Abandon existing lift station and convert wet well to sanitary
<br />sewer manhole, including salvage of existing equipment, Filling
<br />8
<br />lift station bottom with grout to lowest invert level, connecting
<br />EA.
<br />3
<br />$20,000.00
<br />$60,000
<br />new sanitary sewer lateral into manhole, and precast concrete
<br />transition slab with new manhole lid, ring, cover, and cone
<br />section, complete in place, the sum of:
<br />Remove existing sanitary sewer force main, all sizes and
<br />L.F.
<br />3,1D0
<br />$17.00
<br />$52,700
<br />depths, complete in lace, the sum of:
<br />10
<br />Cut, plug, and abandon existing sanitary sewer Force main,
<br />EA.
<br />13
<br />$500.00
<br />$6,500
<br />complete in place, the sum of:
<br />11
<br />12" C900 PVC san swr force main, complete in place, the sum
<br />L. F
<br />8,100
<br />$150.00
<br />$1,215,000
<br />0
<br />12
<br />1complete
<br />12" C900 PVC san swr force main w120" steel casing (Auger),
<br />L. F
<br />200
<br />$250.00
<br />$50,000
<br />in place, the sum of:
<br />13
<br />Connect 12" C900 PVC san swr force main to existing
<br />EA.
<br />1
<br />$14,000.00
<br />$14,000
<br />manhole, complete in place, the sum of:
<br />14 lAir
<br />Release Valve Manhole, complete in place, the sum of:
<br />EA.
<br />10
<br />$5,000.00
<br />$50,000
<br />15
<br />6" C900 PVC san swr force main (Auger), complete in place,
<br />L.F.
<br />530
<br />$50.00
<br />$26,500
<br />the sum of:
<br />16
<br />8" C900 PVC san swr force main (Auger), complete in place,
<br />L.F.
<br />1,350
<br />$75.00
<br />$101,250
<br />the sum of:
<br />Remove and replace 4" thick reinforced concrete
<br />17
<br />sidewalk/walkway, all widths, with compact subgrade,
<br />S.F.
<br />300
<br />$10.00
<br />$3,000
<br />,complete in place, the sum of:
<br />18
<br />Remove and dispose wooden pedestrian bridge, complete in
<br />EA.
<br />1
<br />$1,500.00
<br />$1,500
<br />lace, the sum of:
<br />19
<br />Remove and replace chain link fence, complete in place, the
<br />L.F.
<br />30
<br />$40.00
<br />$1,200
<br />sum of:
<br />Remove and replace existing sidewalk curb ramp in
<br />20
<br />conformance with ADA standards, complete in place, the sum
<br />EA.
<br />1
<br />$2,000,00
<br />$2,000
<br />of:
<br />Connect proposed 12-inch sanitary sewer force main to
<br />21
<br />proposed 8-inch force main from Lift Station 10, complete in
<br />EA.
<br />1
<br />$14,000.00
<br />$14,000
<br />lace, the sum of:
<br />22
<br />Connect proposed sanitary sewer force main to existing force
<br />EA.
<br />1
<br />$1,500.00
<br />$1,500
<br />main at Lift Station 26, complete in place, the sum of:
<br />Lift Station and Force Main Items Total:
<br />$3 481 150
<br />SANITARY SEWER BID ITEMS:
<br />23
<br />Remove existing sanitary sewer gravity main, all sizes and
<br />L.F.
<br />20,000
<br />$17.00
<br />$340,000
<br />depths, complete in place, the sum of:
<br />24
<br />Remove existing sanitary manhole, complete in place, the sum
<br />EA.
<br />67
<br />$550.00
<br />$38,850
<br />o
<br />25
<br />12" PVC sanitary sewer pipe ASTM D3034 SDR26, all depths
<br />L.F.
<br />3,550
<br />$95.00
<br />$337,250
<br />(Open Cut), complete in place, the sum of:
<br />26
<br />12" PVC sanitary sewer pipe ASTM D3034 SDR26 w120" Steel
<br />L,F,
<br />35D
<br />$300.00
<br />$105,000
<br />Casing, all depths (Auger), complete in place, the sum of:
<br />27
<br />115" PVC sanitary sewer pipe ASTM D3034 SDR26, all depths
<br />L. F
<br />3 120
<br />$105 00
<br />$327,600
<br />(Open Cut), complete in place, the sum of:
<br />28
<br />18" PVC sanitary sewer pipe ASTM F679 PS115, all depths
<br />I(Open
<br />L. F.
<br />8,100
<br />$115.00
<br />$931,500
<br />Cut), complete in place, the sum of:
<br />29
<br />18" PVC sanitary sewer pipe ASTM F679 PSI 15 w130" Steel
<br />L. F
<br />640
<br />$450.00
<br />$288,000
<br />Casing, all depths (Auger), complete in place, the sum of:
<br />30
<br />21" PVC sanitary sewer pipe ASTM F679 PSI 15, all depths
<br />L. F.
<br />1 5,200
<br />$135.00
<br />$702,000
<br />(Open Cut), complete in place, the sum of: