HARRIS COUNTY, TEXAS
<br />ENGINEERING COST ESTIMATE
<br />LEFT TURN LANE CONSTRUCTIONS AT THE INTERSECTIONS OF FAIRMONT PARKWAY (22583-3-4)
<br />AT BROOKWOOD DRIVE, WILMONT DRIVE, AND FARRINGTON BOULEVARD
<br />IN HARRIS COUNTY, PRECINCT 2
<br />KLOTZ ASSOCIATES PROJECT NO.11678
<br />BIID TABULATION SHEET
<br />ITEM
<br />NO.
<br />SPEC
<br />ITEM NO.
<br />I QUAN.
<br />UNIT
<br />BID ITEM DESCRIPTION
<br />AAA Asphalt Paving, Inc.
<br />Pedko Paving, Inc.
<br />Silva, Inc.
<br />. UNIT
<br />PRICE
<br />AMOUNT
<br />BID
<br />UNIT
<br />PRICE
<br />AMOUNT
<br />BID
<br />UNIT
<br />PRICE.
<br />AMOUNT
<br />BID
<br />A. SITE PREPARATION AND EARTHWORK ITEMS
<br />1
<br />110 •
<br />1,612
<br />CY
<br />lRoadway excavation
<br />$14.00
<br />$22,568.00
<br />$18.00
<br />$29,016.00
<br />$15.75
<br />$25,389.00
<br />2
<br />165
<br />1.5
<br />AC.
<br />Hydro mulch seeding
<br />$3,000.00
<br />$4,500.00
<br />$1,500.00
<br />$2,250.00
<br />$1,000.00
<br />$1,500.00
<br />3
<br />562
<br />3
<br />1
<br />LS
<br />Right of way preparation
<br />$3,000.00 •
<br />$9,000.00
<br />$200.00
<br />$600.00
<br />$2,170.00
<br />$6,510.00
<br />4
<br />540
<br />920
<br />SY
<br />lRemoving existing asphalt pavement and base (all depths)
<br />$10.00
<br />$9,200.00
<br />$2.50
<br />$2,300.00
<br />$8.00
<br />$7,360.00
<br />SUBTOTAL A. SITE PREPARATION AND EARTHWORK ITEMS
<br />$45,268.00
<br />$34,166.00
<br />$40,759.00
<br />B. PAVEMENT ITEMS
<br />5
<br />220
<br />3,450
<br />SY
<br />Lime manipulation of subgrade
<br />$6.00
<br />$20,700.00
<br />$6.00
<br />$20,700.00
<br />$4.10
<br />$14,145.00
<br />6
<br />221
<br />83.4
<br />TON
<br />Hydrated lime and lime slurry for subgrade stabilization (7%)
<br />$110.00
<br />$9,174.00
<br />$100.00
<br />$8,340.00
<br />$94.50
<br />$7,881.30
<br />7
<br />250
<br />2,233.7
<br />TON
<br />Hot -mix asphalt concrete base course, (12" black base) for
<br />roadway pavements
<br />$43.00
<br />$96,049.10
<br />$42.00
<br />$93,815.40
<br />$39.20
<br />$87,561.04
<br />$
<br />250
<br />465.4
<br />TON
<br />Hot -mix asphaltic concrete surfacing (2.5" depth) for surface
<br />and overlay pavements
<br />$40.00
<br />$18,616.00
<br />$66.00
<br />$30,716.40
<br />$48.50
<br />$22,571.90
<br />SUBTOTAL B. PAVEMENT ITEMS
<br />$144,539.10
<br />$153,571.80
<br />$132,159.24
<br />C. TRAFFIC CONTROL ITEMS
<br />9
<br />624
<br />4
<br />MO
<br />Traffic control
<br />$5,000.00
<br />$20,000.00
<br />$2,500.00
<br />$10,000.00
<br />$9,000.00
<br />$36,000.00
<br />10
<br />665
<br />8,510
<br />LF
<br />Work zone pavement markings, white 4" width
<br />$1.50
<br />$12,765.00
<br />$0.65
<br />$5,531.50
<br />$1.36
<br />$11,573.60
<br />11
<br />665
<br />160
<br />LF
<br />Work zone pavement markings, white 24" width
<br />$7.00
<br />$1,120.00
<br />$6.20
<br />$992.00
<br />$6.12
<br />$979.20
<br />12.
<br />665
<br />4,260
<br />LF
<br />Work zone pavement markings, yellow 4" width
<br />$1.50
<br />$6,390.00
<br />$O.GS
<br />$2,769.00
<br />$1.36
<br />$5,793.60
<br />13
<br />250
<br />.67
<br />TON
<br />Hot -mix asphalt concrete pavement, (12" black base) for
<br />temporary detour pavements
<br />$50.00
<br />$3,350.00
<br />$50.00
<br />$3,350.00
<br />$100.00
<br />$6,700.00
<br />SUBTOTAL C. TRAFFIC CONTROL ITEMS
<br />$43,625.00
<br />$22,642.50
<br />$61,046.40
<br />D. STORM WATER POLLUTION PREVENTION ITEMS
<br />14
<br />724
<br />210 1
<br />SY
<br />Stabilized construction zccess (Type I - Rock)
<br />$20.00
<br />$4,200.00
<br />$9.00
<br />$1,890.00
<br />$18.20
<br />$3,822.00
<br />15
<br />713
<br />1,200 1
<br />LF lReinforced
<br />filter fabric barrier with staking
<br />$2.00
<br />$2,400.00
<br />$1.50
<br />$1,800.00
<br />$2.30
<br />$2,760.00
<br />SUBTOTAL D. STORM WATER POLLUTION PREVENTION ITEMS'
<br />$6,600.00
<br />$3,690.00
<br />$6,582.00
<br />T, 11/26/2003 Page I bid tabulation FAIRMON'r