<br />consultant and the contractor's representative to accurately determine the percentage completion <br />of various components of the work and time used. The entity, the consultant, and the contractor <br />will be required to sign each monthly estimate prior to being processed for payment. <br /> <br />9. All change orders must be approved in writing by the entity prior to any alterations or modifications <br />of the work or specifications. The entity will be responsible for any increase in cost based on any <br />change order required due to errors and/or omissions. Total aggregate Changes in Contract will <br />not exceed twenty five percent of the original contract amount. <br /> <br />10. Entity will submit or cause to be submitted, weekly payrolls for general contractor and all <br />subcontractors to HCOHED for review. HCOHED will review all payrolls and conduct worker <br />interviews and will hold the general contractor responsible for compliance with labor, EEO and <br />minority business requirements. The County through HCOHED reserves the right to withhold <br />funds from the general contractor to compensate workers in accordance with the appropriate <br />wage scales as promulgated by the U.S. Department of Labor. <br /> <br />11. The entity must submit the following documentation to HCOHED prior to award of the <br />construction contract: <br /> <br />}> Copy of the bid advertisement. <br />}> Copy of the bid tabulations. <br />}> Copies of all bids submitted. <br />}> Copies of bidders' bid bonds or cashiers checks. <br />}> Copy of the minutes and attendance roster of the bid opening. <br />}> Consultant's recommendation of contractor. <br />}> Request authorization from HCOHED to award project to lowest/best bidder. <br /> <br />12. The entity must submit the following documentation after award of contract: <br /> <br />}> Copy of the performance, payment and maintenance bonds. <br />}> Copy of "Certificate of Authority" issued by the State Board of Insurance of Texas for the surety <br />company. Only companies listed in the Department of the Treasury circular #570 (most recent issue) <br />will be accepted. <br />}> Certification of bid award by the City Council/Board. <br />}> Original copy of the executed contract between the successful bidder and the entity. <br />}> Copy of the purchase order. <br />}> Copy of subcontractor list. <br />}> Schedule of values based on standard Construction Specifications Institute (CSI) format (16 divisions) <br />and given in labor and materials listed separately per line item including overhead and profit for each. <br />}> Construction schedule (Bar Chart or Critical Path Method). <br /> <br />13. The entity will not be permitted to perform any "force account work", wherein the entity uses their <br />own employees, materials, and/or equipment. All portions of construction work will be subject to <br />the competitive bidding process referenced above. <br /> <br />14. The entity's contractor shall furnish, deliver, and install one 4'-0" X 8'-0" temporary project sign <br />according to Harris County specifications. The entity will ensure that the specifications will be <br />made part of the project manual and the cost of the project sign will be included in all bids. <br /> <br />15. The entity's contractor, on all buildinq projects, shall furnish, deliver, and install one 18" X 24" <br />bronze plaque built according to Harris County specifications. The entity will ensure that the <br />specifications will be made part of the project manual and the cost of the plaque will be included in <br />all bids. <br /> <br />23 <br />