<br />Project Description
<br />
<br />Projected
<br />Cost
<br />
<br />Powell Road
<br />4 lane concrete roadway with curb and gutter and center median
<br />Length of roadway: 7,700 linear feet
<br />Lime stabilization: 41,100 sq. yds.
<br />Concrete paving: 10" thick; 41,100 sq. yds.
<br />Storm sewer: 3,850 linear feet
<br />Curb and gutter: 30,800 linear feet
<br />
<br />Powell Road South
<br />2 lane concrete roadway with curb and gutter
<br />Length of roadway: 2,200 linear feet
<br />Lime stabilization: 8,800 sq. yds.
<br />Concrete paving: 10" thick; 8,800 sq. yds.
<br />Storm sewer: 1,100 linear feet
<br />Curb and gutter: 4,400 linear feet
<br />
<br />McCabe Road (east of'SHI46)
<br />4 lane concrete roadway with curb and gutter
<br />Length of roadway: 4,300 linear feet
<br />Lime stabilization: 22,900 sq. yds.
<br />Concrete paving: 10" thick; 22,900 sq. yds.
<br />Storm sewer: 2,150 linear feet
<br />Curb and gutter: 8,600 linear feet
<br />
<br />McCabe Road (west of'SH146)
<br />2 lane concrete roadway with curb and gutter
<br />Length of roadway: 1,200 linear feet
<br />Lime stabilization: 4,800 sq. yds.
<br />Concrete paving: 10" thick; 4,800 sq. yds.
<br />Storm sewer: 600 linear feet
<br />Curb and gutter: 2,400 linear feet
<br />
<br />San Jacinto Street from Main to Park
<br />4 lane concrete roadway with curb and gutter
<br />Length of roadway: 4,700 linear feet
<br />Lime stabilization: 25,600 sq. yds.
<br />Concrete paving: 10" thick; 25,600 sq. yds.
<br />Storm sewer: 2,350 linear feet
<br />Curb and gutter: 9,400 linear feet
<br />
<br />Park Street from San Jacinto to Garfield
<br />2 lane concrete roadway with curb and gutter
<br />Length of roadway: 3,400 linear feet
<br />Lime stabilization: 13,600 sq. yds.
<br />Concrete paving: 7" thick; 13,600 sq. yds
<br />Storm sewer: 1,700 linear feet
<br />Curb and gutter: 6,800 linear feet
<br />
<br />Bayshore Drive
<br />2 lane concrete roadway with curb and gutter
<br />Length of roadway: 3,600 linear feet
<br />Lime stabilization: 13,600 sq. yds.
<br />Concrete paving: 7" thick; 13,600 sq. yds.
<br />Storm sewer: 1,700 linear feet
<br />Curb and gutter: 6,800 linear feet
<br />
<br />$ 3,000,000
<br />
<br />$ 1,170,000
<br />
<br />$ 2,200,000
<br />
<br />$ 605,000
<br />
<br />$ 2,400,000
<br />
<br />$ 1,700,000
<br />
<br />$ 1,700,000
<br />
<br />County
<br />Participation
<br />
<br />$1,000,000
<br />
<br />390,000
<br />
<br />733,000
<br />
<br />202,000
<br />
<br />800,000
<br />
<br />567,000
<br />
<br />567,000
<br />
|