
such written notice and the contents and posting thereof
SectioD 3 This Ordinance shall be effective from and after
its passage and approval and it is so ordered
e
ORDINANCE NO 98 2262
e
copy
PASSED AND APPROVED this 13th day of July 1998
ATTEST
MGMahaAGif ett
City Secretary
6KnoxWAsk1ns
City Attorney
By
CITY OF LA PORTE
N rma L Ma on
Mayor
PNZE 2