Lomax Area Lift Station Consolidation Project
<br />City of La Pone
<br />Final Design Phase
<br />90% Submittal - O inion of Probable Construction Costs
<br />Item I Item Description Unit I Quantit Unit Price Cost
<br />LIFT STATION AND FORCE MAIN BID ITEMS:
<br />1
<br />Proposed lift station
<br />1a
<br />MCC Building, complete in place, the sum of:
<br />LS
<br />1
<br />$120,000,00
<br />$120,000
<br />Installation of 14` diameter wet well by caisson construction
<br />(precast or cast -in -place), including stainless steel guide rails,
<br />triplex analog control panel with float backup in stainless steel
<br />enclosure, three (3) aluminum access hatches, safety netting,
<br />1b
<br />lift station piping & valves as shown in mechanical plan and
<br />LS
<br />1
<br />$718,440.00
<br />$718,440
<br />section drawings, combination air release valvelvaccuum
<br />valve on header piping, piping supports and thrust blocking, air
<br />vent piping, site work including, fencing, fence gates, concrete
<br />pad for heading piping, and all work as shown on Plans and
<br />described in Specifications, complete in place, the sum of:
<br />1c
<br />Flygt 70 hp Pumps, complete in place, the sum of:
<br />EA.
<br />3
<br />$55,000.00
<br />$165,000
<br />Site Concrete including C-inch concrete curb including ground
<br />1d
<br />leveling, reinforcement, joints, joint sealant, excavation, curing,
<br />SY
<br />300
<br />$100.00
<br />$30,000
<br />complete in place, the sum of:
<br />Electrical System Installation: Provide and install all work
<br />shown on Plans and described in Specifications including as
<br />follows: Provide and install motor control center, odor control
<br />system, automatic transfer switch, lighting and receptacles,
<br />2
<br />pump motor feeders and terminal boxes, electrical service
<br />LS
<br />1
<br />$696,560.00
<br />$696,560
<br />equipment, autosensory controls, telephone service, and all
<br />required appurtenances as shown on Plans and as described
<br />in Specifications for a complete operating system, complete in
<br />place, the sum of:
<br />Lift Station Controller Programming: Allowance for lift station
<br />3
<br />controller programming per Specification Section 16904 -
<br />LS
<br />1
<br />$22,500.00
<br />$22,500
<br />"Controller", complete in place, the sum of:
<br />Lift Station Electric Service: Allowance for electric service by
<br />4
<br />the local Electric Service Provider. Exact amount to be
<br />LS
<br />1
<br />$20,000.00
<br />$20,000
<br />reimbursed to the Contractor upon submittal of invo, ice from
<br />the Electric Service Provider, complete in place, the sum of:
<br />5
<br />Deep well pointing for proposed lift station, complete in place,
<br />EA.
<br />1
<br />$12,000.00
<br />$12,000
<br />the sum of:
<br />Proposed 1-inch long side water service connection to lift
<br />6
<br />station site, including service tap, 1-inch meter, reduced
<br />LS
<br />1
<br />$7,500.00
<br />$7,500
<br />pressure backflow preventer, and hose bib as per details,
<br />com fete in place, the sum of:
<br />Demolish existing lift station including salvage of existing
<br />7
<br />equipment and demolition of the existing structure per details,
<br />EA.
<br />6
<br />$15,000.00
<br />$90,000
<br />complete in place, the sum of:
<br />
|